Court partially allows debt claim for 1053.25 PLN while dismissing remaining claims and splitting costs.
Legislator summary
AI generatedThe court partially granted the plaintiff's claim for payment, awarding 1053.25 PLN plus contractual interest while dismissing the remainder of the suit. The plaintiff, a limited liability company, sued Ł. W. for unpaid debts, arguing specific contractual breaches, whereas the defendant contested the full amount. The court decided to support the proven debt portion but rejected the rest, resulting in a split of procedural costs.
Legislator headnote
AI generatedCivil Code provisions on debt collection; the court holds that partial performance of a claim does not invalidate the entire action, allowing recovery of proven amounts while dismissing unproven requests.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 386/15 WYROK ZAOCZNY W IMIENIU RZECZYPOSPOLITEJ POLSKIEJ Dnia 19 maja 2015 r. Sąd Rejonowy w Suwałkach I Wydział Cywilny w składzie następującym: Przewodnicząca: SSR Agnieszka Kluczyńska Protokolant: Magda Ułanowicz po rozpoznaniu w dniu 19 maja 2015 r. w Suwałkach sprawy z powództwa BUSINESS (...) spółka z ograniczoną odpowiedzialnością z siedzibą w S. przeciwko Ł. W. o zapłatę I. Zasądza od pozwanego Ł. W. na rzecz powoda BUSINESS (...) spółka z ograniczoną odpowiedzialnością z siedzibą w S. kwotę 1053,25 zł (jeden tysiąc pięćdziesiąt trzy złote 25/100) z odsetkami umownymi w wysokości 4 – krotności stopy kredytu lombardowego NBP od dnia 27 października 2014 roku do dnia zapłaty;
II. Oddala powództwo w pozostałym zakresie. III. Koszty postepowania pomiędzy stronami stosunkowo rozdziela i zasądza od pozwanego Ł. W. na rzecz powoda BUSINESS (...) spółka z ograniczoną odpowiedzialnością z siedzibą w S. kwotę 376,20 zł (trzysta siedemdziesiąt sześć złotych 20/100) tytułem zwrotu kosztów postępowania; IV. Wyrokowi w pkt I i III nadaje rygor natychmiastowej wykonalności.