Regional Planning Association Lacks Standing to Challenge Road Project Noise Abatement
Legislator-Zusammenfassung
KI-generiertA regional planning association challenged the approval of a national road project, specifically concerning noise abatement measures. The court ruled that the association lacked the legal standing to appeal. The court reasoned that the association's objectives and legal status did not demonstrate a direct or sufficiently close relationship to the national road project or its environmental impact, particularly noise pollution, to grant it standing to challenge the decision.
Legislator-Regeste
AmtlichNationalstrassen-Ausführungsprojekt | Schallschutzmassnahmen entlang der Nationalstrasse N 1.1.1 (Zürich Hardturm bis Kantonsgrenze Aargau) Fehlende Legitimaion zur Rechtsmittelerhebung eines regionalen Planungsverbands.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertZentrale Rechtsfragen, extrahiert von Legislator
KI-generiertThe court used this provision to determine the scope of the approval process for national road projects, which was central to the decision on the appeal's admissibility.
This provision likely relates to the general rules of procedure or appeal, applied in the context of the administrative court's jurisdiction.
This provision of cantonal planning and building law was likely used to assess the legal basis for the project and the rights of parties involved.
This specific provision of cantonal planning and building law was probably applied to define the specific procedural rights or obligations related to the execution project.
This provision of environmental protection law was likely considered in relation to the environmental impact of the road project, potentially affecting the legitimacy of the appeal.
This provision of cantonal administrative procedure law was likely applied to determine the admissibility of the appeal, specifically regarding the standing of the appellant.
This federal administrative procedure law provision was likely used to assess the legitimacy or standing of the appellant to file an appeal.
Volltext
Verwaltungsgericht des Kantons Zürich: VB.2000.00147
--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)
[Druckansicht](/cgi-bin/nph-omniscgi.exe?OmnisPlatform=WINDOWS&WebServerUrl=&WebServerScript=/cgi-bin/nph-omniscgi.exe&OmnisLibrary=JURISWEB&OmnisClass=rtFindinfoWebHtmlService&OmnisServer=JURISWEB,127.0.0.1:7000&Parametername=WWW&Schema=ZH_VG_WEB&Source=&Aufruf=getDocument&cSprache=GER&nF30_KEY=106138&W10_KEY=13317155&nTrefferzeile=1&Template=standard/results/printviewdocument.fiw)
--- · --- · --- · Geschäftsnummer: · VB.2000.00147 · Entscheidart und -datum: · Endentscheid vom 26.04.2001 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Raumplanungs-, Bau- und Umweltrecht · Betreff: · Nationalstrassen-Ausführungsprojekt · Schallschutzmassnahmen entlang der Nationalstrasse N 1.1.1 (Zürich Hardturm bis Kantonsgrenze Aargau) Fehlende Legitimaion zur Rechtsmittelerhebung eines regionalen Planungsverbands. · --- · Stichworte: · AUSFÜHRUNGSPROJEKT BESCHWERDERECHT EINSPRACHE LEGITIMATION NATIONALSTRASSE ORGANISATIONEN PLANUNGSGRUPPE VERBANDSBESCHWERDE VEREINIGUNG ZUSTÄNDIGKEIT DES VERWALTUNGSGERICHTS · Rechtsnormen: · Art. 12 NHG Art. 103 OG § 12 PBG § 338a Abs. II PBG Art. 55 USG § 21 lit. a VRG Art. 48 VwVG · Publikationen: · RB 2001 Nr. 8 · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3