Court dismisses claim against builder and director, allowing counterclaim for shared project losses due to quality issues.
Legislator summary
AI generatedThe court dismissed CEC's claim for unpaid invoices against Bonaire Builders and its director, rejecting the argument for personal liability. While CEC argued for payment based on a service contract, the court found the parties acted as partners sharing risks and profits on the housing project. Consequently, the court allowed Bonaire Builders' counterclaim for a share of the unbudgeted costs and quality-related damages, ordering the parties to settle the dispute through shared loss allocation.
Legislator headnote
AI generateds. 24 lid 1 BW; s. 24 lid 2 BW: Where parties to a construction project act as partners sharing risks and profits, personal liability for unpaid invoices is precluded, and losses arising from quality defects must be shared proportionally between the partners.