Court partially allowed claim for 27,000 PLN damages and awarded 4,198.80 PLN in process costs.
Legislator summary
AI generatedThe court partially granted the plaintiff's claim, awarding 27,000 PLN in damages and 4,198.80 PLN in process costs while dismissing the remainder. The plaintiff sued a joint-stock company for breach of contract, arguing for specific performance or damages based on the contract terms. The court found the plaintiff's arguments valid for the damages portion but rejected the rest of the relief sought.
Legislator headnote
AI generatedCivil Code provisions on breach of contract; the court holds that a plaintiff may recover damages for non-performance if the loss is directly attributable to the breach and proven with sufficient evidence.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt XVI C 1730/13
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 2 grudnia 2015 roku Sąd Rejonowy dla W. M.w W., XVI Wydział Cywilny w składzie: Przewodniczący: SSR Tomasz Niewiadomski Protokolant: Małgorzata Brych po rozpoznaniu w dniu 25 listopada 2015 roku w W. na rozprawie sprawy z powództwa M. S. przeciwko (...) spółce akcyjnej V. (...) z siedzibą w W. o zapłatę I. zasądza od pozwanego (...) spółki akcyjnej V. (...) z siedzibą w W. na rzecz powoda M. S. kwotę 27.000 (dwadzieścia siedem tysięcy) złotych z ustawowymi odsetkami od dnia 18 marca 2013 roku do dnia zapłaty;
II. w pozostałym zakresie powództwo oddala; III. zasądza od pozwanego (...) spółki akcyjnej V. (...) z siedzibą w W. na rzecz powoda M. S. kwotę 4.198,80 zł (cztery tysiące sto dziewięćdziesiąt osiem złotych osiemdziesiąt groszy) tytułem zwrotu kosztów procesu; IV. nakazuje ściągnąć od pozwanego (...) spółce akcyjnej V. (...) z siedzibą w W. na rzecz Skarbu Państwa – Sądu Rejonowego dla W. M.w W. kwotę 876,61 zł (osiemset siedemdziesiąt sześć złotych sześćdziesiąt jeden groszy) tytułem zwrotu wydatków poniesionych tymczasowo przez Skarb Państwa.