AI generatedThe High Court dismissed the plaintiff's claim for restoration costs but allowed damages for loss of use and general distress. The plaintiff alleged negligence by the Council and contractors caused property damage during drainage works, arguing for full reinstatement and compensation. The court found liability for the damage but ruled that pre-incident restoration costs could not be awarded, instead assessing damages based on rental loss and inconvenience.
Legislator headnote
AI generatedCivil Liability Act 1961; Negligence: Where damage is established but restoration costs are not recoverable, damages may be awarded for loss of use and general distress.
Keywords
AI generatedRelated Decisions
AI generatedFull text
Neutral Citation 2012 [IEHC] 293
THE HIGH COURT
[2006 No. 56 P]
BETWEEN
JAMES O'CALLAGHAN
PLAINTIFF
v.
LIMERICK CITY COUNCIL AND ROADBRIDGE LIMITED AND MURPHY INTERNATIONAL LIMITED
DEFENDANTS
Judgment of Mr. Justice Hedigan delivered the 12th of July 2012
1. The plaintiff resides at 8 Palmerstown Court, Mungret Street, Limerick. The first named defendant is the city council for the limerick
city functional area and has its offices at City Hall, Limerick. The second named defendant is a limited liability company and has its
registered offices at Dock Road, Bunlicky, Limerick. The third named defendant is a limited liability company and has its registered
offices at Hiview House, Highgate Road, London, NW5 1TN.
2. The plaintiff’s claim is for:-
(a) Damages for loss, damage, inconvenience and expense suffered and sustained by the Plaintiff owing to the negligence
and breach of duty (including breach of statutory duty) and/or nuisance and/or breach of the Rule in Rylands v Fletcher
and/or for trespass and/or interference with the Plaintiff’s property rights and/or for breach of the Plaintiff’s rights of
support and/or such other or further basis as is deemed fit arising out of works being carried out by the Defendants at or
near the canal bank, Clare Street, Limerick and which caused interference and damage to the Plaintiff’s property adjacent
thereto.
(b) If necessary, an Injunction or Order requiring the Defendants to restore the Plaintiff’s property to its condition prior to
the matters complained of herein.
(c) Such interim and/or interlocutory relief as is deemed fit.
Background Facts
3.1 The plaintiff in these proceedings seeks damages arising out of the manner in which works were carried out under the Limerick
Drainage Scheme. The plaintiff is the owner of a dwellinghouse and associated outhouses at Canal Bank, Clare Street, Limerick. The
plaintiff’s property is located approximately 10 metres from the canal wall. Extensive works took place on the canal in the course of
the Limerick Drainage Scheme. Limerick City Council ("the Council") appointed Roadbridge Limited ("Roadbridge") as the main
contractor in respect of contract number 3.2 Interceptor Sewers ISU Southern on the Limerick Main Drainage Scheme. These were
the works which took place in the vicinity of the plaintiff’s property. The appointment was made pursuant to the Institution of
Engineers of Ireland Conditions of Contract for use in connection with works of civil engineering construction (Third Edition, 1980
Revised and Reprinted October, 1990). The original plans for contract 3.2 envisaged a tunnelled drive along Clare Street, Limerick
which would join the two sections between ISU 4 and Manhole 10. However due to issues such as traffic disruption, a variation was
ordered by the Council whereby a new drive was directed running directly from ISU 4 to Manhole 10. The proposal for this was a
tunnel drive adjacent to the canal along the canal bank. There were difficulties laying the sewer between ISU 4 and MH10 in the
proposed fashion and this drive was discontinued in early 2003. This necessitated proposals for alternatives as to how to connect the
sewer between ISU 4 and Manhole 10. Roadbridge proposed a form of construction which effectively ran in an open cut down the
canal bed itself in a straight line between the two points. Representations were made by Waterways Ireland who were concerned that
a straight drive would result in damage to a Waterways Ireland Lock. The engineer having charge of the contract decided to choose a
route which would avoid any possible damage to the lock. The engineer appointed was White Young Green and its representative was
the resident engineer Russell Naylor. It was decided that the work to be carried out was partly to be by way of open cut within the
bed of the canal itself from structures known as ISU 1.03 A and ISU 1.03B and thereafter by tunnelling works to manhole 10. The
engineer Mr Naylor wanted and it was decided to include an "S" bend in order to take the tunnel drive away from the lock structure in
the canal. This was to meet the concerns of Waterways Ireland.
3.2 Subsequent to this decision Roadbridge effected the open-cut works along the canal bed between ISU1.03A and ISU1.03B with
these works concluding in or around 25th August, 2003. After the completion of the open-cut works to ISU 1.03B the question of the
remaining section to Manhole 10 was considered. The engineer directed that the S Bend structure should be constructed with the
tunnel running from manhole 10 to a reception pit which in turn was to be tied into ISU 1.03B. The latter structure was to be effected
by a cofferdam. The cofferdam was located adjacent to the plaintiff's house and it entailed the driving in and removal of sheet piles in
this area.
3.3 There was disagreement between the parties in relation to the construction of the tunnel from ISU 1.03B to Manhole 10. This
disagreement centred on whether to use dewatering or not. On 7th October, 2003 Mr. Eamon Curran Contracts Manager with
Roadbridge wrote to Mr. Felix Cocker Engineer with Limerick Main Drainage. Mr. Curran stated in this correspondence:-
"Further to our meeting of last week please find attached details of the dewatering wells to be placed adjacent to the
tunnel drive between Point Band manhole 10... The pumps and generator are on site and will be used if required. The
excavation of the drive pit adjacent to manhole 10 is now below -2.50 m O.D. and in the tunnel horizon. We are at
present excavating a stiff impermeable clay with minimal ground water infiltration."
Mr. Naylor in correspondence dated 9th October, 2003 to White Young Green, expressed his concerns vis-á-vis the dewatering
scheme which was being proposed by Roadbridge. On the 28th October, 2003 Mr. Curran responded by proposing further testing along
the proposed route of the tunnel to provide information with regard to likely water drawdown in the gravel layer confined between the
silt/clay layer and the bedrock. The resident Engineer remained of the view that dewatering on a continuous basis should be carried
out. In correspondence of the 4th November, 2003 Roadbridge commented:-
"We would like to reaffirm our position that dewatering should not be carried out unless absolutely necessary. Inspection
of the clay face at the launch pit would seem to indicate that it is impervious and that water does not pose an immediate
risk. Pumping substantial volumes of water from the gravel layers over a period of time will remove the fines and decrease
the pore water pressure. This may lead to settlement of the overlying soils."
In a further letter of the 4th November, 2003 Mr Curran commented in relation to dewatering:-
"Following the events over the last few days it is our understanding that all decisions regarding the dewatering and
operation of the tunnelling machine are to be taken by the resident engineer. We hereby undertake to carry out his
instructions but feel we must advise of the implications of these actions on the likely outturn cost, and present indemnity
insurances in place under the contract. We have been advised by our insurers that they cannot accept responsibility for
actions over which we have no control."
3.4 Limerick Main Drainage insisted that Roadbridge stick to their own method statement which called for continuous dewatering. The
issue of dewatering was discussed at a site meeting of the 5th November, 2003. The minutes of this site meeting state:-
"The section of work from MH10 to MH1.4 was discussed. LMD were very concerned that they had not received a full
dewatering plan or settlement calculations in the method statement for the tunnelling works at MH10 as requested. This
work had now commenced, approval to continue working would only be given on a day-by-day basis provided that the
dewatering was proven to be effective and alignment and settlement were kept to the required tolerances. LMD insisted
that Roadbridge Limited carry out the dewatering indicated in their method statement and that it was not sufficient to
dewater only if they considered it necessary. LMD considered that Roadbridge's proposal would be too late to prevent
settlement and tunnel misalignment if silty sand and gravels under a high water pressure were encountered in the face.
Ground water levels should therefore be kept below the invert of the tunnel. Measurements taken to date indicated that
the dewatering installed would be able to achieve this and only result in minimal settlement but this would continue to be
assessed on a daily basis."
Subsequently, dewatering continued on a continuous basis until 3rd December, 2003. The reception pit was finished by 10th
November, 2003. The tunnelling works were finished by 3rd December, 2003.
3.5 On 22nd, 23rd and 24th December, 2003 Roadbridge carried out the tie in works between ISU 1.03B and the reception pit by way
of the cofferdam. Mr. Eamon Curran had sent to Felix Cocker of Limerick Main Drainage the drawings for the manner in which the tie
was going to be carried out and specifically sought the approval for same by site correspondence dated 2nd December, 2003. No
method statement however was provided for the connection between Reception Pit 1.03c and Point B. No written response was made
to Roadbridge.
