Portuguese court dismisses claim for price revision in public works contract due to expired 180-day limitation period.

Case Number 024753
Court / Authority
Jurisdiction Portugal (PT)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Administrative Court dismissed the claimant's action seeking indemnity for price revision in a public works contract. The court held that such actions must be filed within 180 days of the breach, a period strictly reproduced in the applicable decrees. Since the claim was filed after this statutory deadline, the court ruled the action inadmissible regardless of the contract's execution phase.

Legislator headnote

Official

EMPREITADA DE OBRAS PUBLICAS PRAZO DE CADUCIDADE ACÇÃO DE INDEMNIZAÇÃO REVISÃO DE PREÇOS RESPONSABILIDADE CIVIL CONTRATUAL RESPONSABILIDADE CIVIL EXTRACONTRATUAL

Keywords

AI generated
public works contract price revision claim 180 day limitation contractual liability statutory time bar administrative procurement indemnity action

Cited Legislation

AI generated
DL 235 DE 1986/08/18 ART175
[LEGISLACAO NACIONAL] DL 235 DE 1986/08/18 ART175 ART222.
DL 235 DE 1986/08/18 ART222
II - As acções de indemnização por incumprimento do contrato de empreitada de obras publicas devem ser propostas no prazo de 180 dias previsto no art. 222 do Decreto-Lei n.
DL 48871 DE 1969/02/19 ART219
DL 48871 DE 1969/02/19 ART219.
CCIV66 ART474
CCIV66 ART474 ART498 N4 ART1207.
CCIV66 ART498
CCIV66 N4 ART1207
LPTA85 ART71 N1
[LEGISLACAO NACIONAL] DL 235 DE 1986/08/18 ART175 ART222. DL 48871 DE 1969/02/19 ART219. CCIV66 ART474 ART498 N4 ART1207. LPTA85 ART71 N1.

Cited Case Law

AI generated
AC STA DE 1986/10/20 IN BMJ N361 PAG341
[JURISPRUDENCIA NACIONAL] AC STA DE 1986/10/20 IN BMJ N361 PAG341.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

[AREA TEMATICA 1] DIR ADM CONT - CONTRATO.

[AREA TEMATICA 2] DIR CIV - DIR RESP CIV.

[LEGISLACAO NACIONAL] DL 235 DE 1986/08/18 ART175 ART222. DL 48871 DE 1969/02/19 ART219. CCIV66 ART474 ART498 N4 ART1207. LPTA85 ART71 N1.

[JURISPRUDENCIA NACIONAL] AC STA DE 1986/10/20 IN BMJ N361 PAG341.

[1ª PAG. DE PUBLICACAO DO ACORDAO] 3209

[ANO DA PUBLICACAO] 88

[APENDICE] DR

[DATA DE ENTRADA] 02/20/1987

[DATA DO APENDICE] 01/20/1994

[Nº CONVENCIONAL] JSTA00029193

[Nº DO DOCUMENTO] SA119880614024753

[OBJECTO] SENT TAC COIMBRA.

[PRIVACIDADE] 1

[RECORRENTE] JOSE , ANTONIO

[RECORRIDO 1] MUNICIPIO DE GOIS

[REFERENCIA A DOUTRINA] SERVULO CORREIA LEGALIDADE E AUTONOMIA CONTRATUAL NOS CONTRATOS ADMINISTRATIVOS A1987 PAG786.

[URL] https://www.dgsi.pt/jsta.nsf/35fbbbf22e1bb1e680256f8e003ea931/A3881FCAF4D89EC0802568FC0037DA7E?OpenDocument

SUMÁRIO

I - As decisões ou deliberações sobre revisão de preço de empreitadas de obras publicas respeitam a materia do contrato e inserem-se na sua fase de execução.

II - As acções de indemnização por incumprimento do contrato de empreitada de obras publicas devem ser propostas no prazo de 180 dias previsto no art. 222 do Decreto-Lei n. 235/86, de 18 de Agosto, que reproduz o art. 219 do Decreto-lei n. 48871, de 19 de Fevereiro de 1969, que o antecedeu.