I C 251/13 AI generated

Court orders payment of 15,000 PLN plus interest and 3,486.70 PLN process costs to plaintiff.

Case Number I C 251/13
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The court ruled in favor of the plaintiff, ordering the defendant to pay 15,000 PLN plus statutory interest and 3,486.70 PLN in process costs. The plaintiff successfully claimed compensation for damages and legal expenses incurred during the proceedings. Consequently, the defendant was held liable for the full amount requested by the plaintiff.

Legislator headnote

AI generated

Civil Code provisions on damages and litigation costs: The court must award the full amount of proven damages and process costs to the prevailing party when the defendant fails to justify the claim.

Keywords

AI generated
civil damages claim litigation costs recovery statutory interest award plaintiff prevailing party court liability order

Cited Legislation

AI generated
Civil Code of the Republic of Poland
Act on the Organization of Courts

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt I C 251/13

WYROK W IMIENIU

RZECZYPOSPOLITEJ POLSKIEJ Dnia 22 stycznia 2014 roku Sąd Rejonowy w Brzegu I Wydział Cywilny w składzie następującym : Przewodnicząca: SSR Joanna Kurowska Protokolant: Anna Siłka po rozpoznaniu w 15 stycznia 2014 roku w Brzegu na rozprawie sprawy z powództwa I. C. przeciwko C. T..U. S.A. (...) w W. o zapłatę I. zasądza od pozwanego C. T..U. S.A. (...) w W. na rzecz powódki I. C. kwotę 15.000 zł ( piętnaście tysięcy złotych) z ustawowymi odsetkami od dnia 12.07.2010r. do dnia zapłaty w pozostałej części powództwo oddalając, II. zasądza od pozwanego na rzecz powódki I. C. kwotę 3.486,70 zł tytułem zwrotu kosztów procesu.