Court dismisses appeal for delay in environmental permit review due to unnecessary water authority scheduling request.

Case Number ÖM 2011-26
Court / Authority
Jurisdiction Sweden (SE)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Mark- och miljööverdomstolen dismissed the applicant's appeal regarding delays in an environmental permit application. The applicant argued that the authority unnecessarily requested a time plan from the water authority regarding environmental quality standards review. The court found this procedural step was not an unreasonable delay warranting the appeal's success.

Legislator headnote

AI generated

49 kap. 7 § RB; The court holds that requesting a time plan from a water authority for environmental quality standard review does not constitute an unreasonable delay under the Administrative Procedure Act.

Keywords

AI generated
unreasonable delay environmental permit procedural delay water authority administrative procedure

Cited Legislation

AI generated
49 kap. 7 § RB
Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap.
AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap. MB. MÖD har ansett att MMD försenat målets handläggning i onödan genom att begära en tidsplan från vattenmyndigheten avseende dess översyn av miljökvalitetsnormerna i området.