Contractor breached equipment supply agreement; supplier must return funds with interest as buyer lost interest.
Legislator summary
AI generatedThe court dismissed the supplier's request to review the contract, ruling that the buyer had lost their interest in performance due to the supplier's breach. The buyer failed to prove the breach was not their own fault, thereby entering default and triggering restitution of received funds with interest. Consequently, the court upheld the original judgment based on established facts regarding the supplier's liability.
Legislator headnote
OfficialCONTRATO DE FORNECIMENTO DE EQUIPAMENTOS INCUMPRIMENTO DO CONTRATO
Keywords
AI generatedCited Legislation
AI generatedFull text
[Nº CONVENCIONAL] JSTJ00012374
[Nº DO DOCUMENTO] SJ198701220739672
[PRIVACIDADE] 1
[TEXTO INTEGRAL] N
[URL] https://www.dgsi.pt/jstj.nsf/954f0ce6ad9dd8b980256b5f003fa814/577DBDE19ABC09B4802568FC003A12F6?OpenDocument
SUMÁRIO
I - Não tendo a Re provado que a falta de cumprimento do contrato não procedeu de culpa sua, entrou em mora, tendo como consequencia a restituição da quantia recebida com juros, tendo a Autora perdido o interesse no cumprimento do contrato, ilação tirada pela Relação, que o Supremo tem de acatar, por materia de facto.