Supreme Court allows cassation complaints in construction contract dispute regarding payment obligations.
Legislator-Zusammenfassung
KI-generiertThe Supreme Court of Poland accepted both cassation complaints filed by the plaintiff and the intervening party for further review. The dispute involves a construction contract where the plaintiff sought payment from the defendant company, with a third party intervening. The court decided to proceed with the case because the lower court's judgment required clarification on specific legal interpretations regarding the contractual obligations.
Legislator-Regeste
KI-generiertArt. 385 § 1 k.p.c.; Art. 386 § 1 k.p.c.: The Supreme Court may accept cassation complaints when the lower court's judgment involves a question of law requiring clarification or when the application of the law was incorrect.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVolltext
Sygn. akt V CSK 292/17 POSTANOWIENIE Dnia 21 listopada 2017 r.Sąd Najwyższy w składzie: SSN Władysław Pawlak w sprawie z powództwa W. Firmy Budowlanej Sp. z o.o. we W.przeciwko M. Sp. z o.o. Sp. komandytowej we W.z udziałem interwenienta ubocznego Przedsiębiorstwa Budowlanego J. Sp. z o.o. we W.o zapłatę,na posiedzeniu niejawnym w Izbie Cywilnej w dniu 21 listopada 2017 r.,na skutek skargi kasacyjnej strony powodowej i interwenienta ubocznego od wyroku Sądu Apelacyjnego we W.z dnia 12 lipca 2016 r., sygn. akt I ACa …/16, przyjmuje obie skargi kasacyjne do rozpoznania.