Legislator Case Law & Legislation
ECLI:NL:OGHACMB:2022:139 ECLI:NL:OGHACMB:2022:139 AI generated

Appeal dismissed; court upheld first-instance rejection of contract termination and damages claims against defendant.

Case Number ECLI:NL:OGHACMB:2022:139
Court / Authority
Jurisdiction Netherlands (NL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Court of Appeal granted the appellant permission to proceed without costs but dismissed the appeal against the first-instance judgment. The appellant argued that the defendant breached the service contract by delivering second-hand pumps and a non-functional generator, seeking contract termination and damages. The court held that the appellant failed to provide sufficient evidence of the defects and did not clearly request replacement of the pumps, thereby lacking the legal right to terminate the contract. Consequently, the first-instance judgment was confirmed, and the appellant was ordered to pay the appeal costs.

Legislator headnote

AI generated

Art. 6:216 BW; Art. 7:16 BW; Art. 7:22 BW; Art. 6:218 BW; Art. 6:220 BW: A party may only terminate a contract upon a fundamental breach and must clearly request specific performance or replacement; failure to do so precludes termination and damages claims.

Keywords

AI generated
contract termination fundamental breach specific performance service contract damages claim evidence burden replacement request

Cited Legislation

AI generated
Art. 6:216 BW
Art. 7:16 BW
Art. 7:22 BW
Art. 6:218 BW
Art. 6:220 BW
Art. 6:82 BW
art. 7:22 lid 2 BW
art. 6:82 lid 1 BW