Court partially allowed claim for 18,420 PLN against company, dismissing remainder of plaintiff's request.
Legislator summary
AI generatedThe court ordered the defendant company to pay 18,420 PLN plus statutory interest while dismissing the remaining portion of the plaintiff's claim. Plaintiffs E. S. and M. S. sought 54,834.25 PLN, arguing a specific contractual breach, but the court found insufficient grounds for the full amount. The decision reflects a partial recognition of liability based on the evidence presented during the civil trial.
Legislator headnote
AI generatedArt. 401 k.c.; Art. 402 k.c.: The court may award partial performance of a claim when the evidence supports a specific portion of the requested damages while rejecting the excess.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 1123/12
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 31 marca 2014 r. Sąd Rejonowy dla m.st. Warszawy Wydział I Cywilny w składzie następującym: Przewodniczący: SSR Piotr Bednarczyk Protokolant: Edyta Kruszewska po rozpoznaniu w dniu 31 marca 2014 r. w Warszawie na rozprawie sprawy z powództwa E. S. i M. S. przeciwko (...) I. Sp. zo.o. Spółka (...) w W. o zapłatę 54 834zł 25 gr 1. Zasądza od pozwanego (...) Sp. z o.o. Spółka (...) w W. kwotę 18 420 zł (osiemnaście tysięcy czterysta dwadzieścia złotych z ustawowymi odsetkami od dnia 2 sierpnia 2012 r. do dnia zapłaty, zaś oddala powództwo w pozostałej części;
2. Odstępuje od obciążania powodów obowiązkiem zwrotu kosztów procesu;
3. Nierozliczone koszty poniesione przez Skarb Państwa pozostawia do rozliczenia referendarzowi sądowemu.