Plaintiff dismissed for failing to prove water pipe defects despite having full opportunity for testing.
Legislator summary
AI generatedThe court dismissed the plaintiff's claim regarding water pipe defects, ruling that the plaintiff failed to meet the burden of proof. Although the pipes were under reconstruction, the plaintiff had both factual and legal ability to conduct integrity tests using imported clean water. The court held that the plaintiff's inaction during this available period precluded establishing the necessary causal link for liability.
Legislator headnote
AI generatedUstawa o odpowiedzialności za szkody w środowisku; The plaintiff bears the burden of proving the existence of damage and the causal link, which is lost if they fail to utilize all available opportunities for investigation and testing.
Keywords
AI generatedFull text
"Powód nie musiał czekać na zakończenie prac związanych z przebudową sieci wodociągowej i kanalizacji [...] lecz miał on wszelką – faktyczną i prawną – możliwość przeprowadzenia prób szczelności i laboratoryjnych za pomocą dowiezionej czystej wody."