High Court refuses to set aside third-party notice due to defendant's culpable delay in identifying correct corporate entity.
Legislator summary
AI generatedThe High Court refused an application to set aside a third-party notice served on BAM Building Ltd. The first defendant delayed joining the correct corporate entity for four months after serving its defence, despite having access to information to identify the proper party. The court held that this delay was culpable and unreasonable, particularly given the risk of statute bar issues regarding the construction contract. Consequently, the motion to strike out the notice was dismissed without prejudice.
Legislator headnote
AI generatedO. 16 r. 8(3) of the Rules of the Superior Courts; A third-party notice is not set aside where the defendant's culpable delay in identifying the correct corporate entity renders the application unreasonable.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedFull text
[2017] IEHC 285
THE HIGH COURT
[2015 No. 1241 P]
BETWEEN
VICKIE MOREY
PLAINTIFF
AND
MARYMOUNT UNIVERSITY HOSPITAL AND HOSPICE LIMITED AND BAM CONSTRUCTION LIMITED
DEFENDANTS
AND
BAM BUILDING LIMITED
FIRST NAMED THIRD PARTY
AND
SUIR ENGINEERING LIMITED
SECOND NAMED THIRD PARTY
JUDGMENT of Ms. Justice Baker delivered on the 4th day of May, 2017.
1. This judgment is given in the application by the first named third party, BAM Building Ltd (“BAM”) for an order pursuant to O. 16, r.
8(3) of the Rules of the Superior Courts to set aside a third-party notice issued and served on BAM on 19th April, 2016.
2. Briefly, the chronology of the proceedings is as follows:
(i) 13th February, 2015 personal injuries summons served;
(ii) 19th August 2015 defence served;
(iii) 14th March, 2016 motion to join third party issued, after warning letter sent on 29th February, 2016;
(iv) 11th April, 2016 order of the High Court;
(v) 19th April, 2016 third-party notice served;
(vi) 9th November, 2016 motion to strike out issued.
3. BAM is a limited liability company with registered offices in the State. In or around the year 2009, BAM entered into a contract with
the first defendant for the construction of a hospital. The personal injuries summons incorrectly named an associated company, BAM
Construction Ltd, as second named defendant although this company never had any involvement in the construction of the hospital,
and had been dissolved on 22nd February, 2008.
4. The accident the subject matter of the proceedings is alleged to have occurred on or about 12th October, 2012. The plaintiff in
the course of her employment with the first defendant was present at its hospital at Marymount, Curraheen in the County of Cork,
when it is alleged that a wall-mounted television unit detached from the wall and struck the plaintiff on the head and face. The
plaintiff alleges that the accident was caused by reason of the negligence, breach of contract and breach of duty of the defendants,
in regard to the installation and fitting of the television unit.
5. The application to set aside the third-party notice is grounded on the argument that the first named defendant delayed unduly in
bringing a motion to join BAM as third party. A period of thirteen months elapsed between the commencement of the proceedings in
February, 2015 and the issue of the motion on the on 14th March, 2016. BAM argues that it ought to have been clear and obvious to
the first defendant that the plaintiff had wrongly named the dissolved company as second defendant, in particular because the first
defendant had access to all documentation relating to the contract for the construction of the hospital, it being one of two parties to
the contract, and the contract being for a significant monetary consideration, and that even a preliminary or superficial investigation
would have identified the error, as the named second defendant company was dissolved before the contract to build had been
entered into.
6. The first defendant through its solicitors and insurance company had written to the named second defendant, by then dissolved, at
its registered office at Kill, County Kildare by letters of 29th April, 2014, and 23rd March, 2015. BAM argues that it is clear from these
letters that the first defendant was well aware that there were different corporate entities within the BAM group of companies, that
investigation and correspondence had occurred as long ago as April, 2014, a year prior to the personal injury summons, and two years
before the motion to join the third party. It is argued in those circumstances that the application to join the third party was not made
as soon as was reasonably possible, as is required by the statutory provisions, and that the delay of thirteen months in taking steps
to join BAM is unexplained and wholly excessive.
