I C 2536/11 AI generated

Contractual delay dismissed due to excessive rain preventing work, not force majeure, under Polish Civil Code.

Case Number I C 2536/11
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court dismissed the County's claim for contractual liquidated damages against the construction company for road work delays. The defendant argued that continuous heavy rain and waterlogging made parts of the work impossible, while the plaintiff insisted the delay was a breach of contract. The court ruled that the weather constituted excessive adverse conditions rather than force majeure, excusing the defendant's liability for non-performance.

Legislator headnote

AI generated

Art. 471 k.c.; Art. 484 k.c.: Excessive adverse weather conditions, even if preventing work completion, do not constitute force majeure but may excuse liability for breach of contract if the debtor exercised due diligence.

Keywords

AI generated
contractual delay force majeure adverse weather liability exemption due diligence construction contract liquidated damages

Cited Legislation

AI generated
Art. 471 k.c.
Art. 484 k.c.
Art. 98 § 1 k.p.c.
art. 484 § 1 k.c
art. 471 k.c
art. 476 k.c
art. 98 § 1 k.p.c

Cited Case Law

AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text