Legislator Case Law & Legislation
I C 1076/14 AI generated

Court orders company to pay city damages for breach of contract and process costs.

Case Number I C 1076/14
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The court ruled in favor of the company, ordering the city to pay over 388,000 zloty in damages plus 26,000 zloty in process costs. The plaintiff argued that the city failed to fulfill contractual obligations, causing financial loss. The court found the city liable for the breach and granted the full claim with statutory interest.

Legislator headnote

AI generated

Civil Code provisions on breach of contract; A party failing to perform contractual obligations is liable for damages and must bear the costs of the proceedings.

Keywords

AI generated
breach of contract damages award process costs civil liability statutory interest

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt IC 1076/14

WYROK W IMIENIU

RZECZYPOSPOLITEJ POLSKIEJ Dnia 28 stycznia 2015 roku Sąd Okręgowy w Piotrkowie Trybunalskim, Wydział I Cywilny w składzie następującym: Przewodniczący Sędzia SO Wojciech Rychliński Protokolant Sekr. sąd. Mariola Budzisz po rozpoznaniu w dniu 14 stycznia 2015 roku w Piotrkowie Trybunalskim na rozprawie sprawy z powództwa (...) Spółki z o.o. przeciwko Miastu P. o zapłatę 1. zasądza od pozwanego Miasta P. na rzecz powoda (...) Spółki z o.o. kwotę 388.070,60 (trzysta osiemdziesiąt osiem tysięcy siedemdziesiąt i 60/100) złotych z ustawowymi odsetkami od 1 stycznia 2014 roku;

2. zasądza od pozwanego Miasta P. na rzecz powoda (...) Spółki z o.o. kwotę 26.621 (dwadzieścia sześć tysięcy sześćset dwadzieścia jeden) złotych tytułem zwrotu kosztów procesu.