Contract price element is constitutive of construction contract and basis for claimed rights.
Legislator summary
AI generatedThe Tribunal da Relação do Porto confirmed the lower court's judgment regarding a construction contract dispute. The court held that the price element, whether precisely or imprecisely indicated, is a constitutive factor of the contract and the foundation for any rights claimed thereunder. Consequently, the appeal was rejected because the price remains an essential component defining the contractual relationship and the associated obligations.
Legislator headnote
OfficialEMPREITADA PREÇO
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedFull text
[DATA DEC. RECORRIDA] 10/27/1993 [Nº CONVENCIONAL] JTRP00014079 [Nº DO DOCUMENTO] RP199503079321040 [PRIVACIDADE] 1 [PROCESSO NO TRIBUNAL RECORRIDO] 2275/2S [TEXTO INTEGRAL] N [TRIBUNAL RECORRIDO] T J V N GAIA [URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/B7937F2A89CC87B08025686B0066AC70?OpenDocument
SUMÁRIO I - O elemento preço, precisa ou imprecisamente indicado, é factor constitutivo do contrato de empreitada e, logo, do direito que com base nele se alegue.