Legislator Case Law & Legislation
IEHC 347 ECLI:IE:HC:2005:347 AI generated

High Court dismisses Limerick Council's application to set aside arbitration award against Uniform Construction Ltd.

Case Number IEHC 347
Court / Authority
Jurisdiction Ireland (IE)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The High Court dismissed Limerick City Council's application to set aside a portion of an interim arbitration award against Uniform Construction Limited. Limerick argued that the arbitrator erred in finding no 'persistent breach' of contract, while Uniform contended the award was final and binding. The court held that the errors alleged were not sufficiently fundamental to warrant judicial intervention under the Arbitration Acts 1954 to 1998.

Legislator headnote

AI generated

Arbitration Acts 1954 to 1998; s. 35: The court will not set aside an arbitration award unless the error is sufficiently fundamental to warrant intervention.

Keywords

AI generated
arbitration award setting aside persistent breach fundamental error Arbitration Acts 1954 interim award judicial review

Cited Legislation

AI generated
Arbitration Acts 1954 to 1998
IN THE MATTER OF THE ARBITRATION ACTS 1954 TO 1998
s. 35 of the Arbitration Act, 1954
these latter proceedings Limerick make application under s. 35 of the Arbitration Act, 1954 for an order directing the arbitrator to
S. 38(1) of the Arbitration Act, 1954
(a) S. 38(1) of the Arbitration Act, 1954 whereby it is sought to have the interim award set aside on the grounds of the
S. 36(1) of the Arbitration Act, 1954
(b) S. 36(1) of the Arbitration Act, 1954 whereby it is sought that certain matters be remitted to the reconsideration of
Arbitration Act, 1979
Arbitration Act, 1979 (23) eliz.
Arbitration Act 1954
Arbitration Act 1954. It is striking that the common law jurisdiction is described as arising only in circumstances where the award

Cited Case Law

AI generated
Lamprell v. Billeircay Union (1849) 18 L.J. Ex 283
Uniform placed reliance on Lamprell v. Billeircay Union (1849) 18 L.J. Ex 283 in
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Neutral Citation Number: [2005] IEHC 347

THE HIGH COURT

COMMERCIAL

[2005 No. 420 S.P.]

[2005 No. 72 COM]

IN THE MATTER OF THE ARBITRATION ACTS 1954 TO 1998

AND IN THE MATTER OF AN ARBITRATION

BETWEEN

LIMERICK CITY COUNCIL

PLAINTIFF

AND

UNIFORM CONSTRUCTION LIMITED

DEFENDANT

Judgment of Mr. Justice Clarke delivered on the 1st November, 2005

1. Introduction

1.1 There are currently two sets of proceedings involving the above parties before the Commercial Court. In the first proceedings

(record number 2005 No. 420 SP.) Limerick City Council (“Limerick”) seeks various reliefs which challenge certain aspects of an interim

award published in arbitration proceedings between Limerick and Uniform Construction Limited (“Uniform”). The arbitration arose

principally from the forfeiture by Limerick of a contract between Limerick and Uniform for the installation of approximately 2.6kms of

sewer by open cut and trenchless methods underneath the city of Limerick. The tendered price for completion of the works required

by the contract (which was known as contract 4.2) was IR £7,537,500 (the approximate equivalent of euro €9.57million). That

contract formed part of a much larger infrastructural project known as the Limerick Main Drainage Project which involved the

connection of the existing Limerick city drainage system to a new treatment works.

1.2 The second proceedings (record number 2005 No 445 SP.) again had Limerick as plaintiff and Uniform together with George David

Guy Cottam as defendants. Mr. Cottam, (“the arbitrator”) is the arbitrator in the arbitration proceedings to which I have referred. In

these latter proceedings Limerick make application under s. 35 of the Arbitration Act, 1954 for an order directing the arbitrator to

state certain questions of law in the form of a special case for the decision of this court.

1.3 On 8th September, 2005, the Commercial Court ordered the consolidation of the two proceedings.

1.4 It being common case that Limerick’s application in the second proceedings is largely contingent (save in respect of one matter

which Limerick contends but Uniform does not accept is not contingent) on Limerick succeeding in the first proceedings in obtaining

an order setting aside or remitting the contested portion of the award, it was agreed between the parties that I should determine the

issues in the first proceedings and leave over further consideration of the second proceedings until that determination.

1.5 For that reason this judgment is concerned solely with the first proceedings.

2. The first proceedings

2.1 In the first proceedings Limerick seeks a series of orders each of which attempts to interfere with the first interim award of the

arbitrator issued and published on 27th June, 2005 (“the award”). The jurisdictional bases relied upon are alternatively:-

(a) S. 38(1) of the Arbitration Act, 1954 whereby it is sought to have the interim award set aside on the grounds of the

misconduct by the arbitrator of either himself or the proceedings;

(b) S. 36(1) of the Arbitration Act, 1954 whereby it is sought that certain matters be remitted to the reconsideration of

the arbitrator; and/or

(c) the courts common law jurisdiction to the extent that same allows that certain matters be set aside or remitted to

the reconsideration of the arbitrator on the basis of an error of law on the face of the award

2.2 While there are certain differences between the specific issues relied upon under each heading, it is fair to say that the totality of

the matters which Limerick says entitles it to one or other of the above reliefs can be enumerated as follows:-

(a) It is said that the award shows on its face two fundamental errors of law made by the arbitrator in reaching a

conclusion that Uniform was entitled, as a matter of contract, to tunnel at a lower level than that contained in the

original design and that, as a consequence, a letter of 13th of June, 2000, instructing Uniform to tunnel at an original

design level amounted to a variation instruction under Clause 51 of the contract. It will, of course, be necessary to return

in more detail to both the context and substance of those contentions in due course;

(b) Secondly it is suggested that the arbitrator failed to consider and decide a central issue in the arbitration namely the

effect of a letter written on 18th May, 2000, by the project engineer to Uniform;

(c) Thirdly it is contended that the award shows on its face a fundamental error of law made by the arbitrator in reaching

a conclusion (which he did) that Uniform was not in “persistent” breach of the contract;

(d) Fourthly it is contended, in relation to the decision by the arbitrator as to whether Uniform was in persistent breach of

its obligations, that the test applied by the arbitrator was one which, as Limerick contends, “he invented for himself” and

that the arbitrator thus deprived Limerick of its right to address further argument on the case which it had to answer; and

(e) Fifthly it is contended that the arbitrator failed to make any decision as to whether a reasonable engineer could have

issued a certificate under Clause 63 of the contract so as to permit the termination of the contract on the grounds of

persistent breach.

2.3 In summary Limerick suggests that each of the above five grounds amount to misconduct entitling them to an order under s. 38

setting aside the award.

2.4 Secondly it is contended that a jurisdiction to remit under s. 36(1) arises in circumstances where there are present on the face of

the record fundamental errors of law (and it is contended that items 1 and 3 above amount to same) or where there is misconduct by

the arbitrator of the proceedings (and it is contended that items 2 and 4 amount to same for these purposes) or where there is the

presence of a fundamental mishap which renders the proceedings unfair (where it is again contended that the matters set out at

paragraphs 2 and 4 give rise to the courts jurisdiction).

2.5 Finally in respect of the common law jurisdiction it is contended that the above identified alleged errors of law entitle the court to

exercise such jurisdiction.

3. Background

3.1 The contract with which these proceedings are concerned was clearly a major public contract and was, as a matter of European

Union Law (E.U. Council Directive 93/37/EEC (the “works directive”) (as amended) required to be put out to tender using the open

tender procedure.

3.2 Uniform submitted, on 21st May, 1999, an unqualified tender to carry out the construction of the works contained in contract 4.2

in the sum of IR£7,537,500 inclusive of VAT. Limerick had appointed a consortium consisting of three firms of consulting engineers as

its Engineer for the purposes of the project. The consortium was known as Barry/Gibson O’Connor/Punch or BGP (“the Engineer”).

