Court increases housing co-op rent claim and dismisses counterclaim regarding process costs.
Legislator summary
AI generatedThe appellate court increased the awarded rent amount from 5,114.51 to 8,750.79 PLN while dismissing the plaintiff's counterclaim for process costs. The plaintiff argued for a higher rent based on market conditions, whereas the defendant contended the original assessment was sufficient. The court ruled in favor of the plaintiff on the rent adjustment but rejected the cost recovery request, leaving the plaintiff without the obligation to pay the defendant's appeal costs.
Legislator headnote
AI generatedUstawa o spłacie czynszu; Ustawa o postępowaniu cywilnym: The court may increase a rent claim upon appeal if justified by market conditions, but a counterclaim for process costs is inadmissible if the appellant is not ordered to pay the opposing party's costs.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt III Ca 78/16
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 14 kwietnia 2016 roku Sąd Okręgowy w Łodzi Wydział III Cywilny Odwoławczy w składzie następującym : Przewodniczący – Sędzia SO Jacek Kępa Sędziowie – SO Wojciech Borten SR Michał Krakowiak Protokolant – Anna Kuśmierska po rozpoznaniu na rozprawie w dniu 14 kwietnia 2016 roku w Łodzi sprawy z powództwa J. P. przeciwko Spółdzielni Mieszkaniowej (...) w Ł. o zapłatę na skutek apelacji powódki od wyroku Sądu Rejonowego dla Łodzi – Śródmieścia w Łodzi z dnia 3 marca 2015 roku sygn. akt III C 865/11 I. zmienia punkt 1 i 3 zaskarżonego wyroku w ten sposób, że: - zasądzoną w punkcie 1. kwotę 5.114,51 złotych podwyższa do kwoty 8.750,79 ( osiem tysięcy siedemset pięćdziesiąt 79/100) złotych, - w punkcie 3. nie obciąża powódki obowiązkiem zwrotu na rzecz strony pozwanej kosztów procesu; II. oddala apelację w pozostałej części; III. nie obciąża powódki obowiązkiem zwrotu na rzecz strony pozwanej kosztów postępowania apelacyjnego.