ECLI:NL:RBALM:2012:BW2517 ECLI:NL:RBALM:2012:BW2517 AI generated

Court orders guarantor to release partial deposit surplus to claimant after contractor bankruptcy.

Case Number ECLI:NL:RBALM:2012:BW2517
Court / Authority
Jurisdiction Netherlands (NL)
Decision Date
Outcome Partially Allowed

Legislator summary

AI generated

The court ordered the guarantor to release a specific surplus amount from the notary's deposit to the claimant following the contractor's bankruptcy. The claimant argued for the release of the remaining balance under the guarantee scheme, while the guarantor contended that the contract required a joint request to access funds. The court ruled that the surplus could be released unilaterally upon the claimant's request, but denied the guarantor's counterclaim for the full deposit amount due to lack of a joint demand. Consequently, the claimant received the surplus, and the guarantor was ordered to pay the remaining deposit to the bankruptcy trustee.

Legislator headnote

AI generated

Articles 3:1 and 3:2 of the GIW Guarantee and Warranty Scheme 2007; The surplus of a performance bond held by a notary may be released to the beneficiary upon their unilateral request following the contractor's insolvency, provided the original agreement permits such release without a joint demand.

Keywords

AI generated
construction contract bankruptcy trustee performance bond notary deposit unilateral release guarantee scheme insolvency proceedings

Cited Legislation

AI generated
Article 3:1 GIW Guarantee and Warranty Scheme 2007
Article 3:2 GIW Guarantee and Warranty Scheme 2007
Article 6:119 Civil Code
artikel 6:119 Burgerlijk Wetboek
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text