Contractor must prove work completion; delivery date irrelevant if no damages claimed; judgment error irrelevant if price fixed.
Legislator summary
AI generatedThe court dismissed the contractor's request to review the judgment, ruling that the burden of proving work completion and delivery lies with the contractor. The court held that the specific date of delivery is irrelevant when the owner claims no damages or seeks no indemnity for the delay. Consequently, the fixed price remains payable, and a potential judgment error is disregarded as it does not affect the liquidated amount.
Legislator headnote
OfficialEMPREITADA PRESSUPOSTOS ÓNUS DA PROVA MORA DO DEVEDOR EFEITOS ERRO DE JULGAMENTO LIQUIDAÇÃO EM EXECUÇÃO DE SENTENÇA
Keywords
AI generatedCited Legislation
AI generatedFull text
[Nº CONVENCIONAL] JSTJ00028479
[Nº DO DOCUMENTO] SJ199510310869531
[PRIVACIDADE] 1
[PROCESSO NO TRIBUNAL RECURSO] 6943/94
[TEXTO INTEGRAL] N
[TRIBUNAL RECURSO] T REL LISBOA
[URL] https://www.dgsi.pt/jstj.nsf/954f0ce6ad9dd8b980256b5f003fa814/71DC39260E8ECF6D802568FC003AE2C7?OpenDocument
SUMÁRIO
I - Na acção movida pelo empreiteiro contra o dono da obra, para pagamento do preço desta, incumbe àquele alegar e provar que realizou a obra e a entregou.
II - É irrelevante a data da entrega da obra, se o dono desta não alegou prejuízos nem pediu indemnização por essa falta.
III - Realizada e entregue a obra, o dono desta tem de pagar o preço dela, incluindo a prestação que devia ter pago, e não pagou, com a adjudicação da empreitada.
IV - A procedência de um erro de julgamento só deve ser decretada quando revela ou tem virtualidade de vir a ser relevante.
V - Estando determinado o preço da empreitada, e não tendo sofrido alteração que a torne ilíquida, não há que relegar para execução de sentença o pagamento daquele.