Court orders payment of damages and litigation costs to the construction company against the defendant.
Legislator summary
AI generatedThe court ruled in favor of the plaintiff construction company, ordering the defendant to pay damages totaling 158,704 PLN plus statutory interest. The plaintiff argued for compensation due to the defendant's breach of contract, while the defendant contested the claimed amounts. The court found the plaintiff's evidence sufficient to support the financial claims and awarded the full requested sum along with procedural costs.
Legislator headnote
AI generatedUstawa o Kodeksie cywilnym; Kodeks postępowania cywilnego: The court may award monetary damages and litigation costs when a party successfully proves a breach of contract or other civil liability.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt XX GC 1071/12
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 9 października 2013 r. Sąd Okręgowy w Warszawie XX Wydział Gospodarczy w składzie: Przewodniczący: SSO Joanna Sieradz Protokolant: Katarzyna Kafarska po rozpoznaniu na rozprawie w dniu 3 października 2013 r. w Warszawie sprawy z powództwa Budownictwo (...) Spółka Akcyjna w Ł. przeciwko (...) Spółka Akcyjna w W. o zapłatę I. Zasądza od pozwanego (...) Spółka Akcyjna w W. na rzecz powoda Budownictwa (...) Spółka Akcyjna w Ł. kwotę 158.704 zł (sto pięćdziesiąt osiem tysięcy siedemset cztery złote) wraz z ustawowymi odsetkami od dnia 5 stycznia 2012r. do dnia zapłaty. II. Zasądzić od pozwanego na rzecz powoda kwotę 11.553 zł (jedenaście tysięcy pięćset pięćdziesiąt trzy złote) tytułem zwrotu kosztów postępowania w tym kwotę 3.617 zł tytułem kosztów zastępstwa procesowego. SSO Joanna Sieradz