Contractor's defense of non-performance in construction contract leads to dismissal of owner's claim for damages.

Case Number 0020606
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court confirmed the lower court's decision dismissing the owner's claim for damages against the contractor. The contractor successfully raised the defense of non-performance, arguing that the owner had failed to pay the agreed price as stipulated in the contract. Consequently, the court ruled that the contractor was entitled to have the claim absolved without prejudice to a future lawsuit if the owner subsequently proves payment.

Legislator headnote

Official

CONTRATO DE EMPREITADA EXCEPÇÃO DE NÃO CUMPRIMENTO ABSOLVIÇÃO DO PEDIDO

Keywords

AI generated
contract of undertaking defense of non-performance absolution of claim construction contract law mutual performance

Cited Legislation

AI generated
CCIV Art. 428

Cited Case Law

AI generated
AC RP DE 1989/05/01 IN CJ T3 ANOXIV PAG210

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[DATA DEC. RECORRIDA] 09/21/1999

[Nº CONVENCIONAL] JTRP00028879

[Nº DO DOCUMENTO] RP200009190020606

[PRIVACIDADE] 1

[PROCESSO NO TRIBUNAL RECORRIDO] 754/96-1S

[TEXTO INTEGRAL] N

[TRIBUNAL RECORRIDO] T CIV PORTO 1J

[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/303C2A2EE5A74B9C80256992003D4BBA?OpenDocument

SUMÁRIO

A excepção do não cumprimento é mera excepção material ou substancial que conduz à absolvição do pedido e paralisa temporariamente a pretensão daquele a quem essa excepção é oposta.

Assim, num contrato de empreitada em que o dono da obra deixa de pagar ao empreiteiro, contra o clausulado, as respectivas prestações do preço, pode o mesmo empreiteiro, quando demandado por esse dono para o indemnizar pela suspensão dos trabalhos da empreitada, opor-lhe a excepção de não cumprimento e, consequentemente, obter a absolvição do pedido, sem que isso impeça, no entanto, que o referido dono o demande novamente, desde que alegue e prove ter-lhe satisfeito a prestação ou prestações cuja falta fundamentou a excepção.