Contractor entitled to payment for materials upon public works contract rescission by contractor's option.
Legislator summary
AI generatedThe court allowed the contractor's claim for payment of construction materials following the rescission of a public works contract initiated by the contractor. The administration argued that the successor company should be summoned to interpret Article 67, but the court held this was unnecessary. The decision established that the contractor's right to compensation for materials is independent of the successor's involvement in the legal interpretation.
Legislator headnote
OfficialEMPREITADA DE OBRAS PUBLICAS RESCISÃO PELO EMPREITEIRO PAGAMENTO MATERIAIS DE CONSTRUÇÃO CHAMAMENTO A DEMANDA
Keywords
AI generatedCited Legislation
AI generatedFull text
[AREA TEMATICA 1] DIR ADM CONT - CONTRATO.
[AREA TEMATICA 2] DIR CIV - DIR RESP CIV.
[LEGISLACAO NACIONAL] D DE 1906/05/09 ART37 PARUNICO ART66 ART67 ART68 PAR1. CADM40 ART835 PAR2.
[ANO DA PUBLICACAO] 1957
[Nº CONVENCIONAL] JSTA00026628
[Nº DO DOCUMENTO] SA119550527004380
[Nº DO VOLUME] XXI
[OBJECTO] DESP MINOP DE 1954/06/03.
[PAGINA] 45
[PRIVACIDADE] 01
[RECORRENTE] PRETO , VIRGILIO
[RECORRIDO 1] MINOP - SOC DE EMPREITADAS MONIZ DA MAIA & VAZ GUEDES LDA
[REFERENCIA PUBLICACAO 1] RLJ N3138 ANO91 PAG334
[URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/E3655833DBF6D58C802568FC0037CB7F?OpenDocument
SUMÁRIO
No caso de rescisão do contrato de empreitada de obras publicas por opção do empreiteiro, este tem direito a que a Administração lhe pague todas as edificações, ferramentas, utensilios e materiais indispensaveis a obra, segundo o inventario oportunamente feito de harmonia com o artigo
66 das clausulas e condições gerais para empreitadas, aprovadas pelo Decreto de 9 de Maio de 1906.
A empresa a quem foi adjudicada a continuação da obra não tem de ser chamada ao recurso em que se trata de interpretar o preceito constante do paragrafo 1 do artigo 67 das aludidas clausulas.