Continued payments after a construction deadline do not automatically cure the contractor's delay or bar damages.

Case Number 083925
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court dismissed the claim that the contractor's delay was cured by the owner's continued payments after the deadline. The owner argued these payments proved the contractor was still performing, while the contractor contended they extinguished the delay. The court ruled that such payments, made in hope of completion, do not legally erase the delay or exclude the right to damages.

Legislator headnote

Official

EMPREITADA MORA CESSAÇÃO INDEMNIZAÇÃO

Keywords

AI generated
construction contract fixed deadline continuing payments cure of delay damages claim contractor liability extinguishment of mora

Cited Legislation

AI generated
Art. 483 do Código Civil
Art. 484 do Código Civil

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[Nº CONVENCIONAL] JSTJ00021111

[Nº DO DOCUMENTO] SJ199310280839251

[PRIVACIDADE] 1

[PROCESSO NO TRIBUNAL RECURSO] 2596/89

[TEXTO INTEGRAL] N

[TRIBUNAL RECURSO] T REL LISBOA

[URL] https://www.dgsi.pt/jstj.nsf/954f0ce6ad9dd8b980256b5f003fa814/6DFD555540508329802568FC003A7372?OpenDocument

SUMÁRIO

Em contrato de empreitada, com prazo certo, a circunstância de o dono da obra, depois de decorrido esse prazo, ter continuado a fazer entregas de dinheiro, na esperança de ver a obra concluída, não tem só por si, o efeito de cessação ou extinção da mora do empreiteiro nem, consequentemente, a exclusão do direito daquele a indemnização pelos respectivos danos.