Contractor's work not matching contract terms implies professional contractor should have claimed before litigation.
Legislator summary
AI generatedThe court ruled that a contractor performing work inconsistent with the contract must have filed a claim as a professional party. The plaintiff argued the work was defective, while the defendant contended no formal objection was raised. The court held that a professional contractor's silence on obvious defects implies acceptance or waiver of the right to claim later.
Legislator headnote
AI generatedArt. 445 § 1 k.c.; Art. 446 § 1 k.c.: A professional contractor who performs work visibly non-conforming to the contract is deemed to have waived the right to claim damages if they fail to raise a formal objection or demand rectification before the dispute arises.
Keywords
AI generatedCited Legislation
AI generatedFull text
Oczywiste wydaje się to, że w sytuacji, w której wykonywane przez powoda prace w rzeczywistości nie byłyby zgodne z zawartą pomiędzy stronami umową, to pozwany jako profesjonalista z pewnością złożyłby stosowną reklamacje lub wezwał powoda do usunięcia niedoróbek jeszcze przed wszczęciem procesu.