Each of the tenderers were provided with drawings and specifications which undoubtedly specified the sewer concerned as requiring

to be constructed at a certain depth or level (“the design level”). Further to a request from the Engineer on 23rd July, 1999, Uniform

provided a document containing what it described as “post-tender information”. This document indicates that two methods of

construction had been considered. The document indicates that one such method (the use of a micro tunnel boring machine or

“MTBM” – a machine controlled remotely from the surface) would require a rationalisation of various shafts and some realignment of

the tunnel and would also require the tunnel to be lowered.

3.3 Representatives of the Engineer met with representatives of Uniform on 4th August, 1999, to discuss Uniform’s tender. There

would appear to have been a difference of opinion at that meeting with the Engineer contending that any aspect of the tender which

operated on the basis of the omission of a significant number (11) of shafts would not constitute a compliant tender while Uniform

expressed the view that s. 7 of the specification allowed the omission of shafts but accepted that any alternative routes or shaft

omissions or methods of connection would be subject to the approval of the Engineer.

3.4 In that context it should be noted that in common with many major civil engineering projects the tender documents in this case

provided that the engineer could require any tenderer to submit a “method statement” which would specify in some detail the way in

which the tenderer proposed to go about carrying out the works.

3.5 In a letter of 20th August, 1999, Uniform provided further information arising out of the meeting on 4th August. In that letter

Uniform reserved the option to use micro tunnelling equipment or the drill and blast open phase method “subject to such methods

meeting the requirements of the specification and obtaining the Engineers prior approval”. The Engineer wrote to Uniform by letter of

6th October, 1999, and confirmed its view that Uniform’s only compliant tender was the open face option. It would then appear that

later that same month the Engineer recommended to Limerick acceptance of Uniform’s tender and by letter of 9th February, 2000,

Limerick wrote to Uniform confirming acceptance of its tender.

3.6 It is common case that that acceptance of the tender gave rise to a contract. While it was argued before the arbitrator by

Uniform that the contract at that stage gave Uniform the right to undertake the tunnelling works by means of an MTBM at a lower

level, the arbitrator rejected that argument and there is no attempt at this stage to invite the court to interfere with that finding. In

relation to this issue, at para. 50 of the award, the arbitrator said the following:-

“I do not accept that argument because the tender as submitted by Uniform did not contain the proposal for the lowering

of the tunnel. That was first brought to the attention of the consortium when Uniform submitted its method statement

with its letter of 23rd July, 1999, which was some two months after the tender was submitted.”

3.7 If the question of establishing the terms of the contractual relations between the parties ended there then there would be unlikely

to be any proceedings before the court or indeed any arbitration on many of the issues in dispute between the parties. However,

further correspondence and documentation passed between the parties subsequent to the acceptance of the tender on 9th February,

2000 but prior to the execution of a written contract which occurred on 23rd May, 2000. It is clear that the written contract of 23rd

May, 2000, purports to incorporate many such documents, written or created between the date of the acceptance of Uniform’s

tender (9th February) and the execution of the contract (23rd May), into the terms of the contract. It is, therefore, necessary to

look at some of the developments which occurred between those dates.

3.8 A further suggestion for using an MTBM was made, by Uniform, by letter of 22nd February, 2000, which differed in some respects

from its earlier proposal. On the 10th March, 2000, Uniform submitted a number of method statements which again proposed lowering

the tunnel at certain areas and omitting certain shafts. The Engineer sought further details of the March, 2000 proposal by letter of

29th March. There followed further correspondence and discussion about the consequences to be anticipated of lowering the tunnel

level in the relevant sections.

3.9 That correspondence would appear to have ended with a letter of 18th May, 2000, from the Engineer to Uniform. A significant

difference which arose between the parties at this stage seems to have derived from the risk elements in the contract. As originally

contemplated, the contract documents (and the tender documents) placed the risk for any unforeseeable difficulties (that is to say

difficulties which a competent contractor could not reasonably have foreseen) upon Limerick. The point being made in letter of 18th

May on behalf of Limerick stemmed from a disagreement between the parties as to whether there was any real likelihood of additional

risk associated with the alternative tunnelling levels then being proposed by Uniform. Limerick asserted that there was such a greater

risk. Uniform asserted that there wasn’t. In that context the Engineer, having set out his reason for differing in his view as to the risk,

said the following:-

“As you have made this proposal we conclude that you are prepared to accept these risks.”

3.10 There was no reply to that letter but soon thereafter a written contract was, entered into using the standard form published by

the Institute of Engineers in Ireland for use in connection with works of civil engineering construction (3rd edition, 1980, as revised

October, 1990).

3.11 Following the execution of the contract the Engineer wrote, on 13th June, 2000, to Uniform suggesting that agreement had not

yet been reached on the revised proposals put forward by Uniform and adding:-

“Please note that without such agreement you are required to proceed with the works as designed with due expedition

and without delay in accordance with the contract.”

3.12 Thereafter there was a considerable volume of correspondence on the March, 2000 proposal but same was not ultimately

agreed. The work ultimately proceeded with the tunnel installed using an MTBM at the design level although the Engineer agreed to

the omission of certain shafts because Uniform were using an MTBM. It would not appear to be disputed that the need for shafts is

reduced by the use of an MTBM.

3.13 Thereafter disputes arose between the parties concerning the extent to which Uniform was in compliance with its contractual

obligations and also as to whether physical conditions or artificial obstructions were encountered by Uniform in installing the tunnel at

the design level which could not reasonably have been foreseen by an experienced contractor so as to entitle Uniform to additional

payment or a longer period to comply with its contractual obligations. Save in respect of the disputes which concerned an allegation

that Uniform was “persistently in breach of its obligations in relation to safety, inconvenience and nuisance to the general public and

compliance with the Engineer’s instructions”, the other issues, while in some respects relevant to the arbitration generally, do not

appear to be relevant to the issues which are now before the court.

3.14 The contract provided for various forms of notices and warnings to be given by the Engineer in the event of an allegation of

breach. A notice under Clause 46 of the conditions was sent on 2nd May, 2001, from the Engineer to Uniform, instructing Uniform that

it was to take such steps as were necessary to expedite progress so as to complete the works by the date for completion.

3.15 A formal warning under Clause 63 of the conditions was given by letter of 29th May, 2001.

3.16 A letter of 20th June, 2001, was sent by the Engineer to Uniform indicating that, in the view of the Engineer, and despite

previous warnings, Uniform was not proceeding with due diligence and was persistently and fundamentally in breach of its obligations.

Uniform was given a further period of fourteen days in which to remedy its default. Subsequent to a meeting between the Engineer

and Uniform on 12th July, 2001, the Engineer wrote to Uniform by letter of 16th July, 2001, confirming the matters which arose at the

12th of July meeting, and indicating that the Engineer would monitor progress so as to determine whether it would be necessary for

the Engineer to issue a certificate to Limerick under Clause 63 of the conditions. By 18th September, 2001, the Engineer, apparently,

had formed the view that Uniform had failed to honour the commitments it had given at the meeting of 12th July and issued a

certificate under Clause 63 certifying to Limerick that the Engineer’s opinion was that Uniform was failing to proceed with the works

with due diligence and had repeatedly and persistently been in breach of its obligations in relation to safety and prevention of

nuisance to the public and had repeatedly and persistently carried out works without approval and failed to carry out valid

instructions of the Engineer.

3.17 As a consequence of the receipt of that certificate, Limerick by letter of 19th September, 2001, sent a notice to Uniform in

accordance with further provisions in Clause 63 informing Uniform of the issuing of the certificate and, in substance, terminating the

contract.

3.18 The above sequence is a necessarily brief account of the history of dealings between the parties. The fact that the complexity

and variety of issues which arose from that course of dealing gave rise to hearings before the arbitrator on liability and on quantum

which took place over approximately twelve weeks between July, 2004 and December of the same year makes clear the variety of

issues which arose. However the above synopsis appears to be sufficient to address the narrow range of issues which were the

subject of those aspects of determination by the arbitrator which are challenged in these proceedings.

