Legislator Case Law & Legislation
T 2302-24 AI generated

Consumer's failure to deliver bank guarantee does not prevent business owner from rescinding small house contract.

Case Number T 2302-24
Court / Authority
Jurisdiction Sweden (SE)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The Supreme Court allowed the business owner to rescind the small house contract because the consumer failed to deliver the agreed bank guarantee. The court determined that the business owner's compensation for work already performed must be calculated based on the completion degree and nature of the work at the time of rescission. This decision clarifies that the lack of a bank guarantee is a valid ground for contract termination without requiring the consumer to provide alternative security.

Legislator headnote

AI generated

Contract Act; Small House Contract Act: A consumer's failure to deliver an agreed bank guarantee constitutes a valid ground for the business owner to rescind the contract, with compensation for work performed calculated based on the work's completion degree and nature at the time of rescission.

Keywords

AI generated
small house contract bank guarantee requirement contract rescission work compensation calculation consumer protection law

Cited Legislation

AI generated
Contract Act
Small House Contract Act
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

En näringsidkare har ansetts ha haft rätt att häva ett småhusentreprenadavtal med hänvisning till att konsumenten inte överlämnat en avtalad bankgaranti. Näringsidkarens ersättning för redan utfört arbete har bestämts med beaktande av arbetets färdigställandegrad och beskaffenhet vid hävningstidpunkten.