7. The first defendant relies on a number of arguments in opposing this application. It points to the multiplicity of BAM entities, and
names six of these by way of illustration. It points to the fact that the error made by the plaintiff was to name the wrong entity
within the group, and that the motion to join a third party arose because the plaintiff chose to discontinue against the dissolved
company and proceed solely against the first defendant. It argues that BAM allowed a period of seven months to elapse since it was
joined as third party before bringing this motion, and that the principles found in the case law suggest that the requirement of
expedition must be applied to all relevant parties in the application. The first defendant also argues that the third party has failed to
disclose any prejudice to it in its defence of the third-party proceedings, and that as a matter of fact BAM was notified of the
incident and carried out an inspection in the days immediately following the incident, and itself then carried out the necessary repair
works on the premises. In those circumstances BAM was aware of the claim, and this is not denied. Further, the named third party is
an appropriate party to the proceedings.
8. A particular emphasis is placed by the defendant on the fact that by letter of 4th August, 2016, BAM’s solicitors requested a third-
party statement of claim and thereby engaged in the proceedings. It is argued that it is thereby estopped from seeking to set aside
the notice. The solicitor for the third party points to a letter written some five weeks later, on 13th September, 2016, in which he
advised that having considered the matter further, a motion to set aside the third-party notice on the grounds of delay was to be
issued, and that a third-party statement of claim was no longer required.
9. No steps have been taken in the proceedings by either party since that date, albeit the first defendant delivered the third-party
statement of claim on 30th September, 2016, after the letter by which the motion to set aside the third-party notice had been
threatened.
10. The defendant has not identified precisely when it became aware of the error in the plaintiff’s proceedings in regard to the correct
BAM entity.
The law
11. Section 27(1)(b) of the Civil Liability Act 1961, provides for the service of a third-party notice by which a defendant may make a
claim for contribution against a person who is not already party to a suit. The statutory provisions expressly require that such notice
be served “as soon as is reasonably possible”. The Act does not prescribe any period within which application is to be made, but O.
16, r. 1(3) of the Rules of the Superior Courts provides a period of 28 days for the making of application for leave to issue a third-
party notice. The time provided in the Rules must be seen in the context of the statutory imperative that application be made as soon
as is reasonably possible, and the delay in bringing any application will be measured in the light of the 28-day period provided by the
Rules. As Hogan J. said in Buchanan v. B.H.K Credit Union Limited & Ors.[2013] IEHC 439:
“… any such permissible delay will generally be measured in weeks and months and not years.” (para. 23)
12. Kelly J. quoted that comment with approval in the recent decision of the Court of Appeal in Mulcahy v. A.S.L. Sports Park Ltd &
Ors. [2015] IECA 353.
13. Finlay Geoghegan J. in Greene v. Triangle Developments Limited & Ors. [2015] IECA 429 said that the court hearing an application
to set aside a notice should:
“… look not only at the explanations which were given by a defendant for any purported delay, but also to make an
objective assessment as to whether, in the whole circumstances of the case and its general progress, the third-party
notice was or was not served as soon as is reasonably possible.” (para. 25)
14. As Kelly J. said in Mulcahy v. A.S.L. Sports Park Ltd & Ors., “The statutory provision itself mandates an element of urgency”. In
that case he considered that the delay was not explained, and noted that the defendant was aware of the involvement of the third
party some five years before the application to join was made. Kelly J. allowed an appeal from a decision of the High Court, which had
refused to set aside the third-party notice, for delay. He did so, inter alia, by reference to the progress of the pleadings and the
manner in which they were pleaded.
15. In Molloy v. Dublin Corporation & Anor. [2001] 4 I.R. 52, Murphy J. identified the purpose for which Oireachtas imposed the
requirement of reasonable expedition as follows:
“There can be little doubt as to what that scheme and purpose was. The legislature was understandably desirous of
avoiding a multiplicity of actions. Instead of defendants against whom awards had been made instituting further
proceedings against other parties liable to them in respect of the same set of facts – and indeed those defendants in turn
perhaps instituting even more proceedings against others – the Oireachtas sought to establish a situation in which the
rights and liabilities of all parties arising out of a particular set of circumstances would be disposed of in the same
proceedings.” (pp. 55/56)
16. This dicta was quoted with approval by Finlay Geoghegan J. in Greene v. Triangle Developments Limited & Ors. It is clear also
from other judgments therein identified by Finlay Geoghegan J. that the obligation is on the defendant to serve the notice within a
reasonable time, and that has the effect that the onus of showing that delay was not unreasonable is on that defendant.
