Portuguese court confirms that the statute of limitations for construction defects begins at contract delivery and payment.
Legislator summary
AI generatedThe Tribunal da Relação do Porto confirmed the lower court's decision regarding a claim for repair of defects in a sold property. The plaintiff argued for a later start to the limitation period, but the court held that under the Civil Code, the clock starts upon contract fulfillment, specifically delivery and payment. Consequently, the claim was deemed time-barred because the statutory period had expired before the action was filed.
Legislator headnote
OfficialCOMPRA E VENDA DEFEITO DA OBRA CADUCIDADE DA ACÇÃO RENÚNCIA MORA DO CREDOR
Keywords
AI generatedCited Legislation
AI generatedFull text
[DATA DEC. RECORRIDA] 06/17/1998
[Nº CONVENCIONAL] JTRP00024004
[Nº DO DOCUMENTO] RP199812219851158
[PRIVACIDADE] 1
[PROCESSO NO TRIBUNAL RECORRIDO] 185/94
[TEXTO INTEGRAL] N
[TRIBUNAL RECORRIDO] T CIRC STA MARIA FEIRA
[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/C8CE403CF1F582AF8025686B00671DF3?OpenDocument
SUMÁRIO
I - O prazo de caducidade da acção prevista no artigo 917 do Código Civil para exigir a reparação de defeitos da coisa imóvel vendida, conta-se desde o cumprimento do contrato que, na compra e venda, ocorre com a entrega da coisa e com o pagamento do preço.
II - A renúncia a qualquer direito, sendo um acto voluntário, deve resultar de um acto do credor que a exprima inequivocamente.
III - Verificada a falta de colaboração do credor na eliminação dos defeitos da coisa vendida, ainda possíveis de reparar, o devedor, para se exonerar da sua obrigação, deveria fixar àquele um prazo razoável para ele pôr fim à mora, permitindo a entrada no imóvel vendido para o devedor eliminar os defeitos.