Administrative appeal dismissed as untimely because filed over 30 days after the act's execution began.
Legislator summary
AI generatedThe Supreme Administrative Court rejected the agricultural company's contentious appeal, ruling it was filed more than 30 days after the commencement of the administrative act's execution. The appellant argued for a review of the 1979 structural planning order, but the court found the procedural deadline had expired. Consequently, the appeal was declared inadmissible due to its untimeliness, preventing any substantive examination of the agrarian reform measures.
Legislator headnote
OfficialACTO ADMINISTRATIVO COMEÇO DE EXECUÇÃO DO ACTO TEMPESTIVIDADE DO RECURSO REJEIÇÃO DO RECURSO CONTENCIOSO REFORMA AGRARIA
Keywords
AI generatedCited Legislation
AI generatedFull text
[AREA TEMATICA 1] DIR ADM CONT. [LEGISLACAO NACIONAL] L 77/77 DE 1977/09/29. DL 81/78 DE 1978/04/29 ART15 N5. [1ª PAG. DE PUBLICACAO DO ACORDAO] 2479 [ANO DA PUBLICACAO] 0 [APENDICE] DR [DATA DE ENTRADA] 03/20/1979 [DATA DO APENDICE] 08/22/1984 [Nº CONVENCIONAL] JSTA00008919 [Nº DO DOCUMENTO] SA119800606012919 [OBJECTO] DESP SE DA ESTRUTURAÇÃO AGRARIA DE 1979/01/19. [PAGINA] 0 [PRIVACIDADE] 01 [RECORRENTE] UCP AGRICOLA 1 DE MAIO SCARL [RECORRIDO 1] SE DA ESTRUTURAÇÃO AGRARIA E OUTRO [URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/EC5E246B3F7E36CC802568FC00387BEC?OpenDocument
SUMÁRIO
Sendo o recurso contencioso interposto mais de 30 dias apos o começo de execução do despacho impugnado, tem de concluir-se que e extemporaneo.*