Portuguese court holds defense of non-performance applies only to bilateral contracts and cannot be used as a counterclaim.

Case Number 96A036
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court dismissed the defendant's attempt to use the defense of non-performance as a counterclaim in a construction contract dispute. The defendant argued that the plaintiff's defects justified withholding payment, but the court clarified that this defense is strictly for bilateral contracts and merely delays performance until defects are fixed. Consequently, the court ruled that the defense cannot be raised as an independent counterclaim but must be integrated into the original defense.

Legislator headnote

Official

EMPREITADA CUMPRIMENTO IMPERFEITO EXCEPÇÃO DE NÃO CUMPRIMENTO DEFESA POR EXCEPÇÃO RECONVENÇÃO

Keywords

AI generated
defense of non-performance construction contract bilateral contract requirement counterclaim limitation Portuguese Civil Code contractual obligations defect remediation

Cited Legislation

AI generated
Art. 483 do Código Civil Português
Art. 484 do Código Civil Português
Art. 485 do Código Civil Português

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[Nº CONVENCIONAL] JSTJ00030250

[Nº DO DOCUMENTO] SJ199606180000361

[PRIVACIDADE] 1

[PROCESSO NO TRIBUNAL RECURSO] 1342/93

[TEXTO INTEGRAL] N

[TRIBUNAL RECURSO] T REL COIMBRA

[URL] https://www.dgsi.pt/jstj.nsf/954f0ce6ad9dd8b980256b5f003fa814/C6F6F49633786CEF802568FC003B0B32?OpenDocument

SUMÁRIO

I - A excepção de não cumprimento diz respeito a contratos bilaterais ou sinalagmáticos.

II - O funcionamento da excepção apenas justifica um retardamento ou dilação na prestação devida por quem dela beneficia até que cesse o incumprimento da outra parte.

III - Na empreitada, a dona da obra beneficia da excepção de incumprimento do contrato no que concerne às obrigações da outra parte, pelo que só deve cumprir o que lhe compete depois de eliminados os defeitos averiguados na obra.

IV - A excepção de não cumprimento não tem que ser deduzida em reconvenção, consistindo embora na alegação de factos novos relativamente aos apresentados pelo autor mas sem concretizar um pedido distinto e autónomo contra o autor.