Portuguese court rules that mere notification of defects is insufficient; the owner must formally demand correction to trigger the contractor's obligation.
Legislator summary
AI generatedThe Tribunal da Relação do Porto revoked the lower court's judgment regarding a construction dispute between an owner and a contractor. The owner argued that notifying the contractor of defects was sufficient to demand repairs, while the contractor contended that formal legal intervention was required. The court held that notification alone does not create the obligation to correct; the owner must actively exercise their right by formally interpelling the contractor, which can be done via a peremptory exception.
Legislator headnote
OfficialEMPREITADA DIREITOS DO DONO DA OBRA DEFEITO DA OBRA RECUSA DE PAGAMENTO EXCEPÇÃO PEREMPTÓRIA
Keywords
AI generatedCited Legislation
AI generatedFull text
[DATA DEC. RECORRIDA] 06/13/1996
[Nº CONVENCIONAL] JTRP00018848
[Nº DO DOCUMENTO] RP199706129621545
[PRIVACIDADE] 1
[PROCESSO NO TRIBUNAL RECORRIDO] 219/93-4
[TEXTO INTEGRAL] N
[TRIBUNAL RECORRIDO] T CIRC PENAFIEL
[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/FC35ED213DECAD228025686B0066F993?OpenDocument
SUMÁRIO
I - Não basta que o dono da obra dê conhecimento ao empreiteiro da existência dos defeitos. Facto essencial para a existência da obrigação de correcção dos defeitos é que o dono da obra exerça o correspondente direito, interpelando o empreiteiro para que proceda à correcção. Este direito à eliminação dos defeitos pode ser exercido por via de excepção.