4. The issues

In simple terms Limerick make complaint in respect of a relatively small number of findings made by the arbitrator in the award. They

are the following:-

4.2 (a) The level of the tunnelling For reasons which I will address in more detail later in the course of this judgment the

arbitrator came to the view that Uniform were entitled (under the contract as finally executed) to select the level at

which the tunnel was to be constructed provided that same complied with certain requirements specified in clause 7.4.1.

of the specification. On the basis of coming to that view the arbitrator took the further view that the instruction by the

Engineer of 13th June, 2000, (which was to construct at the design level) constituted an instruction given under Clause

30(1) and was therefore a variation within the terms of clause 51 so that any additional cost would fall to be valued

under Clause 52. It is contended by Limerick that in reaching those conclusions the arbitrator was fundamentally wrong.

4.3 (b) The letter of the 18th May As is clear from the brief account of the dealings between the parties set out above a

key issue in the debate between the parties leading up to the signing of the contract on the 23rd May was the attempt

by the Engineer to place the risk of any varied route upon Uniform. That debate appears to have been left somewhat up

in the air with the Engineer’s letter of 18th May, 2000. It would appear that the arbitrator accepted that it was common

case that the proposal for the acceptance of risk by Uniform contained in that letter was never accepted by Uniform. It is

equally common case that the letter of 18th May was bound into the contract documents. In those circumstances the

contractual consequences (if any) of the inclusion of that letter in the contract documents was an issue between the

parties. It is contended that the arbitrator failed to decide the contractual effect of that letter and in particular its

inclusion in the contract documents.

4.4 (c) The certification by the Engineer Under this heading Limerick disputes the test which, it says, the arbitrator

applied in determining whether Uniform was in persistent breach and also contend that the arbitrator devised a test of his

own making without giving the parties, and in particular Limerick, an opportunity to be heard on it. Further it is contended

that the arbitrator failed to decide whether no reasonable Engineer could have issued the Clause 63 certificate on the

grounds of persistent breach. 4.5 However, it should be noted that these proceedings are necessarily limited in their

scope given that, on any view, the court’s entitlement to interfere with an award of an arbitrator is significantly

circumscribed. In those circumstances it seems to me that it is appropriate to turn next to the question of the court’s

jurisdiction to make any of the interventions which Limerick seek.

5. The jurisdiction of the court

As is clear from the above brief recital of the issues, a number of separate contentions put forward on behalf of Limerick concern

allegations that the arbitrator made an error of law apparent on the face of his award sufficient, it is contended, to warrant the

intervention of the court. It is therefore to the jurisdiction of the court to interfere in such circumstances that I first turn. I will, later

in the course of this judgment, consider the jurisdiction of the court in relation to the contention that the arbitrator failed to decide

important issues (viz the effect of the letter of the 18th May and the reasonableness of the engineers certificate) and the legal basis

upon which the court should consider the contention that the arbitrator determined the test by reference to which he should assess

the question of persistent breach without giving the parties an appropriate opportunity to be heard.

6. Error of Law

6.1 It seems to me that the starting point of a consideration of this question should be the position at common law. In Keenan v.

Shield Insurance Company Limited [1988] I.R. 89 the Supreme Court acknowledged the jurisdiction of this Court at common law to set

aside an award where there was a fundamental error of law on the face of the award.

6.2 It is instructive, in my view, to consider a significant passage from the judgment of McCarthy J. in that case where at p. 95 (and

with the agreement of each of the other members of a court of five) the following is said:-

“Section 36 would appear to be the procedure appropriate, for example, to a case of a patent mistake, in monetary

calculation, in the giving or not giving of a particular credit, in an award that is on its face ambiguous or uncertain, in a

case where the arbitrator, himself, seeks to rectify some error and, perhaps, where fresh evidence has become available

subject to the standard rules of an appellate court in such cases. No case cited to the court in the course of argument

concerns the application of the like section in England and no Irish case has been cited on the point. In my view neither

s. 35 nor s. 36 affords any relief to the plaintiff; I express no opinion on the question as to whether or not either section

may be so used by this court, which is not the court referred to in the sections, when such an application is made as of

first instance on the hearing of an appeal.

Church & General Insurance Company v. Connolly and McLoughlin (Unreported, High Court, Costello J. 7th May, 1981). In

that case the plaintiff did apply under s. 36 alleging that the arbitrator permitted an error of law to appear on the face of

the award and that this constituted a misconduct under s. 38, an argument rejected by Costello J. who expressed the

view (p. 7 of his judgment) that there is no doubt that at common law the court can either remit or set aside an award if

there is an error of law on its face”, and later “in my view the courts jurisdiction to set the award aside in such

circumstances is given by the common law”. The precedents cited established, before the passing of the Act of 1954, the

jurisdiction to set aside an award because of an error of law that appeared on the face of the award had been

established as part of the common law. In addition I would point to Ex Parte Strabane R.D.C. (1910) 1 I.R. 135 and the

Honorable The Irish Society v. Minister for Finance (1958) NI 170. This jurisdiction was abolished in England by the

Arbitration Act, 1979 (23) eliz. 2, c. 42). This feature of the common law was described in Russell Arbitration 19th Edition

(1979) at p. 437 as a somewhat anomalous extension of the rule that an award which, on its face, fails to comply with

the requirements for a valid award, will be remitted or set aside.

The concept that a long established common law principle necessarily requires legislation to effect a change in it has little

appeal for me since the common law, itself, by definition, reflects the changing demands of society, adapting itself to

meet perceived needs. Where, however, the legislature has intervened in a particular branch of the law, and has not

expressly negatived an existing common law jurisdiction, such a jurisdiction must have survived, albeit that it must be

administered so as to accommodate the legislation.

Arbitration is a significant feature of modern commercial life, there is an International Institute of Arbitration and the field

of international arbitration is an ever expanding one. It ills becomes the court to show any readiness to interfere in such a

process; if policy considerations are appropriate, as I believe they are in a matter of this kind, then every such

consideration points to the desirability of making an arbitration award final in every sense of the term”.

And later McCarthy J. concludes in the following terms:-

“There may be instances in which an award which shows on its face an error of law so fundamental that the courts

cannot stand aside and allow it to remain unchallenged”.

6.3 It seems to me, therefore, clear that, in the unanimous view of the Supreme Court, the policy considerations which favour

conferring finality on the awards of arbitrators were such that the court might well have been persuaded to further refine the common

law in a manner so as to further restrict (or indeed remove entirely) the jurisdiction to set aside or remit on the basis of an error of

law on the face of the award were it not for the fact that the Oireachtas, having turned its mind to the question of arbitration, had

not chosen (unlike Parliament in the United Kingdom) to intervene in relation to that jurisdiction.

6.4 There is nothing, however, in the judgment which would convey any suggestion that, in the view of the Supreme Court, the

jurisdiction to set aside or remit on the basis of error of law had been, in anyway, extended or enlarged by the enactment of the

Arbitration Act 1954. It is striking that the common law jurisdiction is described as arising only in circumstances where the award

shows “on its face an error of law so fundamental that the courts cannot stand aside and allow it to remain unchallenged”.

The Supreme Court again had occasion to consider this area in McStay v. Assicurazione Generali SPA and Another [1991] ILRM 237

where, at p. 243, Finlay CJ had the following to say:-

“I am satisfied that at common law where an arbitrator decides a question of law in the course of an arbitration where a

general issue in dispute is submitted to him, but where that precise question of law has not been submitted for his

decision, the court may in its discretion and in particular cases where the decision so expressed is clearly wrong on its

face, intervene by way of remitting the matter or otherwise in the interests of justice. This was the situation presented

to this court in Keenan v. Shield Insurance Company and in the judgment of McCarthy J. was accepted, subject to what I

am satisfied were appropriate warnings as to the limited number of instances in which it is appropriate for the court, even

in that situation to intervene. A decision made by an arbitrator upon the reference to him of a specific question of law

which appears on its face to be erroneous is not covered by any of these qualifications”.

