I C 2536/11
AI generated
Contractual delay dismissed due to excessive rain preventing work, not force majeure, under Polish Civil Code.
Legislator summary
AI generatedThe court dismissed the County's claim for contractual liquidated damages against the construction company for road work delays. The defendant argued that continuous heavy rain and waterlogging made parts of the work impossible, while the plaintiff insisted the delay was a breach of contract. The court ruled that the weather constituted excessive adverse conditions rather than force majeure, excusing the defendant's liability for non-performance.
Legislator headnote
AI generatedArt. 471 k.c.; Art. 484 k.c.: Excessive adverse weather conditions, even if preventing work completion, do not constitute force majeure but may excuse liability for breach of contract if the debtor exercised due diligence.
Keywords
AI generated
contractual delay
force majeure
adverse weather
liability exemption
due diligence
construction contract
liquidated damages
Cited Legislation
AI generatedArt. 471 k.c.
Art. 484 k.c.
Art. 98 § 1 k.p.c.
art. 484 § 1 k.c
art. 471 k.c
art. 476 k.c
art. 98 § 1 k.p.c
Cited Case Law
AI generatedVI ACa 479/11
II CSK 180/10
Supreme Court dismisses appeal; contractor not liable for delays caused by client's additional orders and defective documentation.
II CSK 318/10
Supreme Court partially allowed appeal on contract penalty excessiveness, remanding case for re-evaluation under general damages criteria.