3.6 On the 14th January, 2004 the plaintiff, Mr James O'Callaghan made a telephone call to Mr Russell Naylor to inform him that his
property on the canal bank had sustained severe structural cracks. Mr Naylor visited the property on the 14th of January to view the
damage. Photographs taken then by Mr. Russell Naylor show severe damage to the property. In November 2005 the third named
defendant Murphy International Limited were hired by the Council to install a cobblelock pathway along the canal bank. This project
was in effect the completion of the work by the defendants on the canal bank. Vibrating equipment was used in the installation. A
300mm zone was left in front of the plaintiff’s property. The parties disagree about the extent to which the use of vibrating equipment
increased the cracking in the property. The cobblelock was put at 50mm higher than the level of the floors of the house. As a result
of the damage to the house, it had to be boarded up in about February 2004 and abandoned as it was obviously unsafe to use or let
out at that stage given the substantial structural cracking. The property deteriorated in condition and was vandalized. In 2007 the
plaintiff received a notice from the corporation about the condition of the property. The property remains in a semi ruinous state and
there has been, prior to the hearing, no agreement on either the extent of the damage sustained or the responsibility for the damage.
Plaintiff’s Submissions
4.1 The first and second named defendants both concede that damage was caused to the plaintiff’s property during the course of the
limerick main drainage project. The Council claims that the cracking was caused by the manner in which Roadbridge carried out the
work adjacent to the plaintiff’s property, whereas Roadbridge claims that the cracking was caused by dewatering ordered by the
Council. In either case the plaintiff is entitled to compensation. The plaintiff claims that on or about the 13 or 14th of January, 2004
substantial cracking and movement of his house occured. The plaintiff claims that further damage was caused during pavement
reinstatement works subsequently carried out by Murphy International on behalf of the Council. The engineering evidence on behalf of
each of the parties during the course of the hearing was in agreement that the house will have to be demolished as a result of the
damage caused to it. The evidence was that the canal wall adjacent to the plaintiff’s property moved a considerable distance
outwards and downwards as a result of these works and that a section of the wall of up to 20 metres was also removed by the
second named defendant in the course of the works. From about November 2003, there was substantial movement of the ground at
and near the plaintiff’s property.
4.2 Counsel on behalf of the plaintiff submits that he ought to be entitled to a joint and several finding of liability in respect of all
three defendants. It was argued by the first named defendant that there ought to be no finding of liability in respect of the third
named defendant. The evidence of the plaintiff’s engineer Mr Cotter regarding the further damage caused by the works carried out by
the third named defendant was not challenged by the first and third named defendants. Mr Cotter gave evidence, that the reinstated
road surface outside the plaintiff’s property was about 50mm higher than the floor of the plaintiff’s property which rendered it
uninhabitable as water would drain into the property. The plaintiff submits that the first named defendant ought to be liable to the
plaintiff in respect of the damage caused during the works. Mr. Naylor, on behalf of the first named defendant, admitted that the
damage was caused during the course of the works. The first named defendant was the party who brought the nuisance concerned
to the plaintiff’s property and it was their contractors who caused the damage. Irrespective of whether the damage was as a result
of de-watering or failure to support the wall during the connection works, the evidence was that the first named defendant's
representative Mr. Felix Cocker was directly involved with the site works in terms of visiting and inspecting. The evidence was that
the second named defendant carried out the works by means of "method statements" agreed with the first named defendant. The
first named defendant commissioned the drainage works which were initially to be along Clare Street. It then directed a change of
direction for the line of the drain along the canal bank. It commissioned the second named defendant to lay their pipes adjacent to
the plaintiff’s property. In these circumstances the plaintiff submits that the first named defendant ought not be entitled to pass all
such liability to its contractor the second named defendant and seek to avoid direct liability itself to the plaintiff. The first named
defendant commissioned the works which gave rise to the resulting damage to the plaintiff’s property, it ought to be directly liable to
the plaintiff not only on that basis but also on the basis of vicarious liability. The second and third named defendants are also so
liable. It is then a matter between the first and second named defendants as to what degree that liability is apportioned between
them.
4.3 The plaintiff’s has made a claim for damages under the following headings:- (i) reconstruction, (ii) renovation, (iii) rental income
lost, (iv) expert fees incurred, (v) lost development opportunity, (vi) the plaintiff’s own expenses, (vii) lost property value.
(i)Reconstruction:- the parties have been able to agree the cost of reconstruction is €300,000 however this is the only category
which they have agreed.
(ii) Renovation:- After purchasing the property in 2001 for €220,000, the plaintiff carried out substantial works of renovation and
restoration in the property. Evidence was given in that respect by Mr. Farren, the Architect who assisted him in that project. The
evidence was that he spent about €104,000 on renovations to the interior of the main house and the annex. This work proceeded
until 2003. As a result of the damage to the house, the house had to be boarded up in about February 2004 and abandoned as it was
obviously unsafe to use or let out at that stage given the substantial structural cracking there. The plaintiff's evidence was that he
intended to reside in the property himself and rent out the annex portion which he intended to develop into townhouses.
4.4 (iii) Rental income lost:- In terms of loss of rental income, the plaintiff's evidence was that when he purchased the property it
was rented to the McAllister family for £800 per month . The plaintiff continued to rent the house to the McAllister family until January
2003 when they left the property because the general disruption from the nearby works was interfering with their occupation of the
property. After that, the Council agreed to rent the property during the course of the works and they paid €1,000 a month rent to
the plaintiff until September 2004. The plaintiff claims loss of rental income from September 2004 to date, plus loss of rental for the
six months which it will take to reconstruct the property. It was accepted by the valuer's for each party that in the period
2007/2008, rental incomes dropped. However the plaintiff's valuer Ms. Leddin, stated in her evidence that rental values are still strong
in Limerick and she felt that the plaintiff would be receiving rent of €750 per month in 2011, had the damage not been caused to the
property. The loss of rent claimed from 2004 to 2012 and continuing including for the six month period for demolition and
reconstruction works comes to €82,200.00.
4.5 (iv) Expert fees:- The plaintiff also has a claim for costs associated with expert fees. These include the fees of Arup Engineers,
Garwin Farren Architect, Brian Archer Limited and Dunworth and Associates regarding ancillary costs incurred in relation to the
planning application and in dealing with the damage caused and as to the restoration works done to the property. In total expert fees
amount to €30,714.33.
4.6 (v) Lost development opportunity:- The plaintiff’s evidence was that he intended to reside in the renovated property himself and
to rent the annex portion which he intended to develop into townhouses. The evidence was that the plaintiff had submitted a
planning application for two town houses in the annex to the property. In 2003 the planning application was refused on one ground
only, namely that it was premature pending completion of the Limerick Main Drainage Works in the vicinity. Mr. Archer's evidence on
behalf of the plaintiff was that once this prematurity objection was obviated, which he considered it would have been in 2004 when
the main drainage works in the vicinity were completed, then the plaintiff would obtain planning permission for those town houses. Ms.
Leddin's evidence was that these sites in 2004 had a value, on the basis that they had planning permission, of €150,000 each. It was
common case that in general the values of all properties diminished considerably in the years since 2008. In terms of quantum
however, the plaintiff’s loss should be seen from the perspective of values in the 2004/2005 period, when on the basis of the
evidence of Mr Archer, he would have been in a position to develop the annex to the house at that stage and reside in the main
house himself as was his intent. Therefore, he ought to be entitled to recover the loss of developmental value in respect of those two
sites. The plaintiff argues that the evidence established it was probable planning permission would be granted for these annex sites.
Notably it was established in evidence that there were no issues regarding access to the property. In this regard Waterways Ireland
confirmed that a right of way existed in favour of the plaintiff to the property. The sites were worth €150,000 each, Ms Leddin puts a
current value of €50,000 on each site therefore the total loss of value for the two sites comes to €200,000.
4.7 (vi) His own expenses:- The plaintiff gave evidence that he spent a considerable amount of his own time firstly assisting with the
renovations and then meeting experts and lawyers in relation to his case. The plaintiff gave evidence that he acted as a runner during
the renovations and also worked weekends on the project. His accountant has worked out that based on 30 hours per week multiplied
by his current rate of pay he is entitled to €41,280.00.
(vii) Lost property value:- The plaintiff claims that he is entitled to the differential between the market value of the property at the
time of the damage and the current value of the property. Ms. Leddin claims that in 2004, at the time of the damage, the property
had a value of about €500,000. Ms. Leddin presented a comparator of a Lock Keepers house in Celbridge, Co. Kildare and which was
for sale for €575,000. Her evidence was that there was no nearer comparator in the adjacent Limerick area for the property and she
disputed the comparators suggested by the defendants. Ms Leddin suggests that the current value of the property is €100.000.