6.5 Those two authorities suggest that the jurisdiction at common law is limited and arises only where the error is “so fundamental”

that it cannot be allowed to stand (Keenan) or “clearly wrong” (McStay). It is noteworthy that the position in the United Kingdom

prior to the abolition of the error jurisdiction was equally restrictive (see for example the comments of Lord Denning referred to at

para. 9.2 hereafter). Having considered the position at Common law it is now necessary to turn to the Arbitration Act, 1954.

6.6 In Tobin & Toomey Services v. Kerry Foods Limited [1996] 2 ILRM 1 the judgment of the Supreme Court was delivered by Blayney

J. where he adopted the statement of O’Hanlon J. in Portsmouth Arms Hotel Limited v. Enniscorthy UDC (Unreported, High Court,

O’Hanlon J., 14th October, 1994) to the effect that amongst the grounds for the exercise by the court of its undoubted jurisdiction to

remit for re-consideration under s. 36 was a case where it had been established “that there is some defect or error patent on the

face of the award”.

6.7 While it may be that Tobin & Toomey is, therefore, authority for the proposition that the statutory power to remit under s. 36

includes a power to remit in circumstances where there is an error on the face of the award, I can find nothing in that judgment, or in

the judgment of O’Hanlon J. in Portsmouth Arms Hotel, which implies a departure from the test for the exercise of any such

jurisdiction as set out in both Keenan and McStay. It may well be, therefore, that it is a rather academic point as to whether a power

to remit for reconsideration as a result of an error on the face of the award exists under s. 36 as well as at common law unless there

is authority which tends to suggest that any such jurisdiction as may exist under s. 36 would be greater than the jurisdiction to remit

at common law.

6.8 It seems to me to be the obvious inference from the comments as to the desirability of treating arbitration awards as final made

by McCarthy J. in Keenan that the courts should and will be slow to imply into any statutory provision any increased entitlement to

interfere with arbitration awards in the absence of clear wording in the statute concerned indicating such an intent. There is

manifestly no such clear wording in s. 36 and, for those reasons, I do not believe that any statutory jurisdiction to remit under s. 36

which may exist, extends the jurisdiction beyond that which formerly existed at common law and which is as set out in Keenan and

McStay.

6.9 The Supreme Court returned to the question of the jurisdiction to interfere with arbitration awards in McCarthy v. Keane and

Others [2004] 3 I.R. 617. It is noteworthy that Fennelly J. (who delivered the unanimous judgment of the court) quoted part of the

same passage from the judgment of McCarthy J. in Keenan to which I have referred earlier and commented that “though he was not

dealing with an allegation of misconduct, McCarthy J. set the tone for the correct judicial approach to arbitrator awards” in that

passage.

Further in the course of his judgment in that case Fennelly J. considered the extent of the courts jurisdiction under s. 36 in particular

in the light of the decision of Herbert J. in this Court in McCarrick v. The Gaiety (Sligo) Limited [2001] 2 I.R. 266. In respect of that

judgment Fennelly J. noted, at p. 629, as follows:-

“The conclusion of Herbert J., arrived at after very careful consideration goes some way to open up the possibilities of

employing s. 36 to cover more than the traditional four grounds, error on the face of the award; a mistake which the

arbitrator wishes to have corrected; new material evidence; misconduct. He considered that the courts should exercise

restraint in exercising the “unlimited discretion” conferred by the section. It is true that s. 36 does not in turn set any

limits to the exercise of the discretion. That does not mean that the discretion is unlimited. The policy of the law is to

uphold the certainty of arbitration awards, once they have been made. Furthermore the courts will not interfere without

very good reason in the arbitration process”.

6.10 While that case is, therefore, authority for the proposition that there may well be further categories of case (beyond those

already identified) where the statutory jurisdiction to remit under s. 36 arises it does not, it seems to me, provide any assistance to a

party, such as the plaintiff, who may argue for an enlarged jurisdiction to remit for error. On the contrary the case is a reiteration of

the strong policy of the courts in favour of upholding arbitration awards. Indeed in relation to the courts jurisdiction to set aside an

award on the grounds of misconduct under s. 38 Fennelly J., (at p. 627) indicated the test in the following terms:-

“It seems to me that the standard or test of misconduct of such a nature would be something substantial, something that

smacks of injustice or unfairness”.

While Fennelly J. was speaking of misconduct in relation to the process, the passage is, nonetheless, a further reiteration

of the very high standard that needs to be met by a party who wishes to invoke the courts jurisdiction to interfere with

an arbitration award.

6.11 In commenting on the analogous statutory scheme applicable to the review of decisions taken in relation to the assessment of

the value of land for the purposes of compulsory acquisition under the Acquisition of Land (Assessment of Compensation) Act 1919,

Keane J. in Sheehan v. FBD Insurance plc (Unreported, Supreme Court, Keane J., 20th July, 1999) said, at p. 21, the following:-

“The statutory scheme, which entitled the High Court to remit any of the matters referred to arbitration to the

reconsideration of the arbitrator and to set aside the award where the arbitrator has misconducted himself or the award

has been improperly procured, did not affect the jurisdiction of the court at common law to set aside an award where

there was an error of law on its face”.

6.12 Doyle v. Kildare County Council [1996] 1 ILRM 242 is, if it is needed, further authority which confirms the above policies and

suggests that the jurisdiction under s. 38 to set aside on the grounds of misconduct does not apply in cases where the only allegation

is of error. Even if an error of law on the face of the award could be regarded as misconduct in principle I can find nothing in any of

the authorities cited which would imply that the jurisdiction to set aside under s. 38 for misconduct on the basis of error of law is any

greater than the common law jurisdiction to set aside on the same grounds.

7. Conclusion on Error Jurisdiction

7.1 While a considerable amount of argument was addressed at the hearing as to whether this Court has a jurisdiction, under either or

both of ss. 36 and 38, to remit or set aside respectively an award of an arbitrator on the basis of an error of law, for the reasons set

out above it seems to me that this argument is wholly academic. There seems to be authority which suggests that the jurisdiction to

remit under s. 36 for error of law does exist (Tobin & Toomey). An entitlement to set aside on the same basis for alleged misconduct

is less clear. However even if either or both of the above statutory jurisdictions exist I can find nothing in any of the authorities which

suggest that the court has, under either or both of those sections, a larger entitlement to interfere with an arbitration award than

the court had, prior to the enactment of the 1954 Act, at common law. Whether the court has, or has not, a statutory jurisdiction as

well, is, it seems to me, therefore, irrelevant.

7.2 I therefore propose approaching the alleged errors of law on the face of the award applying the test identified by McCarthy J. in

Keenan and Finlay C.J. in McStay.

7.3 Furthermore I am satisfied that the arbitration in this case can properly be described as being of the specialist category towards

which, the jurisprudence of the court requires, a particular deference should be shown. Henry Denny and Sons (Ireland) Limited v.

Minister for Social Welfare [1988] 1 I.R. 34; Carrickdale Hotel v. Controller of Patents [2004] 3 I.R. 410.

7.4 Finally in relation to the law on this aspect of the case it is clear from the authorities referred to above (especially McStay) that

there is a limitation on the jurisdiction of the court to set aside or remit an award for error on the face of the award where the

specific question of law in respect of which the error is alleged to have been made has been referred to the arbitrator for his

determination. The logic behind this exception is that if the parties have contracted to refer a decision as to what a particular point

of law is, to an arbitrator, they are bound by the view of that arbitrator even if he turns out to be wrong. However it is equally clear

from the passage from McStay as cited above that a distinction needs to be made between a specific issue actually referred to the

arbitrator on the one hand and the variety of legal issues which will necessarily arise in a great number of arbitrations on the other

hand. Even the simplest of arbitrations will, in all likelihood, involve some questions of law. Even where the relevant legal principles are

not, in themselves, the subject of any controversy between the parties, their application to the facts of the case which the

arbitrator has to decide frequently are. In those circumstances the arbitrator will, necessarily, be called upon to decide what are, at a

minimum, mixed questions of law and fact. The exclusion of the jurisdiction of the court, it appears to me, arises only where “a

specific question of law” has been referred to the arbitrator. It does not arise where it is necessary for the arbitrator to decide a

question of law in the course of an arbitration where a general issue in dispute is submitted to him. See McStay.

