AI generated

The Tribunal da Relação do Porto allowed the resolution of a contract-promissory due to the debtor's negligent breach and the creditor's subsequent loss of interest. The court found that the creditor failed to prove the loss of interest objectively, relying solely on subjective valuation. Consequently, the court ruled that the legal requirements for rescission were not met under the cited civil code provisions.

Legislator headnote

Official

CONTRATO-PROMESSA RESOLUÇÃO DO CONTRATO INCUMPRIMENTO DO CONTRATO MORA DO DEVEDOR PERDA DE INTERESSE DO CREDOR

Keywords

AI generated
contract-promissory negligent breach loss of interest objective assessment contract resolution

Cited Legislation

AI generated
CCIV Art. 66
CCIV Art. 432
CCIV Art. 801
CCIV Art. 808

Cited Case Law

AI generated
AC STJ DE 1997/11/27 IN BMJ N471 PAG391

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[Nº CONVENCIONAL] JTRP00035147

[Nº DO DOCUMENTO] RP200305120352112

[PRIVACIDADE] 1

[TEXTO INTEGRAL] N

[TRIBUNAL RECORRIDO] 1 V MISTA V N GAIA

[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/9B429E9FD3E8F2EB80256DC50030CC92?OpenDocument

SUMÁRIO

I - Há fundamento legal para a resolução de contrato, designadamente de contrato-promessa, no caso de mora culposa de uma das partes e de a outra, em resultado dessa mora, ter perdido o interesse na prestação.

II - Essa perda de interesse deve ser apreciada objectivamente, com base em elementos susceptíveis de valoração por qualquer pessoa, e não segundo o juízo valorativo apenas do próprio credor.