Therefore the total loss of value is €400,000.00.
4.8 In total the claim in is for €1,108, 194.33 which breaks down as follows:
€300,000 in respect of costs of reconstruction
€104,000 in respect of loss of internal renovations
€82,200 in respect of lost of rent
€30,714.33 in respect of expert fees
€150,000 in respect of lost development opportunity
€41, 280 in respect of time the plaintiff’s time dealing with this matter,
€400,000 loss of value of house.
4.9 The first named defendant argues on the basis of Munnelly v. Calcon Ltd & Others [1978] IR 387 that the plaintiff is only entitled
to receive damages in a sum equivalent to the amount by which the value of his property had been diminished by the acts of the
defendants. The plaintiff contends that the measure of loss to him as a result of the damage to the house ought to be determined on
the basis of the value of the house in 2004/2005 and not at current values. The plaintiff’s evidence was that he intended to reside in
the house. Furthermore there was considerable evidence to the effect that this property was a unique property and there has been
considerable Joss to the plaintiff, notwithstanding that the parties may have agreed a sum for demolition and reinstatement to the
property. The evidence was that the property dated back at least to the 19th century. The age of the property, its vintage and
location and that it had originally been the lock keeper's house and was adjacent to the lock gates referred to in the proceedings
were the reasons the plaintiff purchased the property in the first place. In Kelleher and Kelleher v. Don O'Connor & Co, IEHC 2010 313
16th July 2010 the High Court dealt with the question of damages in the property context. Clarke J held at paragraph 9.1:-
"it is important to start with the fundamental proposition that, in almost all cases, the principal function of the award of
damages is to seek to put the party concerned back into the position in which they would have been had the relevant
wrongdoing not occurred".
The plaintiff submits that this general principle ought to apply in the circumstances here. The plaintiff contends that the Court is
entitled to use whatever mechanism it deems appropriate so as to restore the plaintiff to the position he was in prior to the damage.
The plaintiff ought to be entitled to compensation for that damage against the defendants jointly and severally. The first named
defendant commissioned and directed the offending works and the second named defendant as the main contractor carried out same.
The plaintiff ought to be compensated for his loss so that as far as possible he can be restored to the position he would have been in
had the damage not occurred. This ought not to take into account the subsequent drop in property values generally. In valuing the
house regard might be had to (a) the unique nature of the property and (b) the considerable expense he had incurred on the property
at the time of the damage and (c) the loss of its development value per the annex portion, and (d) his loss of use of same in the
interim together with (e) all ancillary losses.
Submissions on behalf of the first and third named defendant
5.1 Counsel on behalf of the first and third named defendant's, submitted that the evidence given in the hearing establishes on the
balance of probabilities that the damage caused to the plaintiff's property was as a result of the works carried out by the second
defendant which occurred after the 3rd December, 2003. The said works resulted in a sudden movement of the canal wall, as a result
of the second defendant's failure to adequately protect and stabilise the canal wall and the failure to properly support the ground at
the location of the works which took place immediately adjacent to the plaintiff's property. The works (connection of Reception Pit
1.03c to Point B) caused the ground which had been supported by the canal wall to destabilise and led to very severe structural
cracking of the plaintiff's property. The works caused the canal wall to move out towards the centre of the canal and subside
downwards by more than 700mm during the "open cut works". During the open cut works it is accepted by the second defendants
that one of the causes of the settlement of 700mm was the positioning of an excavator on or near the canal wall. The evidence has
established that the second defendants used very heavy machinery for a considerable period of time immediately outside the
plaintiff's property without providing any adequate support to the surrounding ground despite being aware of the damage caused by
their excavator during the open cut works. He argues that it has been established by evidence that during the "connection works" the
second defendants were carrying out piling works immediately outside the plaintiff's property using the aforementioned heavy
machinery including a vibrating machine to dislodge the piles. It was accepted by all the witnesses, including the second defendant's
expert witness Mr. Peters, that carrying out piling works without first ensuring that the surrounding ground was adequately supported
would cause damage.
5.2 The first and third defendant's submit that the sudden movement caused by the second defendant's excavation and piling
activities caused severe damage to the property. As a result of this damage the plaintiff contacted Russell Naylor who visited the
site. The photographs taken by Russell Naylor very clearly illustrate the substantial works that were in progress when he arrived at
the site on the 14th January, 2004. Mr. Naylor in his evidence stated that there was very significant movement recorded on the canal
wall at the northern side (Grove Island). Mr. Naylor's evidence was that between the 10th December, 2003 and the 4th February,
2004 there was a sudden and catastrophic movement at monitoring Points BW5, BW6, BW7, which are 37m, 43m and 49m's
respectively from the nearest dewatering well.
5.3 The evidence given on behalf of the first and third defendants by Mr. O'Sullivan, an expert engineer experienced in settlement,
was that the canal wall was supporting the ground behind it and when the canal wall moved it settled and rotated. This affected the
ground behind it that was supporting the house. Mr. O'Sullivan very carefully examined the cracking in the plaintiff's property and
gave evidence to the effect that the cracking rotated out towards the canal wall and his evidence was that the cracking was not
connected with dewatering. The only persons who saw the damage to the property were Mr. Cotter and Mr. Higgins the expert
witnesses for the plaintiff and Mr. Naylor and Mr. O'Sullivan the expert witnesses for the first defendant and they all agree on the
causes of damage to the house.
5.4 The second defendant called one expert witness, Mr. Peters who concluded in his revised report that dewatering was the most
significant cause of all the damage to the plaintiff’s property. His report and evidence also suggest that the impact of the tunnelling
itself from Manhole 10 to Reception Pit 1.03c was very small, perhaps 2-3mm. His report also suggested that the Reception Pit
Cofferdam at 1.03c was a very significant structure involving very deep excavation; very close to the plaintiff’s property and would
have quite a large zone of influence of perhaps 18m which would go right under the plaintiff’s property. He opined that the cofferdam
should have been located elsewhere and that it posed too much of a risk to the properties. In his report and in his evidence Mr.
Peters accepts that piling work or the removal of piles would cause settlement to occur and in dealing with a sudden event which he
states took place in early February 2004 he took the view that this sudden movement of ground could have been caused by such
piling activities.
5.5 The second defendants claim that dewatering was not required during the tunnelling from Manhole 10 to the Reception Pit 1.03c.
The evidence of Mr. Curran a witness, for the second defendants was that he was against continuous dewatering and was of the
view that dewatering should be used only as and when required. The first defendants' resident engineer Mr. Naylor gave evidence
that dewatering on a continuous basis was required and he stated that the first defendant had a Geotechnical Engineer on site, Mr.
Miles Friedman who was insisting that dewatering was necessary. There is also the report from Project Dewatering Limited, a
specialist dewatering company which said that dewatering was necessary. It further stated that it would only result in 0.1 mm of
settlement and it advised that there was no risk of residual or latent settlement. It is to be noted that this firm were retained by the
second defendants tunnelling experts, Messrs A.E. Yates Limited, to advise them in relation to dewatering. The second defendants, as
required by the terms and conditions of contract, provided a method statement for the tunnelling operation which included
dewatering. Mr. Naylor gave evidence that it was prudent and reasonable to use continuous dewatering in light of the severe damage
caused by the failure of the tunnelling which began at Manhole 1.04 in which there was massive settlement and no dewatering. Mr.
Naylor in his evidence stated that the dewatering was seen as a precautionary measure rather then a reactionary measure. The
correspondence on the issue of dewatering on the 4th and 6th November, 2003 and minutes of site meeting 5th November, 2003,
show that there was a disagreement between Mr Curran and Mr Naylor in relation to the necessity of continuous dewatering. The
evidence of Mr. Curran was to the effect that he was against continuous dewatering and felt that he was being ordered by Mr. Naylor
to perform this. Mr. Naylor in response stated that all he was doing was insisting that the second defendants adhere to their own
method statement which called for continuous dewatering.
Paragraph 2 of the letter of the 6th November, 2003 provides that the dewatering:-
"will remain in operation throughout the drive unless monitoring indicated that it is counter productive with regard to
settlement"
It is submitted that this is clear evidence that the second defendants, the first defendants and the Engineer White Young Green had
reached agreement that there would be continuous dewatering as per the second defendants method statement. The second
defendant did not reply to the letter of the 6th of November, 2003 objecting to the contents of the above paragraph and there is no
evidence of any further complaints being made in relation to the issue and it is submitted that the reason for this is that there was
finally agreement as to the contents of the letter of the 6th of November, 2003.