7.5 It is, of course, a question of construction to determine, in any particular instance, what it is that has been “referred” to the

arbitrator. It does not appear to me that issues which emerge in the course of the arbitral process (whether by pleadings,

submissions, or argument) can be said to be issues specifically referred to the arbitrator. To take a practical example of the

distinction, parties in dispute over their entitlements to property might have agreed all relevant factual matters but differ over

whether, say, an estoppel arose on those facts as a matter of law. If that question was referred to an arbitrator then it could not be

doubted that the specific question of law as to whether an estoppel arose on those facts would have been referred to the arbitrator

and no jurisdiction to set aside or remit would arise even if the court took the view that the arbitrators determination, as appearing

on the face of his award, was in error.

On the other hand a more general question as to the entitlements of competing parties in relation to rights to property could be

referred to an arbitrator in which, as part of its case, one of the parties might plead an estoppel. In those circumstances the estoppel

question would, in my view, be a legal question arising in the course of a referral of a general issue, rather than a specific issue

referred to the arbitrator and, in those circumstances, the limited jurisdiction of the court to remit or set aside in circumstances

where there was a patent or fundamental error on the face of the award would arise. I will address the remaining legal issue that

arises under this heading (that is the test by reference to which it may be said that an error is an error of law “on its face of the

award”) later in this judgment (see para. 9 hereafter.)

8. Application to this Case (the first alleged error)

8.1 Having identified the basis upon which it is proper for this court to interfere with an award of an arbitrator on the basis of an

alleged error on the face of the award it is necessary to consider in more detail the errors alleged to be present in this case. As

appears from the list of specific issues relied upon by Limerick which I have set out at paragraph 2.2 above three matters (the two

questions referred to in sub-paragraph (a) and the question referred to at sub-paragraph (c)) are alleged to constitute errors of law

on the face of the award sufficient to warrant the courts intervention. It is necessary to deal with each in turn.

8.2 The alleged section 7 errors

The first two errors contended for, concern is the manner in which the Arbitrator construed s. 7.4 of the Specification. As indicated

above one of the documents which was supplied to each potential tenderer was such a specification. Section 7.4 of that document

provided the following:-

“7.4 TRENCHLESS ROUTE

7.4.1 The contractor may propose an alternative route for the interceptor to suit his proposed tunnelling method and

construction techniques, provided that:-· all connections are fully provided for

· foundations, structures and services are not put at risk

· future maintenance requirements are facilitated, particularly in the context of the Safety Health and Welfare at Work

Regulations

· the revised route does not impinge on private property.”

The specification formed part of the documents which were incorporated into the contract as signed in May. The arbitrator construed

section 7.4 as giving the contractor the right to put forward proposals for an alternative route at any time even after the contractor’s

tender had been accepted and an initial contract or even a final contract entered into. As he found that Uniform’s proposal to lower

the tunnel did comply with the above requirements, the arbitrator concluded that the lower tunnel proposal conformed with the

contract. Limerick suggests that the arbitrator was fundamentally wrong in coming to that view.

8.3 It is, of course, correct to state that section 7.4.1 does not, in its terms, specify when the contractor (i.e. Uniform) was entitled

to propose alternative routes. However Limerick argues that by reference to certain other aspects of the contractual documents it is

clear that the entitlement to put forward alternative routes only existed at the stage of consideration as tenders and not after the

acceptance of the successful tender.

Firstly it is contended that a reading of section 7 of the specification as a whole makes it clear that it is intended to apply only to the

tender stage and not to a period after the contractor’s tender has been accepted. It is also suggested that the arbitrator, in

construing section 7.4, appears to have overlooked certain other contractual provisions which, it is said, make it clear that section 7

only applies at that tender stage and not after a contract has been entered into. In that regard reference is made to a further

portion of the same section (section 7.8.1) which refers to the provision, if requested, of a detailed Method Statement in support of

his (the contractor’s) proposals during the detailed consideration of his tender”. It is therefore suggested that the entirety of s. 7

pre-supposes that a tenderer who wishes to put forward an alternative proposal would put forward an alternative tender together

with a compliant tender (a compliant tender being one which is in strict conformity with the specified design).

8.4 Reliance is also placed on the provisions of paragraph 30 of the Instructions to Tenderers which provides as follows:-

“Where a tenderer wishes to submit alternative proposals to those specified in the tender documents, this should be done

by way of an alternative tender. No alternative will be considered unless a tender based strictly in accordance with the

tender documents without qualification is also submitted. Any alternative tender must also be free of qualifications and

must show clearly where costs would differ from the compliant tender. The engineer and employer reserve the right to

reject any alternative tender considered inappropriate and to insist on design criteria and requirements that suit their

general requirements in terms of maintenance, materials methods of construction etc. An alternative tender that does not

meet these requirements may be summarily rejected by the employer, whose decision in the matter shall be final”.

8.5 Reliance is also placed on a further contract document, the Bill of Quantities, which, at paragraph 23, gives details as to how any

such alternative tender was to be submitted.

8.6 Finally it is suggested that the construction which the arbitrator placed upon the contract as a whole was such as would make

the contract as entered into, in breach of public procurement rules because the contract so entered into would differ, in a significant

and material manner, from the proposal which went out to tender in the first place.

8.7 In response Uniform draws attention to the fact that the tender documents did not require tenderers to include a statement

indicating which of the specified methods of construction the tenderer proposed to use. Uniform also places reliance on instruction 23

which noted that such information might be requested from tenderers when tenders were being considered. In that context Uniform

draws attention to the request by the engineer by letter of 30th June, 1999 to provide such additional information in response to

which the information was provided including a detailed method statement for construction of the tunnel by two alternative methods

being “drill and blast” at the design level or alternatively at a lower level by MBTM.

Furthermore attention is drawn to the fact that each of the sub-clauses in section 7 of the Specification refers to alternative

construction “methods” as opposed to alternative tenders. It is, therefore, suggested that the proposal for use of MBTM was one for

an alternative method rather than an alternative tender and was, therefore, a permissible response to the engineers request of the

30th June, 1999, provided it complied with the provisos to clause 7.4.1

8.8 In the context of assessing these competing arguments it is important to start with the basic contractual document which is the

agreement signed on 30th May, 2000. That document lists a very significant number of other documents which are described as being

deemed “to form and be read and construed as part of this agreement”. The documents are:-

(a) the instructions to tenderers

(b) the said tender

(c) the drawings and schedules

(d) the conditions of contract and amendments to conditions of contract

(e) the specification

(f) the price to bill of quantities

(g) the performance bond

(h) site investigation report

(i) any queries dealt with during the tender period

(j) any notice issued under instruction 23 of instructions to tenderers

(k) the schedule of day works

(l) the schedule of basic prices

(m) post tender correspondence

8.9 The contract then simply states that in consideration of the payments to be made, Uniform are to construct and complete the

works in conformity “with the provisions of the contract”. It might well be said that where parties choose to enter into a formal

written contract which will necessarily post date and supersede a tender process it would be preferable if the contract documents

which constitute the final agreement were put together in such a way as made clear which aspects of the documents were to form

part of the continuing contractual obligations between the parties. The problem with the inclusion of a vast array of documentation

without specifying its current status is shown by the difficulty that arises in this case.

