Contractor's appeal dismissed; moral damages for stress denied; payment due at acceptance; no bad faith found.

Case Number 0252170
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Partially Allowed

Legislator summary

AI generated

The Tribunal da Relação do Porto partially revoked the lower court's decision, dismissing the contractor's appeal regarding moral damages while upholding the obligation to pay the contract price. The court found that the psychological distress suffered by the homeowner and spouse was insufficient in gravity to warrant compensation, and that the contractor's actions in seeking the remaining balance did not constitute bad faith. Consequently, the judgment was modified to deny the claim for non-pecuniary damages while confirming the financial liability of the contractor.

Legislator headnote

Official

EMPREITADA MODIFICABILIDADE DA DECISÃO DE FACTO PAGAMENTO PREÇO DANOS MORAIS LITIGÂNCIA DE MÁ FÉ

Keywords

AI generated
contract price payment moral damages denial bad faith litigation construction contract acceptance psychological distress sufficiency

Cited Legislation

AI generated
CCIV Art. 66
CCIV Art. 496
CCIV Art. 1211 n.º 2
CPC95 Art. 456 n.º 1 n.º 2 alínea b

Cited Case Law

AI generated
AC STJ de 1998/11/17 IN CJSTJ T3 ANOVI PAG124

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[Nº CONVENCIONAL] JTRP00035505

[Nº DO DOCUMENTO] RP200301130252170

[PRIVACIDADE] 1

[TEXTO INTEGRAL] N

[TRIBUNAL RECORRIDO] 9 V CIV PORTO

[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/2DA5871F8628298680256CE600374C5D?OpenDocument

SUMÁRIO

I - O sistema de gravação sonora dos meios de prova é só por si insuficiente para fixar todos os elementos susceptíveis de condicionar ou influenciar a convicção do Juiz.

II - Na falta de cláusula contratual ou de uso em contrário, o preço de empreitada deve ser pago no acto de aceitação da obra.

III - Não merece a tutela do direito, por insuficiência da gravidade do dano, o desgaste psíquico e nervoso sofrido pelo dono da obra e esposa pelo facto de o empreiteiro não a ter acabado nem eliminado os defeitos.

IV - Os pagamentos efectuados no decorrer das empreitadas e os defeitos existentes nos trabalhos realizados, não constituem suporte bastante para se concluir que o empreiteiro tenha actuado com dolo ou negligência grave, como litigante de má fé, ao accionar o dono da obra para lhe cobrar o remanescente do preço.