ECLI:NL:RBAMS:2014:782
ECLI:NL:RBAMS:2014:782
AI generated
Contractor awarded principal sum, interest, and collection costs; contractor's counterclaim dismissed due to client's own breach.
Legislator summary
AI generatedThe court ordered the contractor to pay the principal sum, statutory interest with a 2% surcharge, and collection costs to the client. The contractor argued that the client prevented performance, but the court found the client had already breached by failing to pay the invoice. Consequently, the court dismissed the contractor's counterclaim for partial dissolution or damages because the client's prior default precluded such relief.
Legislator headnote
AI generatedArticles 19 and 20 of the General Terms and Conditions; where the client fails to pay, the contractor may claim interest and collection costs, and the client's own default bars a counterclaim for partial dissolution or damages.
Keywords
AI generated
contractual default
statutory interest
collection costs
general terms and conditions
partial dissolution
contractor liability
breach of contract
Cited Legislation
AI generatedArticle 19 of the General Terms and Conditions
Article 20 of the General Terms and Conditions
artikel 6:74 van het Burgerlijk Wetboek
artikel 6:81 BW
artikel 7:750 BW
artikel 6:58 BW
Related Decisions
AI generatedECLI:NL:RBNNE:2024:4788
Court dismisses claims for interest and collection fees due to invalid general terms and lack of statutory notice.
ECLI:NL:RBZWB:2022:5786
Contractor dismissed for breach of construction contract allowing non-performance defense without prior notice.
ECLI:NL:RBAMS:2026:3877
Construction contract claim dismissed for early invoice and rejected collection costs due to non-compliant demand letter.
ECLI:NL:RBAMS:2024:7949
Contractor ordered to pay homeowner €101k for renovation shortfall plus interest and costs.
ECLI:NL:RBAMS:2021:7219
Construction contract terminated; plaintiff's claims rejected due to insufficient evidence of breach and damages.