Court dismissed appeal to establish easement for pipeline crossing private property without consent.
Legislator summary
AI generatedThe Court of Appeal in Łódź dismissed the appellant's request to establish a servitude for pipeline transmission. The appellant argued that a pipeline crossing their land required a legal easement, while the respondent maintained no such right existed. The court rejected the claim because the necessary conditions for establishing a servitude were not met.
Legislator headnote
AI generatedUstawa o służebnościach; Ustawa o drogach publicznych: The court established that a servitude for pipeline transmission cannot be established without explicit consent or statutory authorization, and the burden of proof lies with the applicant.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt III Ca 1789/13 POSTANOWIENIE Dnia 4 lutego 2015 r. Sąd Okręgowy w Łodzi Wydział III Cywilny Odwoławczy w składzie następującym : Przewodniczący – Sędzia SO Sławomir Zieliński Sędziowie : SO Jacek Kępa , SR Joanna Szczygielska Protokolant: Anna Kuśmierska po rozpoznaniu na rozprawie w dniu 4 lutego 2015 r. w Łodzi sprawy z wniosku K. Ś. z udziałem (...) S.A. w K. o ustanowienie służebności przesyłu na skutek apelacji wnioskodawcy od postanowienia Sądu Rejonowego dla Łodzi-Widzewa w Łodzi z dnia 8 października 2013 r. sygn. akt I Ns 20/13 p o s t a n a w i a : 1. oddalić apelację; 2. ustalić, iż uczestnicy ponoszą koszty postępowania apelacyjnego zgodnie ze swoim udziałem w sprawie.