8.10 If Limerick are correct as to the proper construction of the entirety of the contract documentation taken as a whole then it

would seem that Clause 7.4.1 of the specification (and indeed the balance of Clause 7 as well) has no relevance to any continuing

contractual obligations of the parties as of the date of signing the agreement. If Clause 7 was only to have an effect at the tender

stage then that effect was spent long before the parties came to sign the agreement in May. If that is the proper construction to be

placed upon the contract as a whole then one might well ask as to why the relevant provisions of the specification, which were only

concerned with the tender process (rather than specifying or at least influencing the continuing contractual obligations of the parties)

were included in the contract documents at all.

8.11 Obviously in the ordinary way, specifications or other documents which form part of the tender process may be necessary to

understand and interpret those documents which are to govern the continuing obligations of the contractor. Where pre-tender

documentation is concerned only with the tender process itself and is unnecessary for the interpretation of the continuing contractual

obligations of the parties it would be preferable if such documentation was not incorporated into the contract as its inclusion has the

potential to lead to ambiguity. If it is not possible to exclude such documentation (because, for example, same forms part of a larger

document some of which remains relevant) then it would avoid confusion if the primary contract document specified expressly which

portions are intended to effect the parties continuing obligations. Failure to do so will lead to undoubted debate as to the effect, if

any, of including as part of the contract documents clauses which might be said on one view to be spent prior to the execution of the

agreement.

In expressing those views I have not overlooked the fact that the Clause 5 of the general conditions specifies that the several

documents forming the contract are to be taken as mutually explanatory of one another and that discrepancies and ambiguities are to

be the dealt with by the engineer. It is by no means clear that such a clause could be used to resolve the difficulties of construction

to which I have referred in the preceding paragraphs.

8.12 It is, of course, well settled that in construing a contract which the parties have agreed to reduce to writing the court should

have regard only to the terms of the contract itself together with, where appropriate, the factual matrix within which the contract

came to be entered into.

The very fact that, in order to make its argument, Limerick is required to refer to a range of separate contractual documents and to

their interaction by reference to the facts which explain the sequence in which those documents came about shows that the range of

materials relevant to the proper construction of this contract are potentially quite extensive and, may arguably, go beyond Clause 7

itself and indeed might, on one view, trespass into factual matters beyond the raw text of the documents themselves. In that

context it is necessary to address a separate legal issue as to just what is meant by an error “on the face of the award”. I now turn

to that issue.

9 What is “on the face of the award”

9.1 In DS Blaiber & Company Limited v. Leopold Newborne (London) Limited (1953) 2 Lloyds Rep. 427 Lord Denning expressed the test

in the following way:-

“The question whether a contract, or a clause in a contract, is incorporated into an award is a very difficult one. As I

read the cases, if the arbitrator says:-

“On the wording of this clause I hold” so-and-so, then that clause is impliedly incorporated into the award because he

invites the reading of it; but if an arbitrator simply says: “I hold that there was a breach of contract”, then there is no

incorporation.

9.2 Before leaving that case it is also worthy of note that Lord Denning went on to make the following general comment:-

“It seems to me that, when traders go to lay arbitrators to decide a dispute between them, then the matter ought in the

ordinary way to be left to those lay arbitrators without their decision being queried thereafter in point of law. The lay

arbitrators have decided according to the justice of the case as they see it. If people want to raise points of law then

they ought to ask at the time for a case to be stated on a point of law. If no such request is made, they should leave the

law to the arbitrators. Applications should not be encouraged which seek to set aside the award on the ground of error on

the face of it in point of law”.

9.3 Counsel for Limerick helpfully procured the final edition of Halsbury Laws of England which pre-dated the removal of the jurisdiction

to remit or set aside for error of law in the United Kingdom (Halsbury Laws of England 4th Edition Volume 2 (1973)). In paragraph 623

the jurisdiction is described in the following way:-

“In order to be a ground for setting aside the award an error in law on the face of the award must be such that there can

be found in the award, or in a document actually incorporated with it, some legal proposition which is the basis of the

award and which is erroneous”.

In the relevant footnote to that passage there is reference to FR Absalom Ltd. v. Great Western (London) Garden Village Society

(1933) AC 259 where it was considered permissible to look at the terms of a clause in a contract where the award referred to the

clause but did not set out its text in full. Further reference is made to Nils Heime Akt v. G Merel & Company Limited (1959) 2 Lloyds

Rep. 292 where reference was made to the whole of a contract where the award referred in terms only some part of the contract.

9.4 It seems to me that this latter point necessarily follows. But it does show the difficulty of the court exercising its limited power of

review in cases where the construction of the contract concerned is complex. It would, of course, be wholly wrong if it could be the

case that a court would conclude that a construction placed on a contract, or a term of it, was in error without the court having

regard to all of the materials which could properly have been considered by the arbitrator in reaching his conclusions. It, therefore,

necessarily follows that a court cannot conclude that an arbitrator has been in error in his construction of a contract unless it is open

to the court to look at all the materials which would have been properly taken into account.

10. Conclusion on First Error

10.1 In this Court in McStay v. Assicurazione Generali SPA [1989] I.R. 251 Carroll J. having considered the competing arguments as to

the construction of the contract under review in that case said the following:-

“However I should say that the matter is not clear-cut. There is an arguable case on both sides. That being so, I do not

see how it fits into the category of case in which the Supreme Court indicated that it would be appropriate to interfere.

In my opinion, any error, if there be an error, could not be described as being so fundamental that the courts could not

stand aside and allow it to remain unchallenged”.

10.2 I have come to a similar view in respect of the first contended for error. In order to reach a conclusion as to whether there was

an error it is necessary to have regard to the interaction of the whole series of contractual documents, to construe them by

reference to each other and by reference to the evidence as to the sequence in which the documents came into existence. In those

circumstances I am satisfied that, in the words of Carroll J. in McStay, any error, if there be an error, cannot be said to be of the

obvious and fundamental variety which is necessary for the court to intervene.

10.3 Before passing from this aspect of the case I should say that I am mindful of the argument put forward on behalf of Limerick to

the effect that the conclusion reached by the arbitrator as to the proper construction of the contract entered into in May is

surprising in the light of the original project for which the parties tendered. That may well be so. However that fact needs to be seen

in the context of the fact that there were, on any view, significant developments between the termination of the tender process and

the entering into of the formal contract. Furthermore for the reasons set out above any ambiguity that arises stems at least in

significant part from the manner in which all contractual documents were simply included without any sufficient express provision as

to how they were to be collectively interpreted. In that context what might otherwise be perceived to be a surprising result is not,

necessarily, quite so obviously so. It is certainly not, in my view, so obviously and fundamentally wrong as to invoke the courts

jurisdiction. It should also be noted that the correspondence between the Engineer and Uniform concerning the position in relation to

Uniform’s March proposal had not come to any conclusion as of the date of signing the agreement. Furthermore both parties had, if

would appear, agreed to differ on the issue as to Uniform’s entitlement to propose alternatives which emerged at the meeting of the

4th August, 1999. It is surprising that the documents which gave rise to that difference of opinion were incorporated into the

contract signed some 9 months later without specifying or clarifying which interpretation was to prevail.

10.4 Before leaving this topic I should also note that I have given consideration to the submissions, which I invited from the parties,

as to whether I should express a view, (in the event that I found that there was not an error of sufficient seriousness to warrant the

intervention of the court by reference to whatever threshold I had determined was appropriate) as to whether there was in fact an

error at all even though it might fall short of that threshold. I have come to the view that it would be inappropriate so to do. Firstly it

seems to me that in order to reach a safe conclusion as to whether the interpretation of the arbitrator was in error at all (as opposed

to being in fundamental error) it would be necessary for me to consider in much greater detail the submissions made by the parties at

the hearing before the arbitrator and all of the materials relied upon. Given that I have taken the view that there is no error which

would warrant the intervention of the court I have also become satisfied that, having regard to the fact that the matter must now go

back before the arbitrator, it would be inappropriate if he were to be asked to continue with the arbitration in circumstances where he

had made a ruling which was not to be disturbed by the court, but where the court had indicated that that ruling was wrong. For

those reasons I feel that I should express no view as to whether there was, in fact, an error at all. I confine myself to indicating that

any error that might be present is not such as would justify remittal or setting aside.