5.6 It is submitted by the first and third defendants that the second defendants have failed to establish on the balance of
probabilities that dewatering caused the damage to the plaintiff’s property. The dewatering in question was deep well dewatering with
the wells driven to a depth of eight meters. In his evidence Mr. Peters agreed with the fact that this was deep well dewatering. The
ground conditions at the site of the tunnelling from Manhole 10 to the Reception Pit at 1.03c would not lead to movement at the
surface, caused by deep well dewatering. The evidence of Mr. Higgins for the plaintiff, Mr. O'Sullivan for the first named defendant
and the project dewatering report all support this contention. The cracking in the plaintiff’s buildings indicated movement to the
north, towards the canal wall and not to the west towards the nearest dewatering well (W3). The cracking is not consistent with the
cracking one would expect to see as a result of dewatering. Cracking from dewatering should be radial whereas the cracking evident
in Mr. O'Callaghan's house was rotational and as a result of the ground moving towards the canal.
5.7 The first and third defendants also argue that if it were the case that deep well dewatering might have an influence on the
surface then evidence showed that the maximum limit of the zone of influence is approximately 15m as indicated in Mr. Peters Report.
All of the two storey buildings are outside the zone of influence and all of the two storey buildings have suffered significant movement
and cracking. The gable end of the property was severely damaged by cracking and it is 30 meters from dewatering Well 3, the
closest to the plaintiff’s property. The sudden movement referred to in the evidence which occurred on the 13th or the 14th of
January 2004 occurred over five weeks after the dewatering was turned off on the 3rd December, 2003. The damage to the Northern
Canal Wall on the Grove Island side cannot be explained by dewatering but can only be explained by inadequate temporary support
provided to the ground during the connection works carried out by the second defendant. Mr. Peter's original report submitted to the
court and his subsequent revised report show the nearest dewatering well at a point 10m from the plaintiff’s property. The correct
position should have been 15.7m from the two storey building. In Mr. Peters original report he based his findings and conclusions on
the premise that dewatering took place over a two month period. Mr. Peters accepted on cross examination that the revised report
had to reflect that the impact of dewatering (if any) had to be lessened greatly with the reduction in the period of dewatering from
two months to one month. Mr. Peters prepared two reports, both based on a 1Om separation between the nearest well and the two-
storey buildings. His conclusions did not change, nor did his evidence even though he accepted that the separation was actually
15.7m. It is significant that Mr. Peters never saw the inside of the plaintiff’s property, his first site visit was in October 2011. It should
be noted that Messrs Higgins, Cotter, Naylor and O'Sullivan all visited the site at the critical time, 2004 and reached similar
conclusions, that a sudden ground movement caused the damage. It is therefore submitted that Mr Peters report cannot be relied
upon.
5.8 Counsel for the first and third defendants submitted that the second defendants were negligent and acted in breach of contract
in that they failed to provide a method statement for the connection between Reception Pit 1.03c and Point B, as required by Clause
14 of the General Terms and Conditions of Contract. The second defendants also commenced this stage of the works without
providing notification to the Engineer. The second defendants failed to adequately support the ground in the vicinity of the plaintiff's
property when they knew that failure to do so was likely to cause damage to the said property. The second defendants carried out
piling works without ensuring that the ground was properly supported and they failed to heed the warnings given to them at site
meetings about the settlement which was occurring on the canal walls and the effect that that settlement could have on the
plaintiff's property.
5.9 The assertion made by Mr. Curran that the route chosen to complete the works (S Bend) was at the behest of the first defendant
is incorrect. The evidence establishes that the route was chosen following representations by Waterways Ireland. The evidence
establishes that the route chosen was to avoid any possible damage to the Waterways Ireland Lock which had been renovated at
considerable public expense. It is submitted that all of the works including the connection between 1.03c and Point B are temporary
works completed under the ordered variation and are the responsibility of the contractor in accordance with clauses 7, 8, 14, and 22
of the contract. It is submitted that the responsibility for these works did not transfer to the Resident Engineer at any stage. The
evidence of Mr. Higgins in this regard was to the effect that under the General Conditions of Contract the contractor was responsible
for any issues caused by the carrying out of these works. In the course of his evidence Mr. Curran made reference to Clause 20 (3)
"Excepted Risks". Clause 20 deals with the responsibility of the contractor for the care of the works and the responsibility of the
contractor to make good, at his own cost, any such damage to the works. This clause has no relevance to the indemnity issue which
is clearly covered by Clause 22.
5.10 These defendants argue that the evidence in the case does not establish on the balance of probabilities that the paving works
carried out by Murphy International Limited contributed in any way to the damage caused to the plaintiff's property. Mr. Higgins and
Mr. Cotter indicated that they were making assumptions in relation to the equipment that was used by Murphy International Limited.
They did not have the benefit of Mr. Ryan's evidence to the effect that only light vibrating equipment was used and a 300mm zone
was left between where their work finished and the front face of the plaintiff's property. This work did not cause a problem for the
house. Furthermore because the supporting ground underneath the house had been compromised by the time of Mr. Cotter's first visit
on the 30th January, 2004, the support for the house had to be restored and this restoration could only be achieved by piling. The
site is extremely restricted piling could only be undertaken within the house and the only economical way to do this is to demolish the
house. Any cracking that occurred after the end of January 2004 did not alter this necessity.
5.11 The plaintiff has made a claim for damages of €1,108, 194.33 which breaks down as follows:- (i) €300,000 in respect of costs of
reconstruction , (ii) €104,000 in respect of loss of internal renovations, (iii) €82,200 in respect of loss of rent , (iv) €30,714.33 in
respect of expert fees, (v) €150,000 in respect of lost development opportunity, (vi) €41, 280 in respect of the plaintiff's time dealing
with this matter, (vii) €400,000 loss of value of the property. These defendants had the following observations;
(i) Reconstruction:- It is agreed between the parties that if damages are to be measured on the basis of demolition and
reconstruction of the premises, the cost amounts to €300,000.
(ii) Renovation- The plaintiff’s claims for €104,000 in respect of renovations. In cross examination by Mr McKeon the plaintiff admitted
that he did not have receipts vouching this €104,000 he claims to have spent. Mr. Naylor gave evidence that the only works he saw
taking place were stripping of timbers and painting. It is submitted that this work would not cost €104,000, and the evidence does
not support the plaintiff's claim that he spent €104,000 on renovation works.
(iii) Rental income lost- evidence in relation to values was given by PJ Power auctioneer on behalf of the Council. Unlike Ms Leddin
when Mr Power was compiling his expert report he compared the property with other properties in the area. On the basis of this
comparison he determined that the rental value of the property in 2005 was €600 per month. Mr Power pointed out that problems with
access to the property and parking would make it difficult to rent this property. The total for lost rent according to Mr Power is
€67,000 whereas Ms Leddin values lost rent at €82,200.
(iv) Expert fees. The plaintiff also has a claim for costs associated with expert fees. These include the fees of Arup Engineers, Garwin
Farren Architect, Brian Archer Limited and Dunworth and Associates regarding ancillary costs incurred in relation to the planning
application and in dealing with the damage caused and as to the restoration works done to the property. In total expert fees amount
to €30,714.33. These defendants argue that these costs were not properly proved in evidence.
(v) Lost Development opportunity:- The plaintiff claims €200,000 in respect of lost development opportunity. The plaintiff’s application
for planning permission for two town houses was refused on the basis of prematurity. There were no guarantees that if he applied
again he would be successful. The local Authority would have been concerned with the absence of open space, the density of the
development, and problems with access. Mr Power values the house and sites together at a value of €100.000. Ms Leddin values the
house today at €100.000 and the sites today at €50,000 each.
(vi) His own expenses- The plaintiff’s that his claim of working 30 hours per week on the renovations while at the same time he was
holding down a full time job was not credible. (vii) Lost property value- The plaintiff has claimed €400,000 in lost property value on
the basis that Ms Leddin valued the property at €500,000 in 2004 and €100,000 today. It is submitted that the plaintiff is not entitled
to both reconstruction cost and the loss in value of the property. Mr Power valued the property in 2004 at €175,000. He stated that
after the plaintiff purchased the property in 2001 the area had fallen into decline and experienced problems with anti social behaviour.
Ms Leddin values the house today at €100.000 and the sites today at €50,000 each. Mr Power values the house and sites at a total
of €100.000. Mr Power took into account the problems with parking in arriving at his values, and the absence of any open space with
the house or sites.
Submissions on behalf of the second named defendant
6.1 Roadbridge and its experts are of the opinion that the level of dewatering caused ground settlement and consolidation causing
cracking to the plaintiff’s house and annex. In their view dewatering was the primary cause of the damage to the plaintiff’s premises.
