Provisional injunction denied when it does not match the main pending lawsuit's scope or request.
Legislator summary
AI generatedThe court refused the provisional injunction because the requested measure failed to align with the scope of the main pending action. The plaintiff sought a temporary suspension of construction, but the court found a mismatch between this request and the ultimate relief sought in the primary lawsuit. Consequently, the court ruled that the injunction could not be granted as it did not effectively safeguard the intended outcome of the main case.
Legislator headnote
OfficialPROVIDÊNCIA CAUTELAR EMBARGO DE OBRA NOVA
Keywords
AI generatedCited Legislation
AI generatedFull text
[Nº CONVENCIONAL] JTRL00001350
[Nº DO DOCUMENTO] RL199512070008642
[PRIVACIDADE] 1
[TEXTO INTEGRAL] N
[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/AC49797217B02D36802568030003F6FD?OpenDocument
SUMÁRIO
I - No embargo de obra nova, o que se tem em vista
é suspender provisoriamente uma obra cuja suspensão definitiva ou cuja demolição possa vir a ser decretada na acção.
II - Constatando-se um desajustamento entre o pedido da providência e o da acção principal já pendente e a que foi apensa, não visando aquele acautelar este, deve a procedência ser recusada.