Court allows damages for building collapse due to faulty excavation but dismisses interest claims for the extended period.
Legislator summary
AI generatedThe court awarded the plaintiffs 205,000 PLN in damages for a building collapse caused by the defendant's improper excavation work. While the liability for the physical damage was confirmed, the court rejected the plaintiffs' request for interest calculated from the original filing date for the additional amount claimed later. The judgment established that interest on the expanded claim only runs from the date the claim was formally amended, while costs were assigned to the losing party.
Legislator headnote
AI generatedArt. 481 § 1 k.c.; Art. 113 ust. 1 u.k.s.c.: The court held that while the obligor is liable for damages caused by non-compliance with construction standards, interest on an expanded claim is only calculable from the date of the amendment, not from the original filing date.