Allied to this was the unavoidable damage which would be caused by the tie in works and their proximity to the plaintiff’s buildings.
The plaintiff’s expert evidence was that a combination of activities in the vicinity of his house caused settlement to his property. The
evidence on behalf of the first named defendant was that the dewatering was irrelevant and that the greater part of the damage was
caused to the plaintiff’s house by the removal of the canal wall during the tie in or failure to support the ground during this process
including the removal of sheet piles at the cofferdam in the vicinity of the reception pit. However, Eamon Curran on behalf of
Roadbridge testified that he had been opposed to the tie-in occurring in the vicinity of the plaintiff’s house but was instructed to
construct the tie-in and S bend connecting to a large reception pit in the vicinity of the plaintiff’s premises.
6.2 Eamon Curran said that the intense dewatering of the tunnel which occurred by means of the three wells caused the undermining
of the structures leading to the damage to the plaintiff’s house. He gave evidence that damage was apparent to the annex wall at an
early stage during the works and that it was no surprise to him that subsequently damage developed in the plaintiff’s house. The
tunnelling works were finished by 3rd December, 2003. By this date monitoring points U and Von the annex of the plaintiff’s house
showed movements of 25 millimetre and 27 millimetres, increasing to 35mm and 39mm respectively by 19th December, 2003. Mr Curran
in his evidence explained why he raised concerns with respect to de-watering. He cited inter alia Roadbridge's experience at
Corcanree Industrial Estate where dewatering caused significant settlement. He relied upon his knowledge of the type of soil which
would be encountered in the tunnel drive between Manhole 10 and ISU 1.03B; the impact which dewatering to the extent of 1,000
cubic metres per well per day would have; the amount of settlement which would occur; and the likely impact this settlement would
have on the buildings adjacent, particularly the plaintiff’s. The second named defendant's expert Geotechnical Engineer Mr Peters
gave evidence that in his view dewatering was responsible for 50-60% of the damage to the plaintiff’s property.
6.3 The fact there was an open cut section along the bed of the canal meant that it was unavoidable some degree of interference
with the canal walls themselves would take place which was acknowledged by all parties. Hence, Roadbridge agreed a provisional sum
of IR£35,000.00 for any such remedial works. The status of the canal walls were known to be only marginally stable from a report
commissioned from Dr. Eric Farrell in 1999. A significant factor in the settlement of the property was the decision directed by Mr
Naylor to construct an S bend structure with the tunnel running from manhole 10 to a reception pit which in turn was to be tied into
ISU 1.03B. The latter structure was to be effected by a cofferdam. Mr Curran in his evidence expressed the unequivocal view that as
the cofferdam was adjacent to the plaintiff’s house and as it involved works such as the driving in and removal of sheet piles using
heavy machinery, it was inevitable that some damage to the buildings at that location, primarily those belonging to the plaintiff. In his
evidence to the court Mr Peters stated that in addition to the dewatering there were a combination of events which caused the
balance of the damage. In his view the reception pit ought not to have been constructed where it was. This was done solely on the
instruction of Mr Naylor who directed that Roadbridge install the pit at this location.
6.4 No evidence was adduced by any of the defendants that the plaintiff was not entitled to succeed in the claim. The issue for
determination is as to the respective liability of the defendants. The contract entered into between the Council and Roadbridge was
pursuant to the Conditions of Contract and Forms of Tender Agreement and Bond for Use in Connection with Works of Civil Engineering
Construction Third Edition 1980 (as revised) of the Institution of Engineers of Ireland. It is accepted that pursuant to clause 2, the
resident engineer had no authority to relieve the contractor of any of his duties or obligations or to make any variation of or in the
works. Clause 8 set out the general obligations of the contractor. The contractor was obliged under the contract to construct,
complete and maintain the works and to take full responsibility for the adequacy, stability and safety of all site operations and
methods of construction provided however that the contractor was not to be responsible for the design or specification of the
permanent works or of any temporary works designed by the engineer. Roadbridge submitted that the instruction provided by the
engineer together with his design and construction of the S bend, the reception pit location and the dewatering removed any
responsibility from Roadbridge for these works. Clause 22 provides at subparagraph 1 that the contractor is liable and obliged to
indemnify the employer against all losses or claims which might arise out of or in consequence of the construction and maintenance of
the works and against all other claims. However, it is important to note the following namely in 22(1)(a) that the liability of the
contractor is to be reduced proportionately to the extent that the act or neglect of the employer his servants or agents may have
contributed to the loss or damage, that there is no obligation to indemnify where as set out in clause 22(1)(b)(4) damage (other than
that resulting from the contractors method of construction) arises which is the unavoidable result of the construction of the works in
accordance with the contract. Allied to this provision is the obligation at clause 22(2) that the employer is obliged to indemnify the
contractor from claims which are referred to in the proviso to sub clause 1 of clause 22 while the employer's liability to indemnify is to
be reduced proportionately to the extent that the act or neglect of the contractor or its subcontractors may have contributed to the
damage. Roadbridge are relying upon the obligation set out in clause 22(2) for the purpose of obtaining a full indemnity in these
proceedings. There are a number of circumstances which Roadbridge say constitute an act or neglect, an unavoidable result of the
construction of the works or an excepted risk for the purposes of clause 22. First, the instruction given to construct a reception pit in
the vicinity of the plaintiff’s house. Second the obligation to tie in by an S bend the works between the end of the open cut section
in the canal bed through the canal wall to the reception pit. Third the obligation to maintain continuous dewatering on the tunnelling
section from manhole 4 notwithstanding the objection of the contractor. Fourth the failure to permit the contractor to dewater as
required despite this forming part of the temporary works. Fifth the fact that responsibility was taken by the employer through the
engineer for the design and construction of these works in the immediate vicinity of the plaintiff’s property notwithstanding the likely
effect which this would have upon his property.
6.5 The 2nd defendant argues that, in interpreting the contract, the court has to decide what the intention of the parties was having
regard to the language used in the contract itself and the surrounding circumstances. The general principles of interpretation
applicable under Irish law were set out by the Supreme Court in Analog Devices BV & Ors v Zurich Insurance Company [2005] IR 274
The Supreme Court endorsed the view expressed by Griffin J. in Rohan Construction Limited v Insurance Corporation of Ireland plc
[1988] ILRM 373 where he set out the view at p391 that:-
"The cardinal rule is that the intention of the parties must prevail but the intention is to be looked for on the face of the
policy, including any documents incorporated therewith, in the words in which the parties have themselves chosen to
express their meaning. The court must not speculate as to their intention, apart from their words, but may, if necessary,
interpret the words by reference to the surrounding circumstances. The whole of the policy must be looked at and not
merely a particular clause".
Mr Lucey SC for the second defendant submitted that the interpretation of the contract is straightforward. In an analysis of the
factual issues it demonstrates that Roadbridge were instructed and directed to construct the works in accordance with the design of
the employer in this area and that the responsibility ultimately lay with the employer for its act in usurping the functions of the
contractor. The position of Limerick City Council with regard to the instruction to dewater appears to be that it was included in the
method statement furnished to them by Roadbridge which was compiled by Project Dewatering in July 2003. Limerick City Council seek
to rely on the fact that this method statement provided for very little settlement in the event of dewatering. Mr Lucey submitted that
Roadbridge had worked in the ground where the tunnelling was to take place and had determined that given the nature of the soil it
was satisfactory merely to dewater as and when necessary. This was the expert assessment of Eamon Curran which was ignored.
There was a failure on behalf of Limerick City Council to conduct any ground investigations in the new route chosen. Roadbridge made
suggestions as to the route to be followed which were overruled. The overruling involved a tie in through the canal bank in front of
the plaintiff's property. An analysis of the clay soil encountered at manhole 1.04 was critical and demonstrated that there was no
need for continuous dewatering. Notwithstanding the physical evidence an instruction was given to continuously dewater. No regard
appears to have been had to the effect which this had on the soil and on the likely settlement in its vicinity. As a consequence not
only is the contractor not liable to indemnify the employer pursuant to the provisions of clause 22.1 but the contractor is entitled to
rely upon the provisions of the indemnity set forth in clause 22.2. There were no acts or neglect on the part of the contractor which
contributed to the damage as a consequence of which there should be no reduction in the indemnity to be afforded to the
contractor.
