Legislator Case Law & Legislation
IEHC 349 ECLI:IE:HC:2012:349 AI generated

High Court allows third party notice despite delay, ruling no prejudice and no fixed statutory time limit exists.

Case Number IEHC 349
Court / Authority
Jurisdiction Ireland (IE)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The High Court refused to set aside a third party notice served 14 months after the statement of claim. The architect argued the delay violated the 'as soon as reasonably possible' requirement of s. 27 of the Civil Liability Act 1961, while the sub-contractor claimed potential prejudice from the seven-year gap since the project. The court held that no fixed period exists under the Act and found the architect's information-gathering process was not unreasonably slow, concluding no real prejudice was suffered by the third party.

Legislator headnote

AI generated

s. 27 of the Civil Liability Act 1961; The court has discretion to determine the appropriate time for serving a third party notice, and a delay is not fatal if the party acted as soon as reasonably possible and no prejudice is suffered.

Keywords

AI generated
third party notice Civil Liability Act 1961 reasonable time prejudice assessment discretionary power building negligence procedural delay

Cited Legislation

AI generated

Cited Case Law

AI generated
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

NEUTRAL CITATION NUMBER [2012] IEHC 349

THE HIGH COURT

[2009 No. 10633 P]

BETWEEN

KEVIN O'HALLORAN AND TERESA O'HALLORAN

PLAINTIFFS

AND

KEN FETHERSTON AND BERNADETTE FETHERSTON AND BLACKROCK INNS LIMITED AND ELLEN CONSTRUCTION LIMITED AND

PAUL C. O'DWYER TRADING AS O'DWYER AND ASSOCIATES AND WYG IRELAND LIMITED

DEFENDANTS

AND

MCKELAN CONSTRUCTION LIMITED

THIRD PARTY

JUDGMENT of Mr. Justice Mac Eochaidh delivered on the 31st day of July, 2012

1. This is an application to set aside a third party notice because it is said that the requirements of s. 27 of the Civil Liability Act

1961, that such a notice be served as soon as reasonably possible were not met.

2. The fifth named defendant was the architect of a building in which the plaintiffs purchased an apartment in late 2004. It is

noteworthy that he did not perform a supervisory role during the construction of the building and carried out no inspections of the

building works as they progressed. Whilst this is very often a function assigned to the architect on a project, this was not what

happened in this case.

3. The third party was the main sub-contractor for the project and is said to have carried out most of the building works on the site.

The main contractor (the fourth named defendant) is in liquidation, a factor which may explain why the main contractor has not

sought to join its sub-contractor - something one might expect where there are allegations of shoddy building works.

4. The plaintiffs say that they have suffered from significant damp and mould problems at their home and that remedial efforts have

failed. On 3rd September, 2009, their solicitors wrote 'O'Byrne' letters to five intended defendants but of these only two were

ultimately sued. I note that though the third party was indicated as an intended defendant in the O'Byrne letter, the plaintiffs

ultimately did not sue the third party. I also note that the plaintiffs have not now sought to join the third party as a co​ defendant.

5. A statement of claim was delivered on 1st March, 2010, and para. 15 alleges negligence and breach of duty by the architect in the

design, specification and construction of the property. Reasonably elaborate particulars of this plea are set out describing the

absence of insulation, missing membranes, non-complaint U-values, absence of a thermal brake, absence of vertical damp-proof

coursing and other matters all connected with what the plaintiffs assert is the cause of the dampness in the apartment. The plaintiffs

also say that an opinion on compliance furnished by the fifth named defendant was false, inaccurate and misleading. The reason I

refer to the detail contained in the statement of claim is to show that all of the defendants are elaborately informed that the plaintiffs

believe that the dampness is caused by poor design and construction and inadequate materials. As the fifth named defendant was not

a supervisor of the works, he could not have known of inadequate materials or poor constriction methods. Nor could he have known of

any deficiencies covered up by completed works.

6. An exchange of particulars took place between the plaintiffs and the fifth named defendant which provided quite technical detail of

allegations of want of compliance with Building Regulations amongst other matters.

7. The fifth named defendant delivered its defence on 1st November, 2010. The defence notes the involvement of the third party in

the construction of the apartment and there are numerous references to matters in respect of which the third party had

responsibility. Based on this, the third party says that on the date of the delivery of the defence, the fifth named defendant had

sufficient knowledge to join it as a party.

