Contractor's Premature Refusal Excuses Client from Termination Deadline and Triggers General Non-Performance Rules

Case Number 1B 11 28
Court / Authority
Jurisdiction Switzerland · Canton of Lucerne (CH-LU)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

In a work contract dispute where the contractor definitively refused to continue the work, the court held that such premature refusal by the contractor entitles the client to proceed under the rules for non-performance (Art. 107 para. 2 OR), bypassing the need to first invoke the specific termination clause for work contracts (Art. 366 para. 1 OR). The court reasoned that the contractor's clear and unwarranted declaration of non-performance effectively excuses the client from setting a deadline, and in cases where the client chooses to claim damages for non-performance while upholding the contract, the calculation of damages must adhere to the principles established for breach of contract generally (Art. 97 OR), obligating the client to compensate the contractor for any completed, usable work performed up to that point.

Legislator headnote

Official

Art. 97, 107 und 366 OR. Die Auflösung des Werkvertrags durch den Unternehmer ist aus wichtigen Gründen möglich. Die vorzeitige Herstellungs- und Ablieferungsverweigerung des Unternehmers berechtigt dagegen den Besteller zu einem Vorgehen nach Art. 107 Abs. 2 OR, ohne dass Art. 366 Abs. 1 OR herangezogen werden müsste. Für die Ermittlung des Nichterfüllungsschadens gelten die zu Art. 97 OR entwickelten Regeln. | Zivilrecht

Keywords

AI generated
termination of a contract contractor premature performance obligation to contract nullity of contract positive breach of contract

Cited Legislation

AI generated

Cited Case Law

AI generated
AI generated

Key legal questions extracted by Legislator

AI generated
Art. 107 Abs. 2 OR

Cited as the legal basis for the purchaser (Besteller) to proceed against the contractor's refusal to perform.

Art. 97 OR

Cited as the basis for the principles applicable to damages for non-performance when the purchaser opts for damages instead of withdrawal.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Rechtsprechung Luzern

Instanz: · Obergericht

Abteilung: · 1. Abteilung

Rechtsgebiet: · Zivilrecht

Entscheiddatum: · 10.01.2012

Fallnummer: · 1B 11 28

LGVE: · 2012 I Nr. 13

Leitsatz: · Art. 97, 107 und 366 OR. Die Auflösung des Werkvertrags durch den Unternehmer ist aus wichtigen Gründen möglich. Die vorzeitige Herstellungs- und Ablieferungsverweigerung des Unternehmers berechtigt dagegen den Besteller zu einem Vorgehen nach Art. 107 Abs. 2 OR, ohne dass Art. 366 Abs. 1 OR herangezogen werden müsste. Für die Ermittlung des Nichterfüllungsschadens gelten die zu Art. 97 OR entwickelten Regeln.

Rechtskraft: · Diese Entscheidung ist rechtskräftig.

Das Bundesgericht hat die dagegen erhobene Beschwerde in Zivilsachen am 31. Mai 2012 abgewiesen [4A_156/2012].