Court allows correction of expired temporary building permit via action order when new planning work is pending.
Legislator summary
AI generatedThe Mark- och miljööverdomstolen allowed the use of an action order under the Planning and Building Act to correct an expired temporary building permit. The applicant argued that the old permit had lapsed, while the opposing party contended that a new planning process was underway, making a strict correction disproportionate. The court ruled that since new planning work is in progress and a future permit is likely, the action order is a proportionate measure to regularize the situation.
Legislator headnote
AI generated11 kap 19 § plan- och bygglagen; 11 kap 19 § 1 st. plan- och bygglagen: An action order may be used to correct an expired temporary building permit if new planning proceedings are underway and a subsequent permit is probable, rendering strict enforcement disproportionate.
Keywords
AI generatedCited Legislation
AI generatedRelated Decisions
AI generatedFull text
MÖD har bedömt att ett åtgärdsföreläggande enligt 11 kap 19 § plan- och bygglagen kan användas för rättelse när tiden för ett bygglov för tillfällig åtgärd enligt den äldre plan- och bygglagen löpt ut. I detta fall ansågs dock ett föreläggande oproportionerligt eftersom ett planarbete pågår för den berörda fastigheten och det är sannolikt att bygglov kommer att kunna medges i efterhand för åtgärden.