Court holds contractor's breach of duty of collaboration constitutes debtor's delay in accepting performance under Civil Code.
Legislator summary
AI generatedThe Tribunal da Relação do Porto revoked the lower court's decision regarding a contractor's claim for delay. The court found that the owner's failure to collaborate constituted a duty of creditor rather than a true obligation, triggering 'mora accipiendi'. Consequently, the contractor was deemed to have accepted the work late due to the owner's inaction.
Legislator headnote
OfficialCONTRATO DE EMPREITADA VIOLAÇÃO DEVER DE COLABORAÇÃO DAS PARTES MORA DO CREDOR
Keywords
AI generatedCited Legislation
AI generatedFull text
[DATA DEC. RECORRIDA] 10/13/1998 [Nº CONVENCIONAL] JTRP00025986 [Nº DO DOCUMENTO] RP199906299920419 [PRIVACIDADE] 1 [PROCESSO NO TRIBUNAL RECORRIDO] 207/96-1 [TEXTO INTEGRAL] N [TRIBUNAL RECORRIDO] T J FELGUEIRAS 1J [URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/8C32FCBDBB66071B8025686B00673429?OpenDocument
SUMÁRIO
I - No contrato de empreitada, o dever de colaboração que impende sobre o dono da obra, não constitui uma verdadeira obrigação, mas antes um dever de credor, cuja violação faz incorrer o comitente em
" mora accipiendi ".