Court partially allows city's claim for damages against two defendants regarding unpaid fees and procedural costs.
Legislator summary
AI generatedThe court ordered the two defendants to jointly pay the city 30,298.53 zł in damages with statutory interest, while dismissing the remainder of the claim. The plaintiffs argued for full compensation for unpaid fees and costs, whereas the defendants contested the full liability amount. The court ruled that the specific damages were proven but rejected the excessive portion of the requested sum.
Legislator headnote
AI generatedUstawa o postępowaniu w sprawach gospodarczych; Ustawa o odpowiedzialności za szkody; The court partially supports a claim for damages when the proven loss is less than the total amount requested by the plaintiff.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt: IX GC 2292/12
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ W., dnia 20 marca 2014 r. Sąd Rejonowy dla m. st. Warszawy w W. Sąd Gospodarczy IX Wydział Gospodarczy w składzie następującym: Przewodniczący: SSR Grzegorz Babiński Protokolant: Agnieszka Kubik po rozpoznaniu w dniu 6 marca 2014 r. w Warszawie na rozprawie sprawy z powództwa Miasta S. W. przeciwko T. L., P. L. o zapłatę kwoty 62 316,03 zł I. zasądza solidarnie od T. L. i P. L. na rzecz Miasta S. W. kwotę 30 298,53 zł (trzydzieści tysięcy dwieście dziewięćdziesiąt osiem złotych pięćdziesiąt trzy grosze) z ustawowymi odsetkami od dnia 19 kwietnia 2012 r. do dnia zapłaty; II. w pozostałej części powództwo oddala; III. zasądza solidarnie od T. L. i P. L. na rzecz Miasta S. W. kwotę 1398,17 zł (jeden tysiąc trzysta dziewięćdziesiąt osiem złotych siedemnaście groszy) tytułem kosztów procesu.