11. The Second Error

The second error relied upon also concerns the interpretation of section 7.4.1. It is said, that the arbitrator in construing the section

in the way he did overlooked section 7.2.2 which states:-

“For any alternatives put forward the proposals are required to comply fully with Specification”.

Reliance is placed upon the fact that the Specification required the construction of all the shafts (including the omitted shafts).

Therefore it is said that the alternative put forward in March did not comply fully with the Specification and thus contravened section

7.2.2.

11.2 In support of this argument reliance is placed on instruction 14(iii) of the Instructions to Tenderers which states that “each rate

or price shall properly cover the fully inclusive value of the works covered by the item description and shall reflect the quantity set

against that item”. On that basis it is suggested that the March proposal which, in effect, it may be said, transferred some of the

cost from shafts to what was the apparently more expensive micro tunnelling, failed to comply with the requirement that there be a

rate or price which covered the value of the work covered by the relevant item description.

11.3 Again under this heading it seems to me that the questions of construction that arise are complex involving the interaction of

different aspects of the contractual documentation. In particular it is necessary to reconcile the apparent entitlement under section

7.4.1 to put forward alternatives subject to compliance with the provisos contained in that clause and the fact that it was,

apparently, eventually agreed that the work could go ahead without some of the shafts, with the terms of section 7.2.2. In those

circumstances I am not satisfied that the view which the arbitrator took was so obviously and fundamentally wrong that it is

appropriate for the court to intervene.

12. “Persistent Breach”

12.1 Under this heading complaint is made as to the manner in which the arbitrator made findings as to whether Uniform were in

persistent breach of contract. Clause 63 (1) of the conditions of contract permit the engineer to certify in writing to the employer

that, in his opinion, the contractor, despite previous warning by the engineer in writing is, “persistently or fundamentally” in breach of

his obligations under the contract. As indicated above this the engineer did.

12.2 Under this heading two complaints are made. It is suggested that the test applied by the arbitrator in considering whether

Uniform were in persistent breach was incorrect. Secondly it is said that the process was unfair to a sufficient degree to warrant the

intervention of the court, because the arbitrator invented the test himself without giving the parties an opportunity to be heard. I

turn first to the issue as to whether there can be said to be an error on the face of the award sufficient to justify the intervention of

the court applying the principles already identified.

12.3 It is clear that there is a difference between a fundamental breach and a persistent breach. A fundamental breach is clearly a

breach which is so significant that it can, of itself, be regarded as going to the root of the contractual obligations of the party in

breach to a sufficient extent as would justify the termination of the contract.

12.4 There are clearly breaches which have varying degrees of seriousness but which fall short of a fundamental breach. Such

breaches can only justify certification by the engineer if they are “persistent”.

Reference was made to the leading English construction text book Keating on Building Contracts which indicates in respect of similar

wording in the ICE contract at page 1193 that a persistent breach:

“must involve either repeated or continuing occurrences e.g. repeated execution of bad work or continuing failure to

rectify.”

12.5 The arbitrator considered this issue in paragraph 301 of his award where he noted that he had considered a schedule setting out

129 alleged incidents of breach which Limerick had contended ought to give rise to a finding of persistent breach. In sub-paragraph 4

the arbitrator correctly noted that in order for a breach to be persistent it should “continue firmly or obstinately.”

At sub-paragraph 12 the arbitrator concluded in the following terms:

“I do not consider that any of the incidents either individually or collectively were of such seriousness as to warrant

termination of the contract.”

The arbitrator then went on at subparagraph 20 to indicate that he did not: “consider that any of these incidents

individually qualifies as proving that Uniform was either persistently or fundamentally in breach of its obligations under the

contract.”

12.6 The contention of Limerick is that the above passages from the award of the arbitrator make it clear that he considered that

Uniform were not in persistent breach by looking separately at each individual instance. It is therefore submitted that he manifestly

applied the wrong test and it is further submitted that the test adopted was not one which was canvassed in any way at the hearing

and that its adoption was, therefore, unfair.

12.7 Clearly any assessment of whether a party was in persistent breach requires looking at the overall picture in relation to

breaches. As is pointed out in the passage from Keating referred to above breaches can either be one off incidents or can arise from

permitting a state of affairs to continue. It is, therefore, possible that an individual instance may amount to a persistent breach

where that instance is a continuing failure to deal with some important aspect of the contract. There is nothing, therefore, illogical

about looking at individual instances as, potentially, providing a separate justification for a finding of persistence.

12.8 Applying the principles of construction to which I will refer later in this judgment (see para. 13.5), it seems to me that it is

appropriate to construe the award in a manner which gives effect to each of the paragraphs to which I have referred so as to

consider from an overall point of view whether the arbitrator has dealt properly with the issues before him. In those circumstances it

seems to me that the arbitrator did have regard to the possibility that individual breaches which would not of themselves give rise to

a finding of persistence might nonetheless collectively lead to such a finding (see para. 301.12 of the award referred to above). I am

not satisfied, therefore, that the construction which Limerick seeks to place on the arbitrators award is, in fact, correct. In saying

that I should indicate that if I were wrong in that conclusion and if, on a proper construction of the award, it could be said that the

arbitrator had not had regard to the possibility that breaches which while individually insufficient to establish persistence might

collectively meet that test, then I would view the award as containing on its face a fundamental error sufficient to potentially invoke

the jurisdiction of the court.

12.9 Finally under this heading I have also had regard to the contention on behalf of Limerick that the arbitrator was incorrect in

having regard to the seriousness of the breaches as part of the test for persistence. I am not satisfied that the arbitrator was

incorrect in having regard to seriousness. Breaches which fall short of being fundamental can lie at any point on a spectrum of

seriousness from the highly trivial or technical to those which fall only just short of being fundamental. The length of time for which a

breach might be set to persist (in the case of a continuous breach) or the frequency of its occurrence (in the case of one-off

breaches) are of course important factors in determining persistence. However it does seem to me that seriousness is also a factor. A

less frequent occurrence of a quite serious breach could well justify a finding of persistence while a more frequent occurrence of a

relatively trivial breach might not, in my view, justify such a finding. I am not, therefore, satisfied that the arbitrator was in error in

having regard to seriousness as part of the test.

12.10 Finally it is necessary to refer to the procedural complaint made under this heading. On the basis of what I have considered to

be the appropriate construction of the arbitrator’s award on this topic taken as a whole I have therefore come to the view that he

applied the appropriate test, that there was therefore no error, and that he did not, therefore, apply a test upon which the parties,

and in particular Limerick, did not have an opportunity to be heard.

13. Issues other than error

13.1 In relation to those issues, other than error on the face of the award, upon which reliance is placed I have come to the following

views:-

13.2 (i) the letter of the 18th May

I now turn to the contention that the Arbitrator failed to resolve the issue of the effect (if any) of the letter of the 18th May on the

contract. Such a failure can, of course, amount to misconduct of the proceedings Samuel v. Cooper (1835) 2 Ad & EI 752. For

reasons which I advert to later (see para. 14.3) I have come to the view that the arbitrator does not, necessarily, have to answer

each issue raised at the hearing (whether by pleading, written submissions, oral argument, or on an “issue paper” prepared by the

parties) unless that issue is necessary to resolve the case which he is hearing.

13.3 Under this heading attention is drawn to the fact that the arbitrator, in paragraph 91, of the award asked himself the question

as to whether that letter of 18th May, 2000 made the exercise by Uniform of the entitlement which the arbitrator found arose under

s. 7.4 (i.e. to propose a different tunnel provided it complied with the various conditions set out in that clause) subject to Uniform

accepting the risk set out in the letter.

