Court orders municipality to pay town association damages for unpaid compensation and process costs.
Legislator summary
AI generatedThe court ruled in favor of the municipal district against the town association, ordering payment of 13,084.50 PLN for unpaid compensation plus statutory interest. The plaintiff argued the defendant failed to fulfill its financial obligations, while the defendant contested the amount due. The court found the defendant liable for the breach and awarded both the principal sum and procedural costs.
Legislator headnote
AI generatedUstawa o finansach publicznych; Ustawa o samorządzie gminnym: The court must order payment of outstanding compensation and award process costs when a public entity fails to fulfill its financial obligations to another public body.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 1367/13
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 17 marca 2014 roku Sąd Rejonowy w Dzierżoniowie I Wydział Cywilny w składzie: Przewodniczący: SSR Leszek Kawecki Protokolant: Małgorzata Woś po rozpoznaniu w dniu 17 marca 2014 roku w Dzierżoniowie sprawy z powództwa Gminy Miejskiej D. przeciwko (...) Towarzystwu (...) w W. o zapłatę kwoty 13 084,50 zł I/ zasądza od strony pozwanej (...) Towarzystwa (...) w W. na rzecz strony powodowej Gminy Miejskiej D. kwotę 13 084,50 zł (trzynaście tysięcy osiemdziesiąt cztery złote pięćdziesiąt groszy) z odsetkami ustawowymi od dnia 16 października 2012 roku do dnia zapłaty; II/ zasądza od strony pozwanej na rzecz strony powodowej kwotę 3 072 zł tytułem zwrotu kosztów procesu. Zarządzenie:
1) odnotować;
2) kal. 21 dni. 17.03.2014 r.