17. In Connolly v. Casey [2000 1 I.R. 345], the Supreme Court seems to have preferred a more flexible or broad approach requiring an
analysis of the whole circumstances of the case and its general progress, as well as the general purpose of the subsection:
“A multiplicity of actions is detrimental to the administration of justice, to the third party into the issue of costs. To
enable a third party to participate in the proceedings is to maximise his right - he is not deprived of the benefit of
participating in the main action.” (p. 351)
18. Finlay Geoghegan J. explained in Greene v. Triangle Developments Limited & Ors. that this required an “objective assessment” of
the whole circumstances of the case and its general progress. The mere fact that defendant did not give a full explanation for delay
was not the end of the assessment, and the test is whether, taking all of the circumstances in into account, it was reasonable to
delay. As she said, the 28-day period provided under the Rules of Court is not one that parties normally observe, or can be expected
to observe in many cases. In Greene v. Triangle Developments Limited & Ors., Peart J. added a gloss to the test, that to strike out
the third-party notice in that case would be disproportionate.
19. In Boland v. Dublin City Council [2002] 4 I.R. 409, the Supreme Court added a further factor to the test, that the statutory
requirement to move with reasonable expedition applies also to the bringing of an application to set aside such notice. That approach
is consistent with the general requirement identified in Connolly v. Casey, that the court would look objectively at all of the
circumstances, the overall requirement of the legislation, the value of expedition in the prosecution of claims, and an avoidance of a
multiplicity of actions.
Application to the facts of the present case
20. The third party argues that the legislative purpose of avoiding a multiplicity of actions is not a factor of great significance in the
present case as there is another third party, Suir Engineering Ltd., against whom the defendant may seek contribution. While that
argument may in due course emerge as correct, it seems to me that the objective assessment required to be carried out by the court
must not be done on the basis of an assumption as to whether an existing party is likely to be found liable in the action. It is not the
function of the court in the present application to consider the merits of the action, or the likely success of the third-party
proceedings, or even the degree or percentage of contribution that might be awarded.
21. Following the decision of the Supreme Court in Connolly v. Casey the fact that the first defendant has not provided a satisfactory
explanation for a delay is not the end of the matter, and the general progress of the case and its general circumstances also fall for
consideration. This is because the primary purpose of the statutory provision mandating reasonable expedition is to balance the
desirability of avoiding a multiplicity of actions on the one hand with the objective with the objective that the primary proceedings not
be unduly delayed by the progress of the third party issue.
22. The defence was served in the present case in August, 2015, and allowing for the Long Vacation, the 28-day period for the
service of a notice of motion to seek to join a third party expired in October, 2015. Time is tested at the date of issue of the motion:
McElwaine v. Hughes [1997] IEHC 74. The motion was issued in March, 2016, five months later. The motion to set aside was brought
in November, 2016, eight months thereafter. The plaintiff discontinued against the then second defendant in February, 2016, and the
motion to join the third party was issued twelve days thereafter. Thirteen months elapsed between the date when the personal
injuries summons issued and the service of the motion.
23. The relevant statutory period, taken in conjunction with the period provided in the rules of the Superior Courts for the service of
a notice to join a third party, is the date of the service of the defence, and not the plenary summons. Time must be assessed in that
context, although the general consideration of the case will often involve a consideration of whether reasonableness is to be tested
against the overall delay in the proceedings generally, and the date on which the proceedings were instituted will often in those
circumstances be a factor, especially if a defendant had then all information necessary to consider whether to seek indemnity from a
third party: Board of Governors of St.Laurence’s Hospital v. Staunton: [1990] 2 I.R. 31.
