9920419 AI generated

Court holds contractor's breach of duty of collaboration constitutes debtor's delay in accepting performance under Civil Code.

Case Number 9920419
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Partially Allowed

Legislator summary

AI generated

The Tribunal da Relação do Porto revoked the lower court's decision regarding a contractor's claim for delay. The court found that the owner's failure to collaborate constituted a duty of creditor rather than a true obligation, triggering 'mora accipiendi'. Consequently, the contractor was deemed to have accepted the work late due to the owner's inaction.

Legislator headnote

Official

CONTRATO DE EMPREITADA VIOLAÇÃO DEVER DE COLABORAÇÃO DAS PARTES MORA DO CREDOR

Keywords

AI generated
contractor agreement duty of collaboration creditor's duty mora accipiendi Civil Code Article 813 delay in acceptance unanimous decision

Cited Legislation

AI generated
CCIV66 Art. 813

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[DATA DEC. RECORRIDA] 10/13/1998 [Nº CONVENCIONAL] JTRP00025986 [Nº DO DOCUMENTO] RP199906299920419 [PRIVACIDADE] 1 [PROCESSO NO TRIBUNAL RECORRIDO] 207/96-1 [TEXTO INTEGRAL] N [TRIBUNAL RECORRIDO] T J FELGUEIRAS 1J [URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/8C32FCBDBB66071B8025686B00673429?OpenDocument

SUMÁRIO

I - No contrato de empreitada, o dever de colaboração que impende sobre o dono da obra, não constitui uma verdadeira obrigação, mas antes um dever de credor, cuja violação faz incorrer o comitente em

" mora accipiendi ".