Nature of deadline in construction violation report where legalization procedure was not completed and no demolition order obtained
Legislator-Zusammenfassung
KI-generiertThe High Court of Cassation and Justice admitted the appeal in the public interest filed by the appellate court's leadership, establishing a binding uniform interpretation for the civil procedure code. The dispute concerned the legal nature of a deadline stipulated in an administrative violation report under construction law, specifically whether it functioned as a mandatory expiration point or a recommendation when the authority failed to secure a demolition order and the party did not complete the legalization process within the allotted time. Relying on Article 28 of Law no. 50/1991 regarding construction authorization, the court determined that in such circumstances, the deadline in the violation report is of a recommendatory nature, not obligatory.
Legislator-Regeste
KI-generiertart.28 din Legea nr. 50/1991, art. 517 alin. (4) din Codul de procedură civilă; Nature of deadline in construction violation report where legalization procedure was not completed and no demolition order obtained: The dispute concerned the legal nature of a deadline stipulated in an administrative violation report under construction law, specifically whether it functioned as a mandatory expiration point or a recommendation when the authority failed to secure a demolition order and the party did not complete the legalization process within the allotted time. Relying on Article 28 of Law no. 50/1991 regarding construction authorization, the court determined that in such circumstances, the deadline in the violation report is of a recommendatory nature, not obligatory.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertZentrale Rechtsfragen, extrahiert von Legislator
KI-generiertCited in the final operative order to establish the mandatory nature of the court's decision regarding the uniform interpretation of the law.
Volltext
R O M Â N I A
ÎNALTA CURTE DE CASAŢIE ŞI JUSTIŢIE
Completul pentru soluționarea recursului în interesul legii
Minuta deciziei nr. 10 Dosar nr. 800/1/2021
Şedinţa de la 28 iunie 2021
ÎN NUMELE LEGII
D E C I D E :
Admite recursul în interesul legii formulat de Colegiul de conducere al Curţii de Apel Alba Iulia şi, în consecinţă, stabileşte că:
În interpretarea şi aplicarea unitară a dispoziţiilor art.28 din Legea nr. 50/1991 privind autorizarea executării lucrărilor de construcţii, republicată, cu modificările şi completările ulterioare, în ipoteza în care partea nu a demarat sau nu a finalizat, în termenul acordat, procedura de intrare în legalitate, iar autoritatea nu a obţinut o hotărâre de demolare a construcţiei, termenul stabilit în procesul-verbal de constatare a contravenţiei este unul de recomandare.
Obligatorie, potrivit dispoziţiilor art. 517 alin. (4) din Codul de procedură civilă.
Pronunţată în şedinţă publică, astăzi, 28 iunie 2021.