24. The first defendant must have been aware, at the very latest in February, 2015, that the plaintiff had sued the wrong entity in
the BAM group of companies. Indeed it must have been aware earlier than this, as the claim of the plaintiff had been processed
through PIAB. The PIAB authorisation issued on 30th October, 2014, and the personal injury summons issued on 13th February, 2015.
It is undoubtedly the case that the first defendant had access to all relevant documentation at the very latest when the personal
injury summons was served in February, 2015, and that had it investigated the matter then, it would have seen the error, and realised
it could not seek contribution or indemnity against the named second defendant. It was at that point in time that the first defendant
ought to have considered whether it was appropriate or desirable to seek to join the third party to the proceedings as the first
defendant made a specific plea of negligence against the second defendant when it delivered its defence on 19th August, 2015, and
it must have done so without carrying out a search to ascertain whether the second defendant was correctly named.
25. The somewhat bland explanation for the delay given by the first defendant is that the plaintiff made an error in naming the second
defendant, but by letter of 29th April, 2014 to “BAM Contractors”, in which the insurance company identified that misnamed BAM
entity as being the “main contractor” for the facility, and invited it to indemnify. A letter of 23rd March, 2015, was also addressed to
the same entity also misspelt, although in the body of the document the generic “BAM” was used. It is clear from the correspondence
that no search in the CRO was engaged by the first defendant until much later in the process, although it knew that some BAM entity
had involvement.
26. It could be said that it was unreasonable of the first defendant not to carry out a search in the CRO before writing the letter in
which indemnity was sought from a BAM company. Had the first defendant engaged even a cursory search in the CRO it would have
become aware of the error made by the plaintiff, and indeed had the first defendant thought to check its own records it would have
immediately known the correct name of the contracting company. It was the discontinuance by the plaintiff of her action against the
dissolved entity that triggered consideration by the first defendant of the identity of the party from which it should seek indemnity.
27. Thus the material information that might have guided a decision to seek to join BAM as third party was never explored. The first
defendant had all the information available to it to join BAM as a third party when the proceedings were instituted or when it served
its defence. Its delay therefore was culpable and as Denham J. identified in Connolly v. Casey the question is whether a defendant
was culpable, and not its solicitors or other advisers.
28. However, the matter does not end there, and as explained by the Supreme Court in Connolly v. Casey, the whole circumstances
of the case and its general progress must be considered. The question is whether it was reasonable to wait four months after the
service of the defence before carrying out the necessary searches to ascertain whether the plaintiff had joined the correct party as
second defendant. I consider that the relevant time for the purposes of an examination of the overall progress of this litigation is that
on 2nd March, 2016 the plaintiff discontinued against the named second defendant, and the motion to join the correct BAM entity
was brought exactly twelve days later. It was at that time that the first defendant knew it was at risk that the named second
defendant was not available as a contributor should the plaintiff succeed in the action. While there was a multiplicity of error and
fault in not moving to check the precise identity of the second defendant, it was only when the plaintiff discontinued against that
dissolved entity that the first defendant was genuinely at risk, or knew itself to be genuinely at risk, to the extent that it required to
join a different BAM entity as third party to seek indemnity from a different corporate entity.
29. Reasonableness must also be assessed in the present case, somewhat unusually, in regard to the fact that the third party is one
of one of the many companies in a group of construction companies of which the named second defendant was once a part. The first
defendant had communicated with a BAM entity, at the registered office of most if not all of the entities in the group, and the third
party knew that seeking contribution from a BAM company was under consideration by first defendant. There is a genuine dispute
between the first defendant and the named BAM entity and it seems from the evidence that a claim for breach of contract against
that entity might not be statute barred, or at least was not statute barred when the third-party notice issued, as the works of
construction are said to have commenced on 22nd April, 2009, and concluded on 8th April, 2011. The third-party notice issued in
April, 2016, and it is safe to assume that the fixing of a television unit would not have happened in the early stages of the works, but
at the time when the final fit was done.
30. In those circumstances I do not consider that the third-party application was made too late, and therefore I refuse to make the
relief sought in the notice of motion. I do not propose considering whether prejudice plays a part in the present case, and no
evidence has been adduced by the third party that it suffers actual prejudice by virtue of the delay.