6.6 Further damage was caused to the plaintiff’s property by the actions of Murphy in constructing a boulevard outside the house and
raising the level of the street. Only one witness gave evidence on behalf of Murphy, Mr. Liam Ryan who did not have available to him
any documents upon which his evidence was based. He sought to minimise the extent of the damage caused to the plaintiff’s house
by these works. However, such evidence can be contrasted with the views of Arup engineers who attended at the plaintiff’s house
when Road bridge were carrying out works, after Roadbridge had concluded works and after Murphy had executed its pavement
works. It was their view that there was a contribution in the region of I0 to 15% by the Murphy works with more settlement having
been caused. While John Higgins, engineer was reluctant to put a percentage on the damage caused by Murphy, he was of the view
that there had been some further damage inflicted. Gary Cotter engineer estimated that the Murphy works triggered further
movement and its contribution to the damage was in the region of 10 to 15%. Mr Cotter highlighted the significant issue caused by
the raising of the footpath outside which had a major impact as it was now 50mm higher than the plaintiff’s property
6.7 With regard to the plaintiff’s claim for damages in the sum of €1,108,194.33, the 2nd defendant deals with each of these as
follows;
(i) Reconstruction costs:- it is agreed between the parties that if damages are to be measured on the basis of demolition and
reconstruction of the premises, the cost would amount to €300,000.
(ii) Renovation costs:- the plaintiff alleges that he performed €104,000 of renovation works in 2003 before the cracking occurred in
January, 2004. During cross-examination by Mr Lucey the plaintiff stated he paid his builder Mr. Clohessy €104,000. The plaintiff was
asked did he pay VAT. The plaintiff said that he paid €104,000 inclusive of VAT. The plaintiff was asked whether he paid entirely in
cash, he responded that he made four or five payment of cash which included €20,000 at the start of the project and €20,000
midway through the work. The plaintiff stated that he knew Mr. Clohessy well and he obliged him by paying him in the manner which
Mr Clohessy requested. It was put to the plaintiff that when he was asked to provide all receipts in relation to the renovation work he
was unable to provide any documents of relevance. The plaintiff was asked why in 2009 he claimed €40,000 in respect of the
renovations whereas he now claims €104,000. It was put to him that he surely knew in 2009 what he had spent in 2003. He
responded that €104,000 was the most accurate figure he could arrive at. The second defendant submits that this evidence does not
support the plaintiff's claim that he spent €104,000 on renovation works.
(iii) Rent lost:-The plaintiff claims loss of rental income of approximately €82,200 ongoing. The claim for losses based on loss of rental
is overstated. It fails to include any consideration of the market, cost of maintenance, cost of rental periods during which the
property might not be occupied.
(iv) Expert fees:- No issue arose with the nature of the fees due to ARUP, however the evidence of Garwyn Farran did not support
the extent of works nor of his fees. Mr Farren was asked had he notes recording time spent on the job. He stated that he had
destroyed these. It was submitted that it was not credible that Mr Farren came up with the same figure as Mr Clohessy of €104,000
for the cost of the works done when he had no notes.
(v) Lost development opportunity. The plaintiff claims for loss of development opportunity. This relates to a claim for two sites which
the plaintiff alleges that he would have developed and as a consequence has lost €200,000. During cross-examination by Counsel for
Roadbridge it was put to the plaintiff that the proximity of the sites to a petrol station would make them undesirable. Evidence was
adduced on behalf of Roadbridge from Des O' Malley, valuer and Steven Dowds, planner. It was the evidence of Des O'Malley that the
sites only had a value of €25,000 each in 2004 and have no value today. The evidence of Steven Dowd planner was significant. He
was aware that planning permission for the sites had been refused as premature in 2003. While prematurity was the only reason
stated, in his view there were other reasons why planners were likely to have refused permission. If the plaintiff had resubmitted an
application for planning for the two sites between 2004 and 2007 the evidence of Mr. Dowd's was that the application was likely to
fail for a myriad of reasons including access, density, open space, aspect and changes in policy and standards including the
introduction of the Limerick City Development Plan of 2004. This plan has been replaced by the 2010 Plan. Both plans contain
standards and requirements which could not be met on site. As a consequence the second defendant submits that the basis of the
claim for losses arising out of failure to potentially develop or sell sites is untenable.
(vi) As regards the plaintiff claim for €41,280 in respect of his own time dealing with this matter. The second defendant argues that
this claim is not supported by any evidence.
(vii) Loss of value of house. Mr O'Malley of Sherry Fitzgerald gave evidence that the area where Mr Callaghan's property is located is
in decline, and has a lot of problems with anti social behaviour and that there are a lot of derelict properties in the area. In cross
examination Ms Leddin agreed that there are now problems with anti social behaviour. The plaintiff has claimed for loss of value of the
property. This is claimed at €400,000 on the basis that the property then had a value of €500,000 but now has a value of €100,000.
It is submitted that there is a clear element of double accounting in the claims made as the plaintiff is not entitled to the loss in value
of the property together with reconstruction costs. It was the evidence of Des O'Malley that the property in fact at the height of the
market was only worth in the region of €190,000 and now in a habitable state was only worth in the region of €90,000. In its current
poor condition he was of the view that it was only worth €55,000. This evidence is important as it shows that in fact the plaintiff has
a loss only in the value of the property in the region of €135,000. The evidence in this case is that the plaintiff retains a property
with a certain value. There were works required to the property before any damage was inflicted in the course of contract 3.2. It is
the submission of Roadbridge that the cost of reinstatement is greater than the amount by which the value of the property has
diminished. In those circumstances the measure of damages ought to be the difference between its value pre damage at €190,000
and its value post damage at €55,000.
Decision of the Court
7.1 It is agreed by all parties that the plaintiff is entitled to compensation for the damage to his house at Canal Bank, Clare Street,
Limerick. In issue between the plaintiff and the defendants is the measure of this damage. The first and third named defendants claim
the damage to the house was caused in the first instance by the second defendant whose tunnelling work on site caused the canal
wall to subside, thereby causing the ground adjacent to the plaintiff’s house to move and cause fatal cracking to occur in the house.
This was compounded by their work subsequently in relation to the connection work and the reception pit. The second defendant
claims that this cracking was caused by the dewatering process during the critical phase of the tunnelling ordered by the first
defendant's resident engineer. They had opposed dewatering fearing it would undermine the ground and cause it to subside. They had
been forced to dewater and had warned they would not be responsible for any damage caused thereby. The second defendant also
claims that some of the damage to the plaintiff’s house was caused by the third defendant when they finished off the reinstatement
of the pavement on the canal bank. Their use of machinery to pile the cobbles on the pavement and their finishing the road surface
above the level of the door sill of the plaintiff’s house caused further damage.
7.2 Thus, the first question for the Court to address is the respective levels of liability of the defendants among themselves. The first
defendant indicated at the outset of the hearing that they were taking up the defence on behalf of the third defendant. They also
argued that the evidence showed that the third defendant had no liability for any damage. The evidence that I heard in this case has
satisfied me that this is correct. The work done by the third defendant was over one year later and was to finish off the canal bank
with a fine cobbled boulevard. The evidence, which I accept, was that the machinery used to lay the cobbles did not have the
strength to create vibrations sufficient to cause any structural damage to the house. Moreover, a 300mm zone was left between their
work and the plaintiff’s house. Indeed, all the evidence points to the massive works surrounding the open cut and tunnelling as being
the obvious source of the damage caused to the house. Furthermore, the fact that the level of the pavement is now very slightly
above the level of the door sill in the house is an irrelevance in the context of the requirement now admitted by all that the house
must be demolished and rebuilt. The evidence was that any differential problem involved can be easily resolved in that process. I find,
therefore, that the third defendant has no liability in respect of the plaintiff’s claim.
7.3 Liability lies therefore between the first and the second defendants. Having heard all the evidence in this case, it seems to me
that this entire operation along the canal bank was from the outset a project fraught with peril for the structural integrity of the
adjoining buildings. It is common case that the structural stability of the almost two hundred year old canal wall was very doubtful.
The second defendant argues that the first defendant is responsible because, in relation to the tunnelling works, they insisted, over
the second defendant's strenuous objections, on continuous dewatering. In relation to the connection works and coffer dam, the
second defendant argues that its authority in this respect was usurped and they were forced by the first defendant's engineer to do
the connection in this way and in a manner designed by him. The first defendant insists that dewatering is a red herring and had
nothing to do with the problems encountered by the plaintiff. In relation to the connection works, the first defendant relies on the
absence of the method statement that should have been furnished to them by the second defendant before they commenced the
connection works. They also say this work commenced without their knowledge. They note, finally, in this regard, that the reason for
the S bend and cofferdam being located where they were was because of representations from Waterways Ireland. Their fear was
that the adjacent lock gates of the canal would be adversely affected by tunnelling under them. These gates and the lock itself had
only recently been restored at considerable public expense.
7.4 Dealing first with the dewatering issue. I heard evidence in this regard from Joseph O'Sullivan, Consultant Engineer, who is
experienced in settlement problems. He had also experience in dealing with about five hundred cases of dewatering problems in Cork
where he said it is a sensitive issue. Mr. O'Sullivan examined the cracking in the plaintiff’s house. He noted that the cracking rotated
out towards the canal wall. He stated his firm view that the damage he saw was not consistent with dewatering damage. He noted,
and it was accepted by all parties, that what was involved here was deep well dewatering. This of itself should not cause damage on
the surface. Even if it could, the damage caused would be radial and would be within a certain zone of influence. The damage here,
he stated, was not radial and was clearly outside the zone of influence. He noted, and ultimately it was accepted by the second
defendant, that Mr. Peters, a geotechnical expert who was called as a dewatering expert by the second defendant had wrongly
positioned the nearest well to the house when he drafted his report initially. Contrary to this initial report, the well was actually
located outside the 15 metre zone of influence of dewatering.
7.5 Mr.Peters gave evidence that dewatering led to settling and damage to the house. It was, he thought, the most significant cause
of settlement. He considered this caused fifty per cent to sixty per cent of the house damage. As noted above, however, Mr. Peters
had worked on some incorrect assumptions. He agreed he had thought there was two months of dewatering whereas in fact there
had been just one. He thought the position of the nearest well for dewatering (Well 3) was closer to the house than it actually was.
He had thought it was twelve metres whereas it was, in fact, located 15.7 metres from the nearest gable wall of the house. These
are significant errors made in his original assessment of the situation. Moreover, he never inspected the house internally but worked
off Mr. O'Sullivan's photographs. I note also that Mr. Peters gave his opinion on dewatering six years later and entirely on the basis of
his analysis of data. All the experts at the time were agreed it was necessary. Moreover it was albeit after much discussion and
dissent from Mr. Curran, included in the method statement. Mr. Peters was obliged to twice revise his report on the basis of further
information he received including evidence he had heard in court during the hearing. He seemed initially unsure as to whether this was
deep well dewatering but conceded in the end that it was.
7.6 The issue is a difficult one to resolve. The Court must decide it on the balance of probabilities. I consider Mr. O'Sullivan to have
been a more convincing witness. Despite sticking to his original assessment even after having discovered his location of Well 3 was
incorrect, that the period of dewatering was half of what he originally believed and his acceptance in cross-examination that this was
in fact deep well dewatering, Mr. Peters' evidence seemed much less convincing. I note also that he had not inspected the interior of
the house whereas Mr. O'Sullivan had. Mr. Cotter, Mr. Higgins and Mr. Naylor also had inspected the interior. All were agreed that the
damage to the house was not caused by dewatering. It seems to me that the fully accepted instability of the canal wall together
with the impressively massive and heavy machinery that was deployed on site in close proximity to the plaintiff's house combined
together to cause such differential movement of the subsurface support as to cause fully the damage sustained thereto. In my
judgment dewatering as a main or even partial cause has not been sustained on the evidence. It must be noted moreover that
following considerable discussion of this matter, at the demand of the resident engineer, Mr. Naylor, of Geotechnical Engineer Miles
Friedman and Project Dewatering Ltd., the second defendant had provided in their method statement that dewatering would remain in
operation throughout the drive. Even though it is clear he disagreed with Mr. Naylor on the need for it, I find that Mr. Curran bowed
to the inevitable and as indicated in the letter of 6th November, 2003, agreed to the continuous dewatering. On this basis even were
dewatering to have been found to be responsible in full or in part, it appears to me that this would not assist the second defendant
who had under its contract undertaken the work and the risk thereof including that of dewatering. Responsibility for damages caused
by this stage of the works is entirely that of the 2nd defendant.
7.7 The difficulty in resolving this dispute grows complex in attempting to determine whether the primary cause of the damage to the
plaintiff's house was the initial tunnelling works or the connection works which involved the construction of the S bend and cofferdam.
After considering all the evidence herein, it seems to me that the extent to which responsibility for the damage can be allocated
between these two distinct phases of the works involved is all but unknowable. All the experts agreed that the two hundred year old
structures and the ground upon which they lay, had done some moving over that long period of time. The structures above and below
ground had come to terms with each other over those two hundred years. If the stability of any part of the supporting canal wall or
the ground was compromised, then all structures would take some time to regain the balance between themselves. How long this
would take was unpredictable. What weak or strong areas would remain and how strong or weak they would be must, it follows, be
unknowable. Thus, it seems to me that the Court is forced to the conclusion that the cause of the damage to the plaintiff's house
must be allocated on a fifty/fifty basis between these two stages of work because there is quite simply no otherway to determine the
relative liability therefor.
7.8 The necessity to divide liability between the two different stages of work arises, in my view, because the nature of the
relationship between the parties seemed to undergo some significant change when it came to the connection and cofferdam stage of
the works. The liability of the second defendant for the first stage has already been found by me, but what of the second stage -the
connection works?
The nature of the relationship during the "connection stage"
7.9 It is clear from the evidence that during the "tunnelling" stage, relations between the first and the second defendant became
strained. Dewatering was the first real example of this. There was disagreement at the outset over whether there should be a straight
drive under the canal lock, as Mr. Curran preferred, or an S bend and cofferdam, as Mr. Naylor preferred, and ultimately ordered. As
noted above, there was strong disagreement on the dewatering issue. It seems to me on the evidence that the lead parties lost
confidence in each other. John Higgins, former director of Arup and Consultant Engineer, stated in his evidence (13/12/2011) that
there seemed to be confusion as to who was in charge. Mr. Naylor stated in his evidence (21/12/2011) that there was a lot of
friction. He, for instance, was never happy with the open cut, yet it went ahead. Mr. Curran opposed the S bend, yet it went ahead.
He stated in his evidence (9/02/2012) that after the letter of the 4th November, 2003, he considered that Roadbridge, as contractor,
was under the direct control of the resident engineer. He stated he no longer had control. Yet he was the man in charge on the
ground. He agreed there was no method statement in regard to the "connection works" but he had sent a letter and considered he
had supplied sufficient information on what he proposed to do and was not asked for more. Mr. Curran summed it up by saying in
evidence that it was an unusual situation and one he had not come across before. Mr. Naylor stated unequivocally that the
connection works started without his or his client's knowledge. That, he says, is why the first defendant did not shout stop, as he
put it. It is hard to credit that the connection work could start without the first defendant's knowledge. If it actually did, it is most
surprising since bearing in the mind the nature of the work and the manifest lack of confidence all round, the first defendant should
have been keeping the closest possible supervision over the work. Mr. Curran did state in evidence that Felix Cocker for Limerick Main
drainage was on site every day. Mr. Naylor doubted this and Mr. Cocker did not give evidence. On the evidence, Mr. Naylor did seem
very surprised that the work had started.
7.10 In order to deal with liability for this part of the works, the Court must first look to the contractual terms involved. These are
contained in the Conditions of Contract and Forms of Tender, Agreement and Bond, 3rd Ed. 1980 and specifically, paragraph 22
thereof. This provides as follows:
"22(1) The contractor shall be liable for and shall indemnify and keep indemnified the employer against all losses and
claims for injuries or damage (save as otherwise provided in paragraph (b) hereof) to any person or property whatsoever
(other than the works for which insurance is required under Clause 21 but including surface or other damage to land being
the Site suffered by any persons in beneficial occupation of such land) which may arise out of or in consequence of the
construction and maintenance of the Works and against all claims, demands, proceedings, damages, costs, charges and
expenses whatsoever in respect thereof or in relation thereto.
Provided always that:-
(a) the contractor's liability to indemnify the employer as aforesaid shall be limited to the sum stated in the appendix to
the form of tender and (in accordance with the operation of sub-clause (2) of this clause) shall be reduced
proportionately to the extent that the act or neglect of the employer, his servants or agents, may have contributed to
the said loss, injury or damage;
(b) …
(iv) damage (other than that resulting from the contractor's method of construction) which is the unavoidable result
of the construction of the works in accordance with the contract; ..."
For the purposes of this judgment, it seems to me that the above may be summarised as follows:-
(1) the contractor is liable and must indemnify the employer against all claims for damage (save for paragraph (b)
reservations),
(2) liability may be reduced proportionately to the extent that the act or neglect of the employer may have contributed
to the loss,
(3) the contractor is not liable for damage which is the unavoidable result of construction in accordance with the
contract.
7.11 The questions that arise for the Court therefore seem to me to be (1) Was there any act or neglect on the part of the employer
that may have contributed to the damage that I have found was caused by the "connection" stage of the works, i.e. fifty per cent of
the damage to the plaintiff’s property; (2) Was the damage the unavoidable result of the construction which was done in accordance
with the contract? On the evidence that I have heard, it seems to me that the first and second defendants are jointly responsible for
the breakdown in mutual confidence and in the chain of command that resulted in the connection works being executed in such a way
as to have contributed, as I have already found, to fifty per cent of the damage caused to the plaintiff’s house. In respect of the
first defendant, I find that this amounts to an act or neglect on their part that contributed to the damage to the plaintiff’s property.
In relation to the second defendant, on the balance of probabilities I do not consider that the damage caused was the unavoidable
result of the construction done in accordance with the contract. In my judgment the connection works as ordered could have been
constructed in a way that would have avoided damage to the house had proper securing been done of the cofferdam and tunnel
connection. Piles were removed too soon from the dam. Massive machinery was used too close to the plaintiff’s house. Photographs
of the work in progress show it was carried out with scant regard for the adjacent house.
Thus the relative responsibility of the two defendants in relation to the connection works is, in my judgment, equivalent because
although the work was carried out without due care to avoid damage to the plaintiff’s house, this all followed from the breakdown in
the chain of command on the ground. One thing had to follow the other and so I find that in respect of the "connection works" the
first and second defendants bear responsibility on a fifty per cent basis each. This means that I find liability in respect of the damage
caused to the plaintiff’s property is to be apportioned on the basis overall of seventy five per cent to the second defendant and
twenty five per cent to the first.
The quantum of damage
7.12 The plaintiff claims under a number of headings: (a) loss of house and cost of reconstruction and associated works agreed at
€300,000; (b) loss in respect of the internal renovation of his house up to the date of damage, i.e. December 2003, (c) loss of the
value of the house, (d) loss of rent, (e) loss of value of the two annexe sites, (f) professional fees, (g) loss of his own time.
7.13 The principles which the Court should apply to this kind of case have been summarised in Halsburys Laws of England, Volume 12,
where the learned authors state at paragraph 868;
"The prima facie measure of damages for all torts affecting lands is the diminution in value to the plaintiff, or in the case
of a plaintiff in possession with full ownership, the cost of reasonable reinstatement. In the latter case no deduction falls
to be made merely because the plaintiff gets new for old, that is to say a betterment which is the necessary result of
reinstatement. In general consequential loss of profits may be recovered in accordance with general principles and, in the
case of a private individual such consequential loss such as a necessary stay in a hotel and general damage for
inconvenience."
In Kelleher & Kelleher v. Don O'Connor & Co., IEHC 2010 313, Clarke J. stated at paragraph 9.1:
"It is important to start with the fundamental proposition that, in almost all cases, the principal function of the award of
damages is to seek to put the party concerned back into the position in which they would have been had the relevant
wrongdoing not occurred. . . . In the case of a tort, the court has to attempt to put the plaintiff back into the position in
which that plaintiff would have been had the tort not occurred at all. It is the pre-incident position that the court must
look at as a starting point."
Thus, it seems to me, that this Court should seek to put the plaintiff back in the position he would have been in had the incident
herein not occurred. That can be done by awarding the agreed cost of demolition and rebuilding together with an amount to
compensate for loss of use in the intervening years. Costs involved in renovation of the house cannot be given in addition because,
on the basis that the plaintiff will have the house rebuilt, he will have substantially the same house as he had pre-incident and post
renovation cost. If the plaintiff is to have the house rebuilt then no damages can be awarded for loss of value. The original house
would have increased and decreased in value over the intervening years had no incident of damage occurred. No account therefore
should be taken for change in value over the intervening post-incident years. In relation to the two annexe sites, I take it that the
reconstruction costs agreed reflect the cost of reconstructing these annexes to their pre incident state as well because the plaintiff
in his written submissions states;
"Loss of the house and the cost of reconstruction and associated works as agreed between the parties and as indicated
to the Court during the hearing and as accepted in the second named defendant's submissions €300,000."
7.14 The claim the plaintiff makes in relation to these annexe sites is really one of lost opportunity on the basis that he would have
got planning permission for them, developed them as townhouses and reaped the profits there from either by sale or rent. This claim is
grounded on the plaintiff's claim that he would have obtained planning permission for these sites. Planning permission was sought for
these sites in 2003 but was refused. The plaintiff notes that the only ground for refusal stated was that the application was
premature. He extrapolates from this that were he to apply after the works on the canal were finished, he would be all but assured of
obtaining planning permission. Dealing with this, Stephen Dowds, a town planner with thirty years experience gave expert evidence on
behalf of the second defendant. He observed that planning permission did not always set out the full reason for refusal. He expressed
the greatest doubt that the plaintiff would have obtained planning permission in a later application. He noted that the density at the
site was very high. There was no private open space whatever- not even a balcony. The front faced directly on to the canal bank,
the back on to a filling station. There would be no window south in the living room area. The ground floor of the proposed houses
would be mostly taken up by the garage. There would be access problems. Mr. Dowds also testified that since 2003, there had been
two new development plans for Limerick- in 2004 and 2010. These provided more specific requirements in relation to residential issues,
e.g. private open space is now a requirement whereas it had not been before. He expressed the opinion that a planning permission
would have been contrary to either the 2004 or 2010 plans. I accept Mr Dowds evidence. Thus, on the balance of probabilities, I think
planning permission would have been refused. Thus, I hold that the plaintiff has not been able to sustain this claim on the evidence.
7. 15 In relation to professional fees, those relating to the pre-incident renovation of the house cannot be allowed because in having
the house rebuilt the plaintiff is put back into the status quo ante. That state was of a house renovated with all the professional
costs having been paid or ought to have been. Equally, those fees relating to the applications for planning permission cannot be
allowed for the same reason as the claim for loss of value of the sites as set out above. The professional fees that can be allowed are
those properly incurred after the damage to the house and connected with assessing the damage and the requirements for
reinstatement. These are part of the plaintiff’s costs in making his case and thus fall to be assessed and awarded as costs in the
action. Professional fees are lumped together in the written submissions of the plaintiff and have not been broken down between the
three categories specified, i.e. planning application, damage caused and restoration works. Professional fees incurred in helping the
plaintiff assess the damage which was caused to his property should, as noted, more properly be assessed as part of the costs of
preparing his case. Fees in relation to planning permission cannot be allowed because as I have already found, that claim has not
been established. Restoration works pre incident cannot be awarded. I do not think, therefore, that any award can be made in regard
to this heading in the context of damages.
7.16 The final heading claimed by the plaintiff is for his own time dealing with this matter. The plaintiff said in evidence that his life
had been turned upside down over the last ten years. I can readily understand and accept that. I note the plaintiff is a property
manager and that therefore he would have a role perhaps somewhat greater in trying to deal with this situation that the average
plaintiff. I think some damages are due here under the heading general damages for the distress and inconvenience which has resulted
from this incident of damage.
7.17 Summarising and assessing damage;
(i) I assess the cost of demolition and reinstatement of the buildings at the agreed figure of €300,000,
(ii) I assess the loss of use of the house on the basis that the best valuation thereof is the rental value thereof less a
notional maintenance cost over the years to date.
The period of rental loss should be from January 2004 to date plus six months for rebuilding, i.e. nine years. The evidence was that
the property was rented to the McAllisters for €800 per month prior to the incident. When they moved out due to the works, the
second defendant through Mr. Naylor agreed to pay €1,000 per month rental. This latter figure may be assumed to contain a premium
for the disruption caused as well as the rent. Whilst it was accepted that rental values dropped over the years, the plaintiff’s valuer,
Ms. Leddin, gave convincing evidence that rental values remained strong in Limerick. This confirmed the plaintiff’s own evidence. She
considered a figure of €750 per month could be achieved today were the house rented as fully renovated. It must be recollected that
had the incident never occurred, the house would not have become derelict. The value of the rental should be on the basis of a good
house in good condition. Moreover, it must also be borne in mind that the canal bank would have been paved and all the works
completed in what Limerick County Council according to the evidence considered would be a feature area. Thus, its location would
have been far more desirable than it seems today. Taking all this into consideration, I do not consider Ms. Leddin's valuation to be
unrealistic. Off that figure, however, must come an amount for the normal maintenance costs that would have been payable by a
landlord together with some allowance for periods of non occupation. I have no evidence in this regard and can only assess such
costs at a notional figure of twenty five per cent. Thus, rounding up slightly, I would assess the value of the loss of use by the
plaintiff of his house at €600 per month. Over nine years this amounts to €64,800. (iii) For general damages in respect of the plaintiff's
distress, inconvenience and loss of time, I assess a figure of €40,000.
Thus, the total of damages to be awarded amounts to a sum of €404,800 and liability therefor is assessed on the basis of seventy
five per cent against the second defendant and twenty five per cent against the first defendant.