Court partially allowed appeal to increase necessary road cost from 4,595 to 6,340 PLN.
Legislator summary
AI generatedThe Court of Appeal partially reversed the lower court's decision regarding the necessary road construction costs. The plaintiffs successfully argued for an increase in the awarded sum from 4,595 PLN to 6,340 PLN, while the appeal was dismissed on all other points. Consequently, the court ordered the specific cost adjustment and allocated procedural expenses to each party.
Legislator headnote
AI generatedUstawa o drogach publicznych; Ustawa o kosztach postępowania: The court may partially modify a necessary road cost determination upon appeal if the evidence supports a higher reasonable amount, while dismissing unrelated claims.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt III Ca 1669/15 POSTANOWIENIE Dnia 9 lutego 2016 roku Sąd Okręgowy w Łodzi, III Wydział Cywilny Odwoławczy w składzie następującym : Przewodniczący: SSO Sławomir Zieliński Sędziowie: SO Elżbieta Gawryszczak SR Małgorzata Nowak Protokolant: Monika Bura po rozpoznaniu w dniu 9 lutego 2016 roku na rozprawie w Łodzi z wniosku M. C. (1) i M. C. (2) z udziałem (...) Państwowych Spółki Akcyjnej w W., Miasta Ł., Skarbu Państwa - Prezydenta Miasta (...) Spółki Akcyjnej w W. o ustanowienie drogi koniecznej na skutek apelacji uczestnika (...) Państwowych Spółki Akcyjnej w W. od postanowienia Sądu Rejonowego dla Łodzi - Widzewa w Łodzi z dnia 24 sierpnia 2015 roku sygn. akt I Ns 65/13 postanawia : 1. zmienić zaskarżone postanowienie w punkcie 2. w ten tylko sposób, że kwotę 4.595 zł podwyższyć do kwoty 6.340 (sześć tysięcy trzysta czterdzieści ) zł; 2. oddalić apelację w pozostałej części; 3. ustalić, iż każdy z uczestników ponosi koszty postępowania apelacyjnego związane ze swoim udziałem w sprawie.