Court awards construction contractor partial claim for extra work and costs against subcontractor.

Case Number ECLI:NL:RBDHA:2017:4571
Court / Authority
Jurisdiction Netherlands (NL)
Decision Date
Outcome Partially Allowed

Legislator summary

AI generated

The court awarded the plaintiff contractor €25,730.50 for verified extra work and associated costs against the defendant subcontractor. While most claims for additional work were rejected, the court found a valid agreement in August and September 2014 to offset cable damages with outstanding invoices. Consequently, the plaintiff's specific vordering for this offset was dismissed, but the claim for extra work and legal fees was allowed.

Legislator headnote

AI generated

Articles 6:119a BW; Article 706 Rv: Where parties agree to offset damages with outstanding invoices, such a vordering is dismissed, but separate claims for extra work and legal costs remain adjudicated based on proven facts.

Keywords

AI generated
construction contract extra work claim invoice offset agreement legal costs award construction damages

Cited Legislation

AI generated
Article 6:119a BW
Article 706 Rv
artikel 7:755 BW
artikel 150 Rv
artikel 7:775 BW
artikel 7:752 BW
artikel 6:30 BW
artikel 6:74 lid 1 BW
artikel 6:82 lid 1 BW
artikel 6:61 lid 2 BW

Cited Case Law

AI generated
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text