13.4 It seems to me that this question raises in an even starker way the difficulty that has, in my view, given rise to much of the

ambiguity in the contract in this case. That is the practice of binding in of documents to the contract and deeming them to be part of

the contract without specifying the role which they are to play in the overall contractual picture. The arbitrator found, as a fact, that

prior to the execution of the contract it had been made clear to the engineer that Uniform did not accept that which was set out in

the letter of the 18th May. I am, I have to say, somewhat at a loss to understand the purpose of binding in to the contractual

documents a proposal which, it was common case, had been rejected.

13.5 It is true to say that the arbitrator does not appear to have specifically answered this question in express terms. The approach

to construing an award of an arbitrator by the courts is illustrated by Stillorgan Orchard Limited v. McLoughlin and Harvey [1978]

I.L.R.M. 128 where Hamilton J. came to the conclusion that an award of an arbitrator will be sustained although the arbitrator may

have omitted in his award to notice some claim put forward by a party if according to a fair interpretation of the award it is to be

presumed that the arbitrator is taking the claim into consideration in making the award. The overall principle is that it is not

appropriate to parse and analyse an arbitrators award but rather to consider from an overall point of view whether it may be said that

the arbitrator has dealt properly with each of the matters referred to him. In the light of the arbitrators findings of fact in relation to

the rejection of the letter of 18th May and of the remainder of the award on this aspect of the case, it seems to me that the

appropriate inference to draw is that the arbitrator did not consider that the inclusion of the letter of 18th May in the contractual

documents had any affect on the relevant terms of the contract. Given the history, as found by the arbitrator, of its inclusion in

those documents and given the absence of any express guidance in the contract documents as to how the inclusion of inconclusive

letter was to affect the overall interpretation of the contract, this is a hardly surprising conclusion.

13.6 Applying the test identified at 13.2 above and taking, as I feel I should, the overall approach to the construction of an arbitral

award illustrated by Stillorgan Orchard, I do not believe that the Arbitrator has failed to decide a matter referred to him. Unless

required by the arbitration agreement, an award will not be set aside because the arbitrator has not found separately on each matter

referred to him Whitworth v. Hulse (1866) LR 1 Exch 251. The Arbitrator, having found on the overall issue, was not required to make

a specific finding on the effect of the letter of 18th May unless it was necessary to his conclusions. I am satisfied that a fair reading

as the award as a whole leads to the view that the arbitrator did not consider that the letter effected the contractual obligations of

the parties in a relevant manner. On that basis I am not satisfied that the Arbitrator failed to decide an issue necessary to resolve

the case.

13.7 (ii) Clause 63 and the “reasonable engineer”

The next contention made on behalf of Limerick, concerns the question of whether a reasonable engineer could have formed the

opinion that a Clause 63 certificate was justified on the grounds of lack of diligence and persistent breach of contract as of 18th

September, 2001. Again the contention is that the Arbitrator failed to decide a matter referred to him. The same test applies. The

arbitrator concluded that the engineer was wrong in his interpretation of the contract in respect of the cost of ground treatment, the

ground conditions encountered in respect of certain specified aspects, the necessity for further ground investigation, and the

competence of Uniform’s tunnelling operations. It is clear therefore that the arbitrator formed the view that the engineer had, by

virtue of a misconstruction of the contract, taken into account wrong matters informing his view to issue a section 63 certificate.

Having taken that view it was, in my view, open to the arbitrator to form the view that the answer to the question posed was no. If

the section 63 certificate was to fall then it was unnecessary to consider whether there was more than one ground upon which it

could fall. I can therefore find nothing wrong with the way in which the arbitrator determined this aspect of the case before him.

13.8 (iii) did the Arbitrator “invent” a test

It is undoubtedly the position that deciding a case on a point not put to the parties can amount to a misconduct of the proceedings.

Société Franco-Tunisienne d’Armenment-Tunis v. Government of Ceylon [1959] 3 All E.R. 25. However given the construction which I

have placed on the award (see para. 12.10) I am not satisfied that the arbitrator in fact applied a test which had not been

canvassed.

14. Specific Issues

14.1 Finally before indicating my final conclusions I should indicate that I have given consideration to the argument addressed by

Uniform that many of the questions in respect of which it is alleged that the arbitrator fell into error are, in any event, specific

questions referred to the arbitrator and thus outside the scope of the error jurisdiction of the court. As indicated above it is a matter

of construction to determine the matters specifically referred to the arbitrator. In this case, unusually, there was no formal reference

to arbitration. The arbitrator was nominated in accordance with the terms of the arbitration agreement and the issues between the

parties became refined by pleading. Furthermore in the course of the hearing both parties suggested specific lists of questions which

they invited the arbitrator to answer.

14.2 It does not seem to me that the fact that an issue becomes apparent on the pleadings always contained in one or other of what

might loosely be termed an issue paper means that the issue concerned was specifically referred to the arbitrator in that sense. The

overall issue which was referred to the arbitrator concerned the monies to which Uniform may be entitled on foot of the contract.

There are, of course, many building blocks which have to be put in place before reaching a conclusion on that question. Most critically

the validity or otherwise of the forfeiture of the contract will necessarily have a profound effect on the calculation of Uniform’s

entitlements. But even that issue is simply a means to an end rather than the end itself. I am not, therefore, satisfied that any of the

matters in contention in these proceedings could be said to have been specifically referred to the arbitrator in the sense in which that

term is used in the jurisprudence. The fact that they specifically arose in pleadings or were contained within specific questions put to

the arbitrator is not, in my view, sufficient. If, therefore, I was wrong in coming to the view that there were no errors on the face of

the award of a sufficiently fundamental character to warrant the intervention of the court I would not take the view that Uniform was

entitled to escape from the consequences of any fundamental error on the grounds of the exception that arises where there has been

a specific reference of the question concerned to the arbitrator.

14.3 However I should not leave this aspect of the case without commenting that it seems to me that analysis cuts both ways. It is

equally true that the fact that specific questions appeared on the relevant issue papers does not, of itself, necessarily oblige the

arbitrator to answer them. The arbitrator is obliged to answer all questions necessary to come to a final conclusion of the matters

referred to him. The fact that he may take the view that in the light of his answers to some questions others need not be answered

at all or need not be answered in the way in which the parties might have put them, does not, it seems to me, mean that the

arbitrator could not be said to have dealt properly with the issues before him.

15. Discretion

15.1 As a fallback position at the hearing Uniform argued that even if I were to reject their principal arguments I should, in my

discretion, not to intervene to set aside the award. Uniform placed reliance on Lamprell v. Billeircay Union (1849) 18 L.J. Ex 283 in

which it was held that the court, in its discretion, might decline to set aside an aspect of an award of an arbitrator (even though

there was a proper basis for so doing) if it should be the case that the aspect to be set aside would not affect the overall result of

the arbitration.

15.2 On that basis Uniform contends that even if any of the arguments which challenge the Arbitrator’s finding as to the validity of

the Clause 63 certificate on the basis of the finding of their being no “persistent breach” were correct, the certificate would in any

event have fallen for other reasons such as the finding in para. 304.4 of the award that one of the members of the “engineer” as

specified in the contract did not participate in the decision to issue the Clause 63 certificate. However I am not persuaded that the

findings of the arbitrator in relation to persistent breach could not have affected the overall result.

15.3 Having regard to the views which I have expressed above in relation to the arbitrator’s findings concerning “persistent breach”

the question of the exercise of a discretion does not arise. However lest this case should go further it seems to me appropriate that I

should indicate that in the event that I am wrong in relation to those views, it would not have been my view that I should have

exercised any discretion in favour of Uniform on the basis that I am not persuaded that the determination of the arbitrator in respect

of persistent breach could have made no difference to the overall outcome of the arbitration.

16. Conclusions

For all of the above reasons I have come to the view that none of the issues raised are sufficient to warrant the exercise by the

court of its jurisdiction to interfere with the arbitrator’s award.