8. For the most part, the references to the third party in the fifth named defendant's defence assert what the third party's

responsibilities were, but make no clear allegations against the third party except that para. 20 of the defence says:-

"If, which is not admitted, there was not substantial compliance with the Building Regulations at the time that the fifth

named defendant issued the said Opinion, it was due to the negligence of McKelan Construction Ltd. and/the The Sixth

Named Defendant and/or Lucas Engineering Services who provided the Confirmations of Compliance with the said Building

Regulations on which the said Opinion solely relied."

9. By comparison, the allegations in the third party notice are much clearer. It asserts:

" ..... damage to the plaintiffs apartment was caused by the negligence and breach of duty, including breach of

statutory duty, of the proposed third party as a direct result of using a non-standard method of construction, failing to

carry out adequate remedial works and failing to comply with design specifications provided by the fifth named

defendant particularly in relation to insulation specifications contained in the said design"

10. In its application for liberty to issue and service a third party notice, the fifth named defendant avers as follows:-

"A detailed inspection of the plaintiffs' apartment was carried out by the fifth named defendant's expert recently. This

inspection involved inspection of opened up works that had been carried out on behalf of the Plaintiffs and/or the Third

Named defendant. It should be noted that the Fifth Named Defendant was contracted in a very limited capacity to issue

certificates based purely on visual inspection of the built works and therefore this was the first time that the Fifth

Named Defendant was aware of the standard of works underneath the completed surfaces. The said expert inspection

has revealed defects which are a direct result of the proposed third party departing from the design of the Fifth Named

Defendant could not have been aware of until the works were opened up."

11. That averment was made at about the end of February 2012. It does not inform the court when precisely the inspection was

carried out or what efforts had been made to arrange the inspection.

12. In the second affidavit of the fifth named defendant (sworn on 20th July, 2012) further detail is given in relation to the inspection

of the plaintiffs' apartment. The Court is told that the plaintiffs facilitated an inspection on 19th July, 2011 - some eight months after

the defence was delivered. The plaintiffs excavated holes in the floor of their apartment to facilitate an inspection of the insulation of

the floor slab by the fifth named defendant's expert. On the same day, a detailed and invasive inspection of the rest of the apartment

was conducted and this included an investigation of the cavity insulation and ventilation. The fifth named defendant's expert

produced a report on 25th October, 2011.

13. I accept that the investigations carried out by the fifth named defendant's expert armed him with sufficient information to ground

procedings against the third party and this is information which he did not have at the time the defence was filed. There is a

significant difference between the general references and allegations relative to the third party in the defence and the specific

allegations contained in the third party notice, as set out above. In this connection I note the comment by McMahon J. in Robins v.

Coleman et al [2010] 2 I.R. 18, at 194, as follows:

"[37] In this context, it should be pointed out that there is a big difference between making a general precautionary

statement by way of general pleading in litigation and swearing an affidavit particularising an allegation of professional

negligence. In my view, it would be unsafe to conclude from such a general pleading that the pleader had sufficient

knowledge to justify allegations of professional negligence against a third party or to abandon the prudent caution of

restraint that such a course of action requires. This point is well made by Denham J in Connolly v. Casey [2000] 1 I.R

345, where she says at p. 350:

'Even though there were pleas in the defence relevant to the third party, there is a difference between a general

plea in a defence and swearing an affidavit setting out the basis on which it is alleged counsel [i.e. the proposed

third party} was negligent. A statement from Mr. Murphy was relevant to this. It was not unreasonable to have

sought a statement from Mr. Murphy and awaited its arrival, it was a prudent action'."

14. Clearly, the particular caution with which the law requires parties to approach suing in professional negligence does not pertain in

this case. However, the decision to issue a writ, or in this case to serve a third party notice, is a significant one and it would be

unwise to so proceed without what is perceived to be reliable evidence of the fault of an intended defendant or third party

15. In the recent decision of EBS Building Society v. William E. Leahy and Others [2010] IEHC 456, Hogan J. usefully summarises

recent judicial comment on s. 27 of the Civil Liability Act 1961, as follows:

"9. The objectives of this sub-section are by now so well established in the voluminous case-law on the topic that it is

scarcely necessary to set them out at length here. Briefly, the I96I Act seeks to avoid a multiplicity of actions arising

out of the same dispute, so that where possible all issues involving plaintiffs, defendants and third parties are heard

either together or in a sequenced trial: see, e.g., Governor of St. Laurence's Hospital v. Staunton [1990] 2 IR. 31,

Connolly v. Casey [2003] 1 IR . 345 and Robins v. Coleman [2009] IEHC 486.

10. Second, the concept of what is "as soon is reasonably possible" within the meaning of s. 27(1)(b) is a relative one

and depends on the circumstances of the case: see, e.g., Connolly v. Casey, .Molloy v. Dublin Corporation [2001] 4 JR.

52 and Robins v. Coleman. The Oireachtas did not seek to fix a set time period, but rather imported a concept of

relative urgency which is designed to compel the defendant to seek to issue a third party notice with all deliberate speed

having regard to all the relevant circumstances. As Murphy J explained in Molloy [2001]4 JR. 52 at 56-57):

'The statute is not concerned with physical possibilities but legal and perhaps commercial judgments. Proceedings cannot

and should not be instituted or contributions sought against any party without assembling and examining the relevant

evidence and obtaining appropriate advice thereon. It is in that context that the word 'possible' must be understood.

Furthermore, the qualification of the word 'possible ' by the word 'reasonable ' gives a further measure of flexibility ... "

16. By enacting section 27 of the 1961 Act, not only did the Oireachtas intend to achieve efficiency in litigation by linking cases

arising from the same facts, it may also be said that the Oireachtas intended to avoid the problem of conflicting judgments which

might arise if cases arising from the same nexus are tried at different times by different courts. In my opinion, the requirement in s. 27

that a third party notice be served as soon as is reasonably possible is intended to ensure that the writs between the parties and all

procedural steps be completed in a manner that permits the various actions to be tried either together or sequentially, and by the

same court. Thus, when one is considering whether a third party notice has been served "as soon as is reasonably possible", one may

have regard to the effect any delay has on the achievement of joined or sequential trials. It is noteworthy in this case that the

application to issue and serve a third party notice was served on the plaintiffs and that no complaint has been identified to this Court

from the plaintiffs as to any delay the third party proceedings will cause to its action, which, I understand, is due to be heard in the

spring of 2013.

Conclusion

17. The delay in this case is approximately fourteen months from the delivery of the defence to the service of the third party notice. I

accept that the fifth named defendant prudently sought to inspect physically the plaintiffs' apartment before suing the third party. No

complaint was addressed to me that undue delay attended this process though it took 8 months. The fifth named defendant's expert

produced a report in October 2011, following the inspection approximately three months earlier, and leave to issue the third party

notice was sought on 28th February, 2012. The 14- month delay is in the danger zone in relation to the sort of delay under discussion

(though an even longer delay could well fall within an acceptable period if properly justified), but I find that the fifth named defendant

has discharged its burden of persuading the Court that it acted as soon as was reasonably possible in obtaining additional information

which permitted it to engage in a decision making process as to whether to sue the sub-contactor. While this process of gathering

information compiling a report and deciding to sue was not conducted quickly neither could it be said that it was unreasonably slow. A

fixed period for joining third parties has not been set by the Oireachtas in section 27 of the 1961 Act. Instead, it has given the Court

a discretion to determine what period is appropriate and in my view when the Court is considering a period of a little over a year, the

court should strive to achieve the main purpose of section 27- i.e., joined or immediately sequential trials for all parties to avoid

duplication of hearings and possibly conflicting results.

18. I have also considered two other factors in deciding not to set aside the third party notice. The fifth named defendant says that

it anticipated that another of the defendants (namely, the main contractor) would seek to join its sub-contractor as a third party

given its presumed state of knowledge about the involvement of the third party in the building project. This was not an unrealistic

expectation on the part of the fifth named defendant although the fact the main contractor did not ultimately do so highlights the

danger of waiting for another party to join a third party to proceedings.

19. The other factor I have considered is that no real prejudice is suffered by the third party arising from the 14-month delay. Though

the third party claims that seven years have passed since it was last involved in the project, such period is not solely or even mainly

attributable to the actions of the architect. Even if the third party notice had issued immediately after the delivery of the defence,

the period between the last involvement of the third party and such an event would have been about six years. The extra year or so

occasioned by the delivery of the third party notice, in my opinion, does not ground a plea of prejudice and, fairly, counsel for the

third party did not press this matter.

20. I refuse to make an order setting aside the third party notice, but in view of pending trial of the main action, I require the parties

to engage with the Court to establish a strict timetable for exchange of pleadings and any interlocutory matters in the third party

proceedings to ensure that the plaintiffs' action proceeds as planned and that the third party action closely accompanies that action.

I will hear the parties on the timing of all matters pertaining to the third party action.