Contractor's liability for work defects is denied when not attributable to their fault or proven execution failure.

Case Number 085103
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Court of Justice dismissed the review of a lower court's decision regarding a construction contract under the 1969 Decree-Law. The contractor argued they were not liable for work defects absent proof of their fault or defective execution, while the owner sought payment based on presumed final acceptance. The court upheld the lower court's factual findings, ruling that the Supreme Court lacks jurisdiction to re-evaluate established facts and that liability requires proven fault.

Legislator headnote

Official

EMPREITADA DEFEITO DA OBRA CULPA PAGAMENTO PREÇO

Keywords

AI generated
construction contract liability work defects attribution presumed final acceptance contractor fault requirement Supreme Court jurisdiction

Cited Legislation

AI generated
Decreto-Lei n.º 48871, de 19 de Fevereiro de 1969

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[Nº CONVENCIONAL] JSTJ00024668

[Nº DO DOCUMENTO] SJ199404190851031

[PRIVACIDADE] 1

[PROCESSO NO TRIBUNAL RECURSO] 379/93

[TEXTO INTEGRAL] N

[TRIBUNAL RECURSO] T REL COIMBRA

[URL] https://www.dgsi.pt/jstj.nsf/954f0ce6ad9dd8b980256b5f003fa814/5427DF13CA1384E0802568FC003A8FD8?OpenDocument

SUMÁRIO

I - No contrato, de empreitada submetido ao regime do Decreto-Lei 48871, de 19 de Fevereiro de 1969, o dono da obra está obrigado a pagar o preço em dívida com a recepção definitiva daquela, ainda que a recepção seja apenas presumida por falta de realização da vistoria pedida pelo empreíteiro.

II - Este não é responsável por defeitos da obra no caso de eles não serem imputáveis a culpa dele e mesmo no de falta de prova de deficiente execução dos trabalhos.

III - A decisão da Relação, quanto à matéria de facto, está excluida da competência do Supremo.