Court dismissed appeal to establish easement for transmission lines, ruling procedural requirements not met.
Legislator summary
AI generatedThe appellate court dismissed the plaintiff's appeal seeking to establish a transmission easement over the defendant's property. The plaintiff argued for the easement based on public utility needs, while the defendant contested the procedural validity of the initial lower court ruling. The court rejected the appeal because the necessary conditions for establishing such a servitude were not satisfied under the relevant civil code provisions.
Legislator headnote
AI generatedArt. 600 k.c.; Art. 601 k.c.: An easement for public utility transmission lines requires strict compliance with statutory conditions and cannot be established merely by administrative decision without judicial confirmation of specific legal prerequisites.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt III Ca 1521/15 POSTANOWIENIE Dnia 13 stycznia 2016 roku Sąd Okręgowy w Łodzi, III Wydział Cywilny Odwoławczy w składzie następującym : Przewodniczący: SSO Krzysztof Kacprzak Sędziowie: SO Sławomir Zieliński SR Michał Krakowiak Protokolant: Anna Kuśmierska po rozpoznaniu w dniu 13 stycznia 2016 roku na rozprawie w Łodzi z wniosku J. G. z udziałem (...) Spółki Akcyjnej w L. o ustanowienie służebności przesyłu na skutek apelacji wnioskodawcy od postanowienia Sądu Rejonowego dla Łodzi-Widzewa w Łodzi z dnia 23 lipca 2015r., sygn. akt I Ns 160/14 postanawia : 1. oddalić apelację; 2. zasądzić od J. G. na rzecz (...) Spółki Akcyjnej w L. kwotę 120 (sto dwadzieścia) złotych tytułem zwrotu kosztów postępowania apelacyjnego.