Court confirms sentence regarding railway easement removal requiring prior compensation payment and technical feasibility.
Legislator summary
AI generatedThe Tribunal da Relação de Lisboa confirmed the lower court's decision on a dispute involving railway easement removal for new construction. The plaintiff argued for the displacement of EDP supports, while the defendant contested the necessity without addressing technical constraints. The court ruled that such removal is only permissible if the concessionaire receives prior compensation under the relevant decree-law and no technical inconveniences exist.
Legislator headnote
OfficialSERVIDÃO DE PASSAGEM EDP REMOÇÃO LEI APLICÁVEL OBRAS
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedFull text
[Nº CONVENCIONAL] JTRL00024459
[Nº DO DOCUMENTO] RL198711170019271
[PRIVACIDADE] 1
[REFERENCIA DE PUBLICACAO] CJ 1987 TV PAG106
[TEXTO INTEGRAL] N
[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/169F2C6A4BA2EC7280256803000455C5?OpenDocument
SUMÁRIO
I - Os artigos 43 e segs. do Decreto-Lei n. 43335, de 19-11-60, revogaram o que em contrário se dispunha no Regulamento aprovado pelo Decreto-Lei n. 26852, de 30/07/36, designadamente no seu artigo 52 parágrafo único.
II - O direito de exigir o afastamento dos apoios das linhas de alta tensão, no caso de construção de novos edifícios, depende quer do prévio pagamento ao concessionário da indemnização prevista no artigo 44 do Decreto-Lei n. 43335, quer da inexistência de inconvenientes de ordem técnica na deslocação daqueles apoios.