Administrative court dismisses suspension of a municipal order due to lack of immediate damage and causal link.
Legislator summary
AI generatedThe court rejected the request to suspend a municipal council's order granting a 30-day deadline for legalizing earthwork operations. The applicant argued that the order caused immediate damage and a causal link existed, but the court found no such immediate harm or direct causation. Consequently, the suspension was denied because the legal requirements for suspending the order were not met.
Legislator headnote
OfficialSUSPENSÃO DE EFICÁCIA PREJUÍZO DE DIFÍCIL REPARAÇÃO DANO NEXO DE CAUSALIDADE LEGALIZAÇÃO DE OBRA CLANDESTINA
Keywords
AI generatedCited Legislation
AI generatedFull text
[AREA TEMATICA 1] DIR ADM CONT - MEIO PROC ACESSÓRIO SUSPEFIC. [LEGISLACAO NACIONAL] LPTA85 ART76 N1 A ART76 N2. [ANO DA PUBLICACAO] 97 [DATA DE ENTRADA] 01/30/1997 [Nº CONVENCIONAL] JSTA00048450 [Nº DO DOCUMENTO] SA119970213041686 [OBJECTO] SENT TAC PORTO. [PRIVACIDADE] 01 [RECORRENTE] SILVA , MANUEL [RECORRIDO 1] CM DE GUIMARÃES E OUTROS [URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/E8F4F645FD0F4F3A802568FC0039C3A3?OpenDocument
SUMÁRIO
O despacho de Vereador da Câmara Municipal que concede ao munícipe um prazo de 30 dias para legalizar obras de terraplanagem levadas a efeito num caminho alterando a topografia do local, não é susceptível de provocar danos imediatos na sua execução, susceptíveis de preencher o pressuposto da alínea a) do n. 1